Resolved
The committee: i . note the report. ii. approves the changes to the Risk Management Policy.
Audit and Accounts Committee noted this item on Monday 5 December 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
The committee: i . note the report. ii. approves the changes to the Risk Management Policy.
1.1This report is to present Audit and Accounts Committee with the current status of the corporate risks and to request approval of the revised Risk Management Policy.
2.1It is recommended that:
2.1.1 The committee note the contents of the corporate risk register.
2.1.2 Approve the changes to the Risk Management Policy. PRIORITIES, IMPACTS AND RISKS Contribution to Council Priorities This report accords with the council’s Policy and Budget Framework and supports the development of an effective and efficient council.
GLOSSARY OF TERMS Term Definition SLT Strategic Leadership Team OMG Operational Management Group
MAIN CONSIDERATIONS
3.1The corporate risk register is reviewed every six months by SLT before being presented to Audit and Accounts Committee.
4 Current Position
4.1As part of the six monthly review, risk owners were asked to update the risks that they are responsible for before being presented to SLT and Audit & Accounts Committee.
4.2SLT approved the latest review of the corporate risk register on 24 August 2016. This included one change to reflect the lower interest rate environment we are currently in. The revised score is detailed below:
Risk Risk Owner Previous Score Revised Score
Treasury Executive Likelihood: 3 Likelihood: 6 Management Director of (Possible) (Very High) Finance and Resources Impact: 3 Impact: 3 (Critical) (Critical)
Overall : Overall : High Medium Risk Risk
4.3As a result of the change, the council’s corporate risk register risk scores are:
Corporate Risk Current Risk Score
1 Staffing, Skills & Capacity Medium
2 Priority & Skills Medium
3 Information Management Medium
4 Partnerships, Projects & Relationships Medium 5 Finance & Budgets Medium
6 Treasury Management High
7 Change – Regulatory (Universal Credit, Medium Welfare Reform, Business Rates, Land Charges, Planning Development, Environmental Health & Community Safety)
8 Cyber Risk Medium
9 Business Continuity Medium
10 Fraud Medium
4.4The summary corporate risk register including risk description, controls to mitigate and detailed risk score for each of these risks can be found in appendix 1.
4.5To assist the committee, appendix 2 is an extract from the Risk Management policy and provides the risk matrix and definitions of impacts and likelihoods used by risk owners when assessing the risks.
5 Risk Management Awareness
5.1As agreed by SLT, a risk management workshop was arranged for OMG members to further enhance the awareness of risk throughout the council.
The workshop was hosted by Zurich Management Services and took place on 8 July 2016. The workshop focused on the following areas:
- The world of risk (Global risks and the public sector) - Risk management cycle (definitions, risk issues, mitigation and action planning) - Risk in projects
6 Review of Risk Management Policy
6.1A review of the Risk Management Policy has been conducted in consultation with the Executive Director of Finance and Resources.
6.2The following amendments have been made:
- Para 1.4 : Council’s Risk Management Champion is now the Executive Director of Finance and Resources - Para 4.6 : Risk Matrix – All ‘negligible’ impacts are now ‘Low Risk’ - Para 6.6 : Signpost to the ‘Project Management Handbook’ - Appendix 2 : ‘Controls’ column added Corporate Risk Register - Throughout policy : Organisational changes including job titles
6.3A copy of the revised policy can be found at appendix 3. 7 Conclusion
7.1This report is to present Audit & Accounts Committee with the current status of the corporate risks and to request approval of the revised Risk Management Policy.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Item 6: Appendix 1Appendix | 286 KB | Download |
PDF |
Item 6: Appendix 2Appendix | 222 KB | Download |
PDF |
Item 6: Appendix 3Appendix | 639 KB | Download |
PDF |
Review of the Corporate Risk RegisterReport | 249 KB | DownloadRead as text |
Follow Audit and Accounts Committee at Basingstoke and Deane and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Jul 2026 | EY Audit Planning Report 2025/26The Committee note the EY Planning report. | Noted | Open |
| 1 Jul 2026 | Internal Audit Progress Report (April - June 2026)The Committee considers the Internal Audit Progress Report (April-June 2026) and notes the contents of the report. | Decided | Open |
| 1 Jul 2026 | Internal Audit Annual Report 2025/26The Committee considers the Internal Audit Annual Report 2025/26 and notes the contents of the report. | Decided | Open |
| 1 Jul 2026 | Fraud Update – Protecting The Public PurseThe Committee considers the Fraud Update- Protecting the Public Purse and notes the contents of the report. | Decided | Open |
| 1 Jul 2026 | Local Code of Corporate Governance 2026/2027The Committee approve the . | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.