Item135
Resolved
That (i) the changes approved through the Project Adjustment Request (PAR) to MHCLG for the Ashford International Studios Development, Newtown Works project to enable delivery of the Levelling Up funding within the timescales, be noted. (ii) it be noted that the college educational facility part funding of £6.2m is now to be met by Ashford International Development Company before profits are distributed in line with the Shareholders Agreement. (iii) the Solicitor to the Council and Monitoring Officer be authorised to negotiate, finalise and complete all necessary legal agreements and other documents to give effect to the above.
Word for word from the decision Ashford published for this meeting.
Source: ashford.moderngov.co.uk