That Cabinet: 1) Approve moving to the second stage of the model for use of the £1m budget towards the purchase of ESP’s in 2016/17 according to the terms set out in 3.1.4 (ii) in the report 2) Delegate authority to the Executive Director of Borough Services, in consultation with the Executive Director for Finance and Resources, to finalise the revised detailed terms and conditions with SHA accordingly 3) Delegate authority to the Head of Law and Governance to enter into an amendment to the original agreement to reflect the changes agreed as referred to in 2 above. 4) Delegate authority to the Executive Director of Borough Services, in consultation with the Executive Director for Finance and Resources and Portfolio Holder for Housing and Regeneration, to approve any subsequent amendment to this ESP programme agreement with SHA so long that it • remains within the approved total budget • optimises uses of the budget in order to best meet housing and homelessness needs, and • ensures the Council receives a proportionate return on its investment Reasons for decision: To ensure the ESP programme can be delivered, homelessness is prevented and unnecessary use of B&B avoided.
Word for word from the decision Basingstoke and Deane published for this meeting.Source: democracy.basingstoke.gov.uk
1.1The purpose of this report is to recommend Cabinet approve moving straight to the second stage of the Existing Satisfactory Property Programme (ESP) already approved by Cabinet in a report considered at its meeting in December 2015.
1.2The ESP programme which enables the provision of grant funding to Sentinel Housing Association (SHA) to acquire properties for use as temporary accommodation to deal with homelessness. In December 2015 Cabinet recommended a sum of £1m be earmarked within the annual budget report (approved by Council in February 2016) for acquiring ESPs. The model approved at the time assumed a total of 15 properties would be acquired at £50,000 grant per unit. The remaining budget would then be used to fund properties at a rate of £80,000 per unit. The model provides for repayment of the sum in full after 10 years together with a proportionate return of any capital value uplift.
1.3Current market conditions and rising property sales values have prevented SHA acquiring properties at the £50,000 grant level, as this required them to seek properties at a lower total value. Moving straight to the second stage of the model would enable SHA to raise its own investment in the scheme, increase the value level of properties being acquired and successfully complete the scheme.
1.4The only readily available alternatives would be to abandon the scheme altogether, or acquire small flats, bedsits and cheaper properties outside of the borough in order to strictly adhere to the terms of the original agreement. Neither option would be deemed acceptable or are recommended.
Recommendation
2.1It is recommended that Cabinet:
1 of 5 2.1.1 Approve moving to the second stage of the model for use of the £1m budget towards the purchase of ESP’s in 2016/17 according to the terms set out in 3.1.4 (ii) below
2.1.2 Delegate authority to the Executive Director of Borough Services, in consultation with the Executive Director for Finance and Resources, to finalise the revised detailed terms and conditions with SHA accordingly
2.1.3 Delegate authority to the Head of Law and Governance to enter into an amendment to the original agreement to reflect the changes agreed as referred to in 2.1.2 above
2.1.4 Delegate authority to the Executive Director of Borough Services, in consultation with the Executive Director for Finance and Resources and Portfolio Holder for Housing and Regeneration, to approve any subsequent amendment to this ESP programme agreement with SHA so long that it
- remains within the approved total budget
- optimises uses of the budget in order to best meet housing and homelessness needs, and
- ensures the Council receives a proportionate return on its investment
PRIORITIES, IMPACTS AND RISKS Contribution to Council Priorities This report accords with the council’s Budget and Policy Framework and directly supports the Council Plan priority/priorities of creating neighbourhoods where people feel safe and want to live.
GLOSSARY OF TERMS Term Definition Bed and Breakfast Emergency overnight accommodation for example a (B&B) Premier Inn. Typical nightly rates paid per household for homeless usage range from £65 - £95 inclusive. Existing Satisfactory Properties (ESPs) The ESP programme involves the acquisition and repair of properties currently for sale on the private market, to convert them into affordable housing.
MAIN CONSIDERATIONS
3 The Proposal
Background
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.