Resolved
RESOLVED that: Members of the Development Control Committee notes the outcomes of the appeal decisions and the reasons given for those decisions.
Development Control Committee decided this item on Wednesday 2 December 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that: Members of the Development Control Committee notes the outcomes of the appeal decisions and the reasons given for those decisions.
1 This Report
1.1Attached as Appendix A and B is a summary analysis of the appeal decisions received from the 01.05.2015 to 31.10.2015 This highlights some of the issues drawn out by the Inspectors in arriving at their decision and which should be taken into account when future decisions are made, but is by no means a summary of all the issues referred to in the Inspectors’ decision notices.
1.2Those decisions of particular note have been more fully detailed in Appendix A. A full copy of the decision letters can be requested from the contact above.
1.3Any comments or suggestions on this quarterly report are welcomed from Members. Members may want to note that the next Appeal Summary Report will be reported to the 10 February 2015 Development Control Committee meeting.
1.4Any costs decisions are reported with each planning appeal. The agreed amount is finalised sometime after the appeal decision is issued. Between 01.05.2015 and 31.10.2015 there has been 2 settlement to report to Members.
1.5The first related to the partial award of costs against the council in the Caesars Way, Whitchurch appeal related to planning application 13/01522/OUT proposing development of the site for 36 dwellings. The outcome of the appeal being allowed has previously been reported to Members of the Development Control Committee. The partial award of costs related only to the refusal of the planning application on grounds of prematurity ahead of the preparation of the Whitchurch Neighbourhood Plan. The final costs settlement was £20,000.
1 of 11 1.6 The second related to the partial award of costs against the council in the Worting Farm appeal related to planning application 13/02553/FUL proposing the development of that site for 70 dwellings. The outcome of the appeal being allowed has also previously been reported to Members of the Development Control Committee. The partial award of costs related only to the refusal of the planning application in relation to highway safety impact. The final costs settlement was for £53,750
It is recommended that:
2.1Members of the Development Control Committee note the outcomes of the appeal decisions and the reasons given for those decisions.
2 of 11 PRIORITIES, IMPACTS AND RISKS
Contribution to Council Priorities This report accords with the council’s Budget and Policy Framework and directly supports the Council Plan priority/priorities of planning policies that safeguard local distinctiveness, protecting our environment.
MAIN CONSIDERATIONS
3 Corporate Implications
3.1.1 There are no financial implications from this report other than the reporting of the cost settlements set out above.
3.2Risk Issues
3.2.1 There are no risk issues from this report.
3.3HR Issues
3.3.1 There are no HR issues from this report.
3.4Equalities
3.4.1 There are no equalities issues from this report.
3.5.1 There are no legal implications from this report.
3.6Any Other Implications
3.6.1 There are no other implications from this report.
3 of 11 APPENDIX A
14/07/2015 Bullington Cross 13/00046/FUL Withdrawn
Decision Level : Committee
Recommendation : Refuse
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appeal Decisions Quarterly Summary ReportDecisions | 298 KB | DownloadRead as text |
Follow Development Control Committee at Basingstoke and Deane and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | Applications for planning permission and public participation thereonRESOLVED that : the application be APPROVED subject to the applicant entering into a Section 106 legal agreement unde... | Approved | Open |
| 9 Sep 2026 | Quarterly Planning Appeals ReportRESOLVED that: Members of the Development Control Committee note the outcomes of the appeal decisions and the reasons... | Noted | Open |
| 12 Aug 2026 | Applications for planning permission and public participation thereonRESOLVED that : the application be REFUSED for the following reason: Reason for Refusal 1 The proposed development by... | Refused | Open |
| 8 Jul 2026 | Applications for planning permission and public participation thereonRESOLVED that : the application be APPROVED subject to: · the completion of a Section 106 legal agreement under the T... | Approved | Open |
| 10 Jun 2026 | Applications for planning permission and public participation thereonRESOLVED that : the application be APPROVED subject to: · the completion of a Section 106 legal agreement under the T... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.