Resolved
The Committee; 1) Congratulates Officers for the work carried out so far 2) Notes the content of the report
Audit and Accounts Committee decided this item on Monday 11 December 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee; 1) Congratulates Officers for the work carried out so far 2) Notes the content of the report
3.1The decision to procure a new PMIS was taken in March 2013 in order to meet internal audit recommendations, to achieve more efficient working processes, provide a comprehensive view of properties and the portfolio and better management information.
3.2At their meeting held on the 25th September the Audit and Accounts committee considered a report updating on progress in the implementation of the PMIS. This report now serves to update on progress since then, and to generally update on project implementation
3.3This report also updates on the signing off of further outstanding audit recommendations.
4 Update on Implementation phases
4.1Phase 1
4.1.1 During phase 1 we delivered the Property, Estates, and Plant and Helpdesk modules. Data was transferred from the existing Uniform system to the Property and Estates Modules. Plant data was collected, users, tenants and suppliers were set up in the system, the helpdesk was substantially configured, the LLPG interface was run to the test system, the property development scope for the interface with Aspect was drafted and the Property Services team received full training in using the system from supplier Technology Forge.
Since the last report the Operational Portfolio team are using the Helpdesk to manage repairs and maintenance calls. In addition a Lease Analyst has been appointed and commenced the exercise of reading all property leases to verify data held and ensure comprehensive data is loaded into the system, (we also had access to a Commercial Property Lawyer for a short while to assist with this work).
4.2Phase 2
4.2.1 This phase is currently in progress and is to execute the work required to implement the loading of specific documents against property records (static condition, asbestos, Display Energy Certificates (DECs), photos etc), KEL
2 of 6 (valuations software), Insurance Valuations data load, and capital accounting module.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Property Management Information SystemReport | 255 KB | DownloadRead as text |
Follow Audit and Accounts Committee at Basingstoke and Deane and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Jul 2026 | EY Audit Planning Report 2025/26The Committee note the EY Planning report. | Noted | Open |
| 1 Jul 2026 | Internal Audit Progress Report (April - June 2026)The Committee considers the Internal Audit Progress Report (April-June 2026) and notes the contents of the report. | Decided | Open |
| 1 Jul 2026 | Internal Audit Annual Report 2025/26The Committee considers the Internal Audit Annual Report 2025/26 and notes the contents of the report. | Decided | Open |
| 1 Jul 2026 | Fraud Update – Protecting The Public PurseThe Committee considers the Fraud Update- Protecting the Public Purse and notes the contents of the report. | Decided | Open |
| 1 Jul 2026 | Local Code of Corporate Governance 2026/2027The Committee approve the . | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.