Resolved
RESOLVED that the proposed Capital Programme adjustments, as set out in this report, be approved.
Council approved this item on Thursday 7 July 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the proposed Capital Programme adjustments, as set out in this report, be approved.
To seek Council approval for one new Scheme to be added to the 2022/23 Capital Programme and to approve an increase in funding for an existing Scheme.
Recommendation(s)
Council is recommended to approve the proposed Capital Programme adjustments as set out in this report.
Reasons for Recommendation(s)
Lindley’s Windmill works – to meet grant funding condition obligations. Urban Road Offices’ works – to meet the cost of additional identified works and materials cost inflation.
Alternative Options Considered (with reasons why not adopted)
None. As a condition of former grants received, the Council has an obligation to address the repair issues at Lindley’s Windmill. The additional costs for the works at Urban Road Council Offices only became evident on more detailed inspection of the building once scaffolding was in situ. In addition, the level of inflation in the economy over recent months has inevitably resulted in materials cost increases. Detailed Information
1. New Scheme – Lindley’s Windmill Roof - 36 Prospect Place, Sutton-in-Ashfield NG17 1AD.
The Council owns a heritage asset in the form of a stone mill base. Grants and gifts have been received over time in order to ensure it is protected. As a result of accepting the grants the Council has an ongoing legacy to ensure the structure is wind and weather-proof.
In recent years the roof has leaked and allowed water ingress to the walls and interior and this has compromised the use of the building.
The cost of replacing a flat roof with a conical structure is £55,000. This can, in part, be offset by utilising an historic section 106 agreement funding balance of £5,700. It is proposed that the balance of the funding requirement (£49,300) is met from the Asset Repair and Renewal Reserve.
2. Scheme cost increase - Council Offices, Urban Road – External Health and Safety Works
Members will be aware that in 2021/22 Council approval was given to undertake essential Health and Safety works on the Council’s Urban Road Offices and a budget of £216k was included in the Capital Programme.
It has been necessary to instruct additional works following commencement on site, where further remedial works were identified once full access to the roof areas was possible to enable detailed inspection (including after timbers/tiles being removed exposing other necessary repair works), and to account for variations at the outset after tender including the decision to amend the colour of soffits and fascias, and the inclusion of painting the aluminium entrance area to match the colour scheme. Variations include:
- Window seals - replace all rubber seals to timber windows with silicone - Additional Asbestos samples - Scaffold alteration - design variation due to roof being considered unsuitable to support operatives (too much flex in the roof) - Soffit colour change - Wholesale replacement of tiles necessary to the tank house (highest point which had been storm damaged previously) - Dry verges replacements (necessary as the original verges were nailed to the tiles which was considered unsuitable and insufficient to hold the tiles down) - Aluminium decorations (paint red aluminium in grey to match the window colour) - Materials uplift; delays to contract formalisation during which market rates had increased - Welfare – necessity to provide - Ridge tile replacement (including scaffold alterations) as a consequence of the tiles being damaged/end of life
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Proposed Amendments to the Capital Programme for 2022/23Report | 239 KB | DownloadRead as text |
Follow Council at Ashfield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Jul 2026 | Local Government Reorganisation - UpdateRESOLVED that the information provided, and the ongoing work being undertaken to support the LGR transition programme... | Noted | Open |
| 27 Jul 2026 | Recommendations from the Cabinet and the Council's CommitteesRESOLVED that a) being satisfied that a land exchange is in the best interests of the charitable trust, Council appro... | Approved | Open |
| 27 Jul 2026 | Notice of Motion 1RESOLVED that a) the Council asks the Leader of the Council and Chief Executive to write to Government calling for a ... | Decided | Open |
| 27 Jul 2026 | Notice of Motion 2RESOLVED that this Council agrees to: a) ask Cabinet to bring forward a simple Ashfield Pub Protection Plan; b) revie... | Agreed | Open |
| 18 May 2026 | Election of Chairman of the CouncilRESOLVED that Councillor Dale Grounds be elected Chairman of the Council until the next Annual Meeting. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.