Item27
Resolved
RESOLVED that Cabinet :- 1. noted the final financial position on the 2020/21 Capital Programme; 2. approved scheme slippage totalling £23.9M and scheme re-phasing totalling £3.9M (paragraphs 3.5, 3.6 and Appendix B refer); 3. noted the total net increase in scheme costs in 2020/21 of £0.3M (paragraph 3.7 and Appendix B refer); and 4. receive an updated 2021/22 indicative Capital Programme position (as part of the Quarter 1 monitoring report).
Word for word from the decision Barnsley published for this meeting.
Source: barnsleymbc.moderngov.co.uk