Ashfield District Council
Cabinet, Monday 27 July 2026 at 10.00am

Corporate Plan Year End Delivery 2025/26

Noted Executive 1 paper

AI summaryAshfield Cabinet notes 2025/26 year-end performance, with 83% of corporate scorecard measures on or near target, and plans to extend the Corporate Plan to 31 March 2028 ahead of the council ceasing to exist under local government reorganisation.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNoted83% of delivery measures on or near target, 80% improved on prior year
MoneyNo direct financial implicationsPer finance officer; report is a performance review
What happens nextPropose extending Corporate Plan to March 2028A 'Final Corporate Plan' to run until LGR Vesting Day on 1 April 2028
Who it affectsAshfield residents, tenants, staff and partnersCouncil will wind down before unitary authority takes over from 1 April 2028

What was decided

Cabinet received and noted the levels of delivery achieved against the Corporate Plan Priorities, as set out in the report. Report P3

Cabinet also noted the levels of performance against the Corporate Scorecard as of March 2026, covering the April 2025 to March 2026 period. Report P4, P16

Why

The Council's ambitions for 2023 to 2027 are set out in revised Corporate Priorities developed by Cabinet and monitored through the Performance and Strategic Planning Framework. Report P6, P8

Local Government Reorganisation for Nottinghamshire is expected, with a decision due by 16 July 2026 and Vesting Day set for 1 April 2028, when the council will cease to exist. Report P10, P62, P63

What happens next

A forthcoming proposal will be brought to Cabinet to extend the Corporate Plan period to 31 March 2028 in the form of a 'Final Corporate Plan', covering delivery of remaining priorities and a safe, legal wind-down. Report P10, P63

The Council will continue to monitor performance and deliver against its Corporate Priorities up to Vesting Day, with a legacy review to be presented covering the Council's achievements. Report P10

An alternative considered, preparing a new Corporate Plan when the existing period ends in March 2027, was rejected as less appropriate given the LGR timetable. Report P11

The money

  • £6.34m Additional social value delivered through the Leisure Operating Contract between April 2025 and March 2026 Report P19
  • £1.2 million Total external funding secured for five PlayZones across the District Report P20
  • £1 million Council grant funding committed to Selston High School to support redevelopment of leisure facilities Report P20
  • £220,000 Funding secured from the East Midlands Combined County Authority for health inequality initiatives in 2025/26 Report P21
  • £12 million Planned investment in green spaces and public realm under the updated Public Open Space Investment Plan Report P36
  • £560,000 Efficiencies identified and delivered through the Council's Service Review Programme Report P45
  • £67,000 Situational Crime Prevention funding from the Office of the Police and Crime Commissioner for Sutton-in-Ashfield Report P43
  • £220k Total of 29 Enterprise Development Grants awarded between April and June 2025 Report P29

Options considered

  • Chosen: Extend the existing Corporate Plan by 12 months in the form of a 'Final Corporate Plan' to 31 March 2028. More appropriate given the council will cease to exist from 1 April 2028 under LGR, supporting delivery of remaining priorities and a safe transition Report P11, P10, P63
  • Rejected: Prepare a new Corporate Plan once the existing four-year period ends in March 2027. Deemed less appropriate because Ashfield District Council will cease to exist from 1 April 2028 under LGR Report P11

Implications

  • Other: Local Government Reorganisation for Nottinghamshire: decision expected by 16 July 2026, with Vesting Day on 1 April 2028; the council will lead implementation work and ensure safe, legal wind-down of operations and seamless transition of powers, staff and assets to the new unitary authority. Report P10, P62, P63
  • Financial: No direct financial implications from this report; the Corporate Plan and Delivery Plan are aligned to the Medium-Term Financial Strategy and financial sustainability. Report P56
  • Legal: Corporate Priorities and strategic plans have been developed in consideration of current and forthcoming legislative requirements. Report P55
  • Equalities: No direct implications on equality and diversity as a consequence of the proposals and recommendations. Report P61
  • Climate: Cleaner and Greener priority reduces scope 1 and 2 emissions by 295 tonnes CO2 in 2025/26, around 800 tonnes since 2021/26 (29% reduction); biofuel fleet introduction planned to reduce carbon footprint by approximately 1000 tonnes CO2. Report P34, P35
  • Risk: Identified risks include lack of prioritisation without a Corporate Plan and inability to deliver priorities if performance is poor; mitigated by annual review and regular performance monitoring. Report P57
  • Staffing: Human Resources shared service transferred to Ashfield District Council as host from 1 December 2025; staff turnover reduced from 3.58% to 2.19%; sickness absence at 9.93 days per FTE, above the 9.5 target. Report P49, P51

Who and where

  • Residents of Ashfield District Report P10, P13
  • Council staff, ahead of Local Government Reorganisation transition Report P10, P49, P63
  • Council house tenants Report P19, P22, P25
  • Local businesses and employers in Ashfield Report P27, P29
  • Community and voluntary sector partners Report P21, P28, P43
  • Users of leisure centres and parks Report P19, P34, P36

Timeline

  • April 2025 to March 2026: Performance reporting period covered by the year-end report Report P1, P16
  • 16 July 2026: Government decision on preferred Local Government Reorganisation model for Nottinghamshire expected Report P10, P62
  • 27 July 2026: Cabinet meeting at which the year-end delivery report was noted
  • Summer 2026: Bronze Workforce Accreditation application through Thrive anticipated to be submitted Report P49
  • 30 July 2026: End of 6-week consultation on Main Modifications to the Ashfield Local Plan 2023 to 2040 Report P32
  • September 2026: Launch of the revised Be Healthy, Be Happy Strategy for Ashfield Report P20, P46
  • 31 March 2028: Proposed end date of the 'Final Corporate Plan' Report P10, P63
  • 1 April 2028: Local Government Reorganisation Vesting Day; Ashfield District Council will cease to exist Report P10, P63

Plain English for the jargon

  • Local Government Reorganisation (LGR): Government-led restructuring of councils; for Nottinghamshire, expected to replace existing district and borough councils with a new unitary authority.
  • Vesting Day: The date on which a new local authority comes into existence and existing councils are dissolved, here set for 1 April 2028.
  • Corporate Scorecard: The Council's performance measurement tool, split into Delivery and Living in Ashfield sections, aligned to the Corporate Plan.
  • ADMC: Automated Distribution and Manufacturing Centre, a regeneration project in Ashfield.
  • EPC: Energy Performance Certificate, a rating of a property's energy efficiency.
  • MASH: Multi-Agency Safeguarding Hub, a partnership for safeguarding vulnerable adults and children.
  • UKSPF: UK Shared Prosperity Fund, a central government funding programme for local growth.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.12

Resolved

RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be received and noted; b) the levels of performance achieved against the Corporate Scorecard as of March 2026, as presented, be also noted. Reason: The Council’s ambitions for 2023-27 are clearly identified in a set of revised and updated Corporate Priorities which are presented in the Corporate Plan. These have been developed by Cabinet.
Word for word from the decision Ashfield published for this meeting. Source: democracy.ashfield.gov.uk

Follow this further

Built from Ashfield's papers

What the report saysPro

Report to Cabinet

Purpose of report

This report presents to Cabinet progress updates regarding delivery of the Corporate Plan 2023-2027 and the April 2025 to March 2026 performance position against the associated Corporate Performance Scorecard.

Recommendation(s)

1. For Cabinet to consider and proactively review the levels of delivery achieved against the Corporate Plan Priorities.

2. For Cabinet to consider and proactively review the levels of performance achieved against the Corporate Scorecard as of March 2026.

Reasons for Recommendation(s)

The Council’s ambitions for 2023-27 are clearly identified in a set of revised and updated Corporate Priorities which are presented in the Corporate Plan. These have been developed by Cabinet.

The Corporate Plan sits above a wider strategic context which includes the Corporate Project Management Framework, Corporate Performance Indicators and a range of strategic documents relating to the Council and its services. The Corporate Plan aligns to the Council’s overarching Strategic Direction.

Our priorities have been translated and cascaded into specific projects and initiatives, the successful delivery of which is being monitored through our Performance and Strategic Planning Framework, into the Corporate Plan Delivery Plan and Operational Service Plans to facilitate focussed delivery.

The Council’s Performance Management Framework continues to reflect the Council’s vision to be ‘Great’ across all services, enhancing our strong performance management culture aligned to Local Government Association (LGA) Standards, particularly focussed on ensuring best value through insight driven understanding of performance and ongoing development of the Council’s Power BI ‘Knowledge hub’ - our single repository and standardised access point providing timely and open data to officers and leaders across the Council. The enhanced framework also clearly outlines the key responsibilities of councillors and officers working together to deliver our vision, including the role of Cabinet to lead the achievement of value for money through the delivery of services and the Council’s objectives.

It is also important to note that, whilst the government’s decision on a preferred model for Local Government Reorganisation (LGR) for Nottinghamshire is awaited (expected by 16 July 2026), it is important that the Council continues to monitor performance and deliver against its Corporate Priorities. Ashfield District Council, in common with the other Nottinghamshire Districts and Boroughs are very proud of and fully committed to the vast range of services delivered effectively and efficiently at a localised level based on identified community needs. Up to LGR Vesting Day, 1 April 2028, the Council will remain focussed on delivering great services for our residents and communities. A forthcoming proposal to Cabinet will be to extend the Corporate Plan period to 31 March 2028, in the shape of a ‘Final Corporate Plan’ ensuring both the delivery of the Council’s remaining priorities up to Vesting Day, whilst also ensuring a "safe and legal" winding-down of operations and seamless transition of powers, staff, and assets to the new unitary authority. In recognition of Ashfield District Council’s legacy, a full review will be undertaken and presented of the Council’s achievements and delivery of our priorities. Alternative Options Considered

To prepare a new Corporate Plan once the existing four-year period ends in March 2027 – through Local Government Reorganisation Ashfield District Council will cease to exist from 1 April 2028, it is therefore deemed more appropriate to extend the existing Corporate Plan period by 12 months in the form of a Final Corporate Plan.

Detailed Information

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Corporate Plan Year End Delivery 2025/26Report 284 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 21 attended
SD
Councillor Samantha DeakinCommittee Member, present
PG
Councillor Paul GraftonCommittee Member, apologies
VH
Councillor Vicki HeslopCommittee Member, present
CH
Councillor Christopher HuskinsonCommittee Member, present
RM
Councillor Rachel MaddenCommittee Member, present
AM
Councillor Andy MeakinCommittee Member, present
MR
Councillor Matthew RelfCommittee Member, present
HS
Councillor Helen-Ann SmithCommittee Member, present
JW
Councillor John WilmottCommittee Member, present
JZ
Councillor Jason ZadroznyChairman, present
JB
John BennettOfficer, in attendance
LC
Lynn CainOfficer, in attendance

All 21 on the meeting page

On this subject at Ashfield

Search all
  1. Corporate Plan Year End Delivery 2025/26This decision
  2. Corporate Plan Delivery Update - Economic Growth and Place and Innovate and ImproveNoted
  3. Corporate Plan Delivery - Quarter 2 2025/26Noted
  4. Corporate Plan RefreshApproved
  5. Corporate Plan Delivery - Year End 2024/25Noted
  6. Corporate Plan Delivery - Year End 2024/2025Noted

More from Ashfield Cabinet

All decisions
MeetingDecisionOutcome
27 Jul 2026 Local Government Reorganisation (Verbal Update and Q/A Session)RESOLVED that a) the information provided and the ongoing work being undertaken to support the transition programme, ... Noted Open
27 Jul 2026 Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas... Noted Open
27 Jul 2026 Update - Charitable Trust Issues at Lord Francis Park (Kirkby-in-Ashfield), Hucknall Leisure Centre and Titchfield Park (Hucknall)RESOLVED that a) the current position relating to Charitable Trust Issues at Lord Francis Park (Kirkby-In-Ashfield), ... Noted Open
27 Jul 2026 Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ... Noted Open
27 Jul 2026 Be Health, Be Happy Strategy 2026 - 2035RESOLVED that a) the successes of the 2021-25 Strategy, be received and noted; b) the revised Be Healthy, Be Happy St... Noted Open