Budget 2027/27 - Process

Approved Committee 1 paper

AI summaryArun District Council's Policy and Resources Committee approved the budget process for 2027/28, with service committee reviews from September 2026 and Special Council sign-off targeted for 24 February 2027.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedProcess for setting 2027/28 budget agreed
MoneyNot stated
What happens nextService committees from September 2026Service committees consult 3 to 24 September 2026
Who it affectsAll council committees and MembersSets the timetable for 2027/28 budget setting

What was decided

The Committee approved the budget process for 2027/28 as set out in the report. Report 9.1

Ad hoc briefings to all Members will support the process as needed. Report 3.1

Why

The Council is under a statutory duty to set a balanced budget and must follow Part 6, Section 2 of the Constitution and the Local Government Finance Act 1992. Report 9.2, 9.3, 1.1

The council continues to face cost pressures and increasing service demands after the Fair Funding Review, making a clear budget timetable necessary. Report 4.2, 4.3

What happens next

Four service committees will receive budget consultation reports between 3 and 24 September 2026. Report P12, 4.7

The Medium Term Financial Forecast will go to the Policy and Resources Committee on 10 December 2026 or earlier. Report P13

Service committee budget reports run from 14 January to 11 February 2027, with Special Council approving the budget and council tax on 24 February 2027. Report P14, P15, P53, P54

Options considered

  • Chosen: Approve the 2027/28 budget process as outlined. Process must comply with the Constitution and statutory framework Report 7.1, 9.3
  • Rejected: No other options are available. The report records that no other options are available Report 6.1

Implications

  • Legal: The Council must set a balanced budget under the Local Government Finance Act 1992, with the process following Part 6, Section 2 of the Constitution. No direct legal implications arise from approving the process itself. Report 9.2, 9.3, 9.4
  • Risk: Main risks are missing the statutory deadline for setting the budget and council tax, and not following statutory guidance and the Constitution. Existing financial controls are said to mitigate these. Report 8.1, P24, 8.2
  • Financial: Members are asked to minimise any growth bids and meet them from resource switching where possible within the overall corporate budget. Report 4.4, 4.5
  • Other: The Director of Resources notes that budget proposals may need to be assessed in the context of Local Government Reorganisation. Report 7.2
  • Equalities: Each committee will be expected to have regard to the Public Sector Equality duty when making recommendations. Report 13.1

Who and where

  • All Members of Arun District Council, who will receive updates and ad hoc briefings Report 3.1, 4.3
  • The four service committees that will consult on and scrutinise budget proposals Report P12, P14, 5.1
  • Council tax payers in the Arun district, who are set by Special Council on 24 February 2027 Report P15, P54

Timeline

  • 02 July 2026: Policy and Resources Committee approves the 2027/28 budget process Report P48
  • 03 September 2026: Planning Policy Committee budget consultation report Report P12
  • 10 September 2026: Economy Committee budget consultation report Report P12
  • 17 September 2026: Environment Committee budget consultation report Report P12
  • 24 September 2026: Housing and Wellbeing Committee budget consultation report Report P12
  • 10 December 2026 (or earlier if possible): Medium Term Financial Forecast to Policy and Finance Committee Report P13
  • 14 January 2027: Housing and Wellbeing Committee budget report Report P14
  • 19 January 2027: Environment Committee budget report Report P14
  • 21 January 2027: Planning Policy Committee budget report Report P14
  • 28 January 2027: Economy Committee budget report Report P14
  • 11 February 2027: Policy and Resources Committee overall budget and council tax recommendation Report P14, P53
  • 24 February 2027: Special Council sets budget, council tax and housing rents Report P15, P54

Plain English for the jargon

  • Medium Term Financial Forecast (MTFF): A multi-year projection of the council's spending and income used to plan the budget.
  • Section 151 Officer: The statutory chief finance officer responsible for the proper administration of the council's financial affairs.
  • Balanced budget: A budget where projected income equals or exceeds planned spending, as required by law.
  • Fair Funding Review: A central government review of how funding is allocated between local authorities.
  • Resource switching: Reallocating existing budget from one area to another rather than adding new spending.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item92

Resolved

RESOLVED To approve the budget process for 2027/28 as outlined in the report.
Word for word from the decision Arun published for this meeting. Source: democracy.arun.gov.uk

Follow this further

Built from Arun's papers

What the report saysPro

Report to Policy and Resources Committee

Purpose of report

1.1The purpose of this report is to inform Members of the budget process for 2027/28 as required by Part 6, Section 2 of the Council’s Constitution.

2. RECOMMENDATIONS 2. 2.1. The Committee is recommended to approve the budget process for 2027/28 as outlined in the report.

Executive summary

3.1The report provides a summary of the budget process for 2027/28 for Members’ consideration and approval. The budget process will be supported by ad hoc briefings to all Members as and when necessary.

4. DETAIL

4.1The budget for 2026/27 was the fifth to be completed under the committee system form of governance. The relevant budgets were considered by each service committee before the full budget was reviewed by this Committee on 12 February 2026 and subsequently approved by Special Council on 25 February 2026.

4.2The financial impact on the council of the Fair Funding Review undertaken by central government was reported to this Committee on 12 February 2026. Whilst the outcome was not as severe as first feared, members will recall that despite this, the council continues to face cost pressures and increasing demands on service delivery.

4.3Members will continue to be provided with high-level updates during the financial year on the council’s Medium Term Financial Forecast, including a more detailed forecast in the Autumn.

4.4It is accepted that within the existing resource constraints, there is the requirement for some resource switching to enable the council’s priorities to be progressed and to meet new statutory requirements. Committees will be consulted on the budget, taking account of the medium-term requirement to achieve a balanced budget. Any growth should be minimised and met from resource switching where possible.

4.5The budget guidelines issued will run parallel with any initiatives that are being developed. Any bids for growth will be assessed for affordability within the overall corporate budget parameters.

4.6At the then Policy & Finance Committee of 08 July 2025, members requested that they be given an opportunity to develop budget proposals prior to the service committee meeting cycle in January and February 2026. As a result, the Director of Resources and Section 151 Officer developed a process that enabled this to happen. It is intended to operate this process again for 2027/28 and further details will be issued around September 2026.

4.7The key dates for the Budget 2027/28 process are summarised below:

Budget Consultation Reports Date Planning Policy Committee 3 September 2026 Economy Committee 10 September 2026 Environment Committee 17 September 2026 Housing and Wellbeing Committee 24 September 2026

Medium Term Financial Forecast General 10 December 2026 (or earlier if Fund (Policy and Finance Committee) possible)

Budget Reports Date Housing and Wellbeing Committee 14 January 2027 Environment Committee 19 January 2027 Planning Policy Committee 21 January 2027 Economy Committee 28 January 2027 Policy and Resources Committee 11 February 2027

Special Council 24 February 2027 5. CONSULTATION

5.1No consultation has been undertaken with external bodies. Service Committees will be consulted on the process during the next cycle of meetings.

6. OPTIONS / ALTERNATIVES CONSIDERED

6.1No other options are available.

7. COMMENTS BY THE DIRECTOR OF RESOURCES & SECTION 151 OFFICER

7.1The budget will form the main reference point for financial decisions made in 2027/28 and the process must comply with the Constitution.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Budget 2027/27: ProcessReport 268 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 27 attended
DH
Dawn HuddOfficer, expected
SG
Sukdave GhumanOfficer, expected
NC
Neil CrowtherOfficer, expected
JR
Joe Russell-WellsOfficer, expected
RT
Richard TomkinsonOfficer, expected
WP
William PageOfficer, expected
JC
Joe CurreyOfficer, expected
AB
Antony BadenOfficer, expected
AC
Angela CurryOfficer, expected
KP
Karen PearceOfficer, expected
KR
Karl RobertsOfficer, expected
NS
Nat SladeOfficer, expected

All 27 on the meeting page

On this subject at Arun

Search all
  1. Budget 2027/27 - ProcessThis decision
  2. Budget 2026/27 - ProcessApproved
  3. Budget Process - 2025/26Approved
  4. Budget 2024-2025 - ProcessApproved
  5. Budget 2023/2024 - ProcessNoted
  6. Budget Process 2023-2024Approved

More from Arun Policy and Resources Committee

All decisions
MeetingDecisionOutcome
2 Jul 2026 Start TimesRESOLVED That its start times for meetings for this new Municipal Year be 6.00 pm. Decided Open
2 Jul 2026 Adoption of the Resolution FrameworkRESOLVED - To (1) Approve the adoption of the Resolution Framework as the Council’s primary approach for managing con... Approved Open
12 Mar 2026 Pay Policy Statement 2026RESOLVED That the contents of the /27 as set out in Appendix 1 be noted. The Committee then RECOMMEND TO FULL COUNCIL... Noted Open
12 Mar 2026 Q3 Performance Report for the Key Performance Indicators (KPIs) which form part of the Council's Vision 2022-2026RESOLVED – That it (1) Approves that we no longer collect information for KPI CP36, the number of new homes completed... Approved Open
12 Feb 2026 Committee Revenue and Capital Budgets 2026/27RESOLVED – That (1) It agrees the 2026/27 Revenue Budget as set out ... view the full minutes text for item 551. Agreed Open