Resolved
The committee: 1. Note the report 2. Request the Deputy Leader to consider its views.
Economic, Planning and Housing Committee noted this item on Thursday 25 January 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
The committee: 1. Note the report 2. Request the Deputy Leader to consider its views.
In June 2017 a report to EPH set out the findings of an independent expert review of the Council’s prospects for achieving large scale regeneration projects within the borough. The success of the Council’s regeneration objectives depend on clearly allocated resources, and this has been a focus for work over the last six months. It was considered that developing a corporate, cross-service approach to managing the regeneration function was very important to ensure that regeneration issues around housing, finance, property, planning are planned and coordinated.
2 Actions over the last six months
The EPH report identified a series of actions to progress particularly in the short term, to ensure achievement of realistic housing-led regeneration outcomes. These are repeated here, with an update on actions to implement:
2.1“Dedicating specialist resources and adopting a single point of contact for both the council and housing associations.”
The Head of Borough Development and Implementation has been given the responsibility to lead and co-ordinate regeneration work. That post is supported at a strategic level by the Executive Director Borough Services and the Executive Director Borough Development through a matrix approach.
Through a service restructure a new post, Community Regeneration Manager has been appointed as the operational lead officer, starting work at BDBC on 8 Jan 2018. Supporting that role is the Community Investment Team (formerly Community Development), and a dedicated Regeneration Officer (currently under recruitment). Detailed structure can be viewed on the BDBC website.
2.2“Clarifying roles and responsibilities and ensuring that officers have the necessary authority, impact and mandate to deliver this as a key priority”
1 of 4 Roles have been clarified as detailed in 2.1, and regeneration work forms part of the council’s programme management approach.
2.3“Gaining an understanding for what the residents’ actual perspective on the agenda is and determine what consultation approach would be best to adopt.”
Work with communities to develop community plans in urban wards has given substantial insight into the desires of local communities. This is being used in the development and evaluation of regeneration options. The consultation approach to regeneration schemes will be considered case by case, involving the expertise of the Policy and Performance team.
2.4“Understanding the housing associations’ agenda and required outcomes in a more informed way within the context of a significantly changed housing delivery / social housing context.”
Through work led by the Executive Director of Borough Services there is an improved engagement at a senior level with housing associations. This is leading to more focused collaboration with them on specific regeneration projects.
2.5“Adopting a Cost Benefit Analysis (CBA) and Opportunity Cost Analysis framework approach, whereby a methodology to establish where agreed deliverable priorities can be tested in order to inform future funding decisions on the part of the Council.”
This approach will be integrated into the strategic framework and delivery plan for regeneration that will be developed over 2018 once the Community Regeneration Manager is in post.
2.6“Considering whether an opportunistic exemplar approach (i.e. initiating special projects in advance of more costly, time-consuming, expectation- raising master planning processes) may, in some circumstances be more appropriate and productive”
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Update briefing: community regenerationReport | 308 KB | DownloadRead as text |
Follow Economic, Planning and Housing Committee at Basingstoke and Deane and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 4 Jan 2024 | Infrastructure Funding Statement (2022/23)The Committee provides its views to the Cabinet Member for Planning and Infrastructure. | Decided | Open |
| 7 Sep 2023 | Local Plan Update: next steps and spatial strategyAgreed to look at strengthening the Grampian clause in relation to water quality. Advised Members that the climate is... | Agreed | Open |
| 2 Mar 2023 | Housing and Homelessness Strategy - ReviewRESOLVED – The Committee recommends to the Cabinet Member for Homes and Regeneration that: The wording of the strateg... | Decided | Open |
| 2 Mar 2023 | Maintaining Amenities and Green SpacesRESOLVED – The Committee recommends to the Cabinet Member for Planning and Infrastructure that ward councillors are i... | Approved | Open |
| 2 Mar 2023 | Update note on the recommendations of the EPH committee (1st September 2022) on the Water Cycle StudyRESOLVED – The Committee recommends that a task and finish group be set up to report back to the committee on the Wat... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.