RESOLVED that virement required within the Housing Revenue Account, as outlined in the Cabinet report, be endorsed in accordance with Financial Regulations; Minute No. CA. Cabinet – 30 th November, 2017 Capital Strategy Update & Proposed Capital Programme 2017/18– 2021/22 RESOLVED that the changes to the strategies and revised capital programme covering 2017/18 – 2019/20, as outlined in the Cabinet report, be approved. (During consideration of the recommendations to Council, Councillors Helen-Ann Smith and Lee Anderson left the room at 7.56 p.m. and 8.00 p.m. and returned to the meeting at 8.00 p.m. and 8.02 p.m. respectively.)
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
This report sets out the details of income and expenditure incurred to August 2017 by the General Fund and Housing Revenue Account, compares it to the approved budgets and explains the significant variances.
The report also recommends amendments to the 2017/18 budget however all changes are fully funded from a specific reserve or are agreed savings.
Recommendation(s) Members are requested:
(i) Note the budget monitoring to August 2017. (ii) Approve the movements from earmarked reserves to fund specific projects as outlined in section 2.3. This has no impact on the position of the General Fund or Housing Revenue Account (HRA). (iii) Approve the virement required within the Housing Revenue Account (above the limit permitted within Financial Regulations) and recommend to Council in accordance with Financial Regulations.
Reasons For Recommendation(s)
To report to those charged with Governance the financial position to August 2017 and comply with the Council’s Financial Regulations.
Alternative Options Considered (With Reasons Why Not Adopted)
The changes to the 2017/18 budget are required to facilitate the progression of specific projects however these are funded from specific earmarked reserves designated for this purpose. Not to approve these changes would prevent some projects from progressing or require them to be financed from the General Fund balance which is not recommended.
Detailed Information
1. Budget Monitoring to August 2017
a. General Fund to August 2017
The table below shows the overall summary for the General Fund by Directorate, excluding capital financing costs and internal recharges.
Actuals Budget Variance (£000) (£000) (£000) Chief Executive Officer 292 200 (92) Legal and Governance 637 652 15 Resources and Business Transformation 1,943 2,131 188 Place and Communities 4,916 4,866 (50) Housing and Assets 1,037 1,117 80 Total 8,826 8,966 140
The table below shows a subjective analysis of the net expenditure for the General Fund, excluding capital financing costs and internal recharges.
Actuals Budget Variance (£000) (£000) (£000) Employee Expenditure 8,213 8,181 (32) Premises Expenditure 785 781 (4) Transport Related Expenditure 982 1,045 63 Supplies and Services 2,635 2,863 228 Transfer Payments 154 106 (49) Income (3,943) (4,010) (66) Total 8,826 8,966 140
Net Expenditure to August 2017, excluding Capital and Internal Recharges, at £8.826m is £140k under spent. The key variances of note are detailed below, this does not include offsetting variances or those that are not material:
Employee Expenditure
Expenditure at £8.213m is £32k (0.39%) higher than budget.
Indirect Pay is £29k under spent and Direct Pay is £61k over budget to the end of August. Significant variances include:
£103k greater than budget in the CEO Directorate which relates to savings expected from Service Reviews that have not yet been finalised and accounted for in individual service budgets. Savings have been identified from reviews but there has been some slippage in respect of implementation. £16k over spend in Planning due to £20k of Agency costs that relate to 2016/17 that were not accrued for. Underspends due to vacancies of £21k in Democratic Services, £18k in Community Protection and £25k in Selective Licensing.
Premises Expenditure
At £785k, premises expenditure is only £4k (0.43%) overspent, there are no material variances of note.
Transport Expenditure
Transport Related Expenditure, at £982k is £63k (6.01%) under budget. The main variance being an under spend for fuel due to reduced mileage to August.
Supplies and Services Expenditure
Supplies and Services at £2.635m are £228k (7.96%) less than budget. The main variances consist of the following:
Place and Communities is £206k under spent with the main variances being:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Local Government Reorganisation - UpdateRESOLVED that the information provided, and the ongoing work being undertaken to support the LGR transition programme...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.