Resolved
The Committee notes the content of the report.
Audit and Accounts Committee decided this item on Monday 26 March 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee notes the content of the report.
Review of the Corporate Risk Register
Report to Audit and Accounts Committee – 26 March 2018 Ward(s): All Key Decision: No Appendix 1: Revised Summary Corporate Risk Register Appendix 2: Risk Matrix (taken from the current Risk Management Policy)
Audit & Accounts Committee 25 September 2017 – Review Papers relied on: of Corporate Risk Register
1 Foreword
This report is to present Audit & Accounts Committee with the current status of the corporate risks.
Recommendation to the committee:
That the content of the report is noted GLOSSARY OF TERMS Term Definition SLT Strategic Leadership Team
SMG Senior Management Group
2 Background, corporate objectives and priorities 2.1 Zurich Risk Engineering UK facilitated two risk identification workshops with SMG on 6 May 2014 and 29 July 2014 with the objective of producing a new corporate risk register.
2.2The corporate risk register is reviewed by the Strategic Leadership Team every six months before being presented to Audit and Accounts Committee.
3 Current Position
3.1As part of the six monthly review, risk owners were asked to update the risks that they are responsible for before being presented to SLT and Audit & Accounts Committee.
3.2SLT approved the latest corporate risk register on 28 February 2018. This included a change to two of the risk scores. These relate to the ‘finance and budgets’ and ‘treasury management’ risks. The revised scores are detailed below:
Risk Risk Owner Previous Revised Score Score
RR5 - Finance & Executive Likelihood: 2 Likelihood: 3 Budgets Director of (Low) (Possible) Finance and Resources Impact: 3 Impact: 3 (Critical) (Critical) Overall : Medium Overall : Risk Medium Risk
Justification for change in risk score from Accountancy Manager The overall likelihood has changed from ‘low’ to ‘possible’ due to the addition of 3 new Risk areas relating to the council’s additional income targets all of which have a medium risk level which when added to the existing low risk areas increases the overall risk slightly, albeit it remains ‘medium’ overall. In particular the likelihood of not achieving the required income targets has increased due to the higher risks associated with council’s plans to switch £90m from treasury investments to property related investments over the medium term financial plan period. Risk Risk Owner Previous Revised Score Score RR6 - Treasury Executive Likelihood: 4 Likelihood: 3 Management Director of (Significant) (Possible) Finance and Resources Impact: 2 Impact: 2 (Marginal) (Marginal) Overall : Medium Overall : High Risk Risk
Justification for change in risk score from Accountancy Manager The overall likelihood has reduced from ‘significant’ to ‘possible’ because of a combination factors. The likelihood of counterparty defaults (i.e. credit risk), failing to follow the Treasury Management Strategy and failing to achieve investment income have all reduced. Credit risk has been diversified as a result of externalising the risk through the increased use of external fund managers and the in-year monitoring for investment income shows a forecast above budget previously the forecast was showing forecasts below budget.
3.3SLT also identified a new corporate risk that has been added to the register. The new corporate risk relates to ‘poor relationship between political groups impacting on effective governance’. The new risk is detailed in appendix 1, risk reference RR11.
3.4The summary corporate risk register including risk description, controls to mitigate and detailed risk score for each of these risks can be found in appendix 1. A diagrammatic version of the register can be found below:
6 Corporate Risks : 5 1. Staffing, skills & capacity 4 2. Priority & skills 3. Information 3 1, 6, 7, 2, 3, 4, Management Likelihood
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
/17Appendix 1 | 289 KB | Download |
PDF |
/17Appendix 2 | 222 KB | Download |
PDF |
Review of the Corporate Risk RegisterReport | 431 KB | DownloadRead as text |
Follow Audit and Accounts Committee at Basingstoke and Deane and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Jul 2026 | EY Audit Planning Report 2025/26The Committee note the EY Planning report. | Noted | Open |
| 1 Jul 2026 | Internal Audit Progress Report (April - June 2026)The Committee considers the Internal Audit Progress Report (April-June 2026) and notes the contents of the report. | Decided | Open |
| 1 Jul 2026 | Internal Audit Annual Report 2025/26The Committee considers the Internal Audit Annual Report 2025/26 and notes the contents of the report. | Decided | Open |
| 1 Jul 2026 | Fraud Update – Protecting The Public PurseThe Committee considers the Fraud Update- Protecting the Public Purse and notes the contents of the report. | Decided | Open |
| 1 Jul 2026 | Local Code of Corporate Governance 2026/2027The Committee approve the . | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.