RESOLVED that : the application be APPROVED subject to th e applicant entering into a legal agreement (in accordance with the Community Infrastructure Levy Regulations 2010 and Policy CN9 of the Basingstoke and Deane Local Plan 2011-2029) between the applicant and the Borough and County Council to secure: Provision of a Full Travel Plan together with approval and monitoring fees, and a Travel Plan bond A financial contribution towards improvements to the local highway network surrounding the site. Should the requirements set out above not be satisfactorily secured, then the Planning and Development Manager be delegated to REFUSE permission for appropriate reasons. On completion of the legal agreement the Planning and Development Manager be delegated to grant planning permission subject to the conditions listed below. Reasons for Approval 1 The development would provide a complementary facility to support the regeneration of ... view the full minutes text for item 5/18
Word for word from the decision Basingstoke and Deane published for this meeting.Source: democracy.basingstoke.gov.uk
Application no: 17/04186/FUL For Details and Plans Click Here
Site Address Land At Plot W Basing View Basingstoke RG21 4EQ Proposal Erection of a six storey hotel (Use Class C1) with associated leisure uses, car parking and landscaping
Registered: 5 January 2018 Expiry Date: 8 June 2018 Type of Full Planning Case Officer: Katherine Fitzherbert- Application: Application Green 01256 845716 Applicant: VUR Village Trading Agent: Katie Brown No 1 Ltd Ward: Eastrop Ward Member(s): Cllr Gavin James Cllr Stuart Parker
Parish: OS Grid 464688 152686 Reference:
Recommendation: The applicant be invited to enter into a legal agreement (in accordance with the Community Infrastructure Levy Regulations 2010 and Policy CN9 of the Basingstoke and Deane Local Plan 2011-2029) between the applicant and the Borough and County Council to secure: Provision of a Full Travel Plan together with approval and monitoring fees, and a Travel Plan bond A financial contribution towards improvements to the local highway network surrounding the site.
Should the requirements set out above not be satisfactorily secured, then the Planning and Development Manager be delegated to REFUSE permission for appropriate reasons.
On completion of the legal agreement the Planning and Development Manager be delegated to grant planning permission subject to the conditions listed at the end of this report.
Reasons for Approval
1. The development would provide a complementary facility to support the regeneration of Basing View as a 21st century business location and a high quality strategic employment site, whilst also making efficient use of land in a sustainable location in accordance with the overarching requirements of Policy SS8 of the Basingstoke and Deane Local Plan 2011 - 2029. Whilst the location of the site only would not be in full accordance with the detailed requirements of Policy SS8 (iii) of the Basingstoke and Deane Local Plan 2011 – 2029, information submitted within the application demonstrates alternative sites as not being available. Furthermore, the wider benefits of the proposal weigh in favour of the development to further support the role of Basingstoke town by
1 of 163 encouraging economic prosperity and inward investment.
2. The development proposes main town centre uses within an edge of centre location however, as demonstrated by information submitted within the application, the development would not result in any significant negative impact upon the vitality or viability of Basingstoke Town Centre and as such would accord with Policy EP3 of the Basingstoke and Deane Local Plan 2011-2029.
3. The development would provide a safe and suitable access and would not cause an adverse impact on highway safety. The agreed transport contribution would mitigate impacts of traffic associated with the proposed development. In addition, adequate parking would be secured to serve the proposed development and therefore the proposal would comply with Policies EM10 and CN9 of the Basingstoke and Deane Local Plan 2011-2029.
4. The proposal would conserve the biodiversity value and nature conservation interests of the site and as such would comply with the National Planning Policy Framework (March 2012) and Policy EM4 of the Basingstoke and Deane Local Plan 2011-2029.
5. The proposed development would not result in an undue loss of privacy or cause undue overlooking, overshadowing, or overbearing impacts to existing neighbouring properties, and as such would comply with Policy EM10 of the Basingstoke and Deane Local Plan 2011-2029.
6. Adequate drainage (foul and surface water) can be provided for the development and can be adequately controlled through other legislation, and through planning conditions, so as to ensure that there would be no risk to property or the environment. The proposal accords with Policies EM7 and CN6 of the Basingstoke and Deane Local Plan 2011-2029.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Development Control Committee at Basingstoke and Deane and we tell you when its next papers are published, before the meeting rather than after it.
Quarterly Planning Appeals ReportRESOLVED that: Members of the Development Control Committee note the outcomes of the appeal decisions and the reasons...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.