Southern Manydown Project Update Report

Noted Executive 1 paper

Manydown Executive Committee noted this item on Tuesday 17 December 2019. Below is the council's own wording, with the papers it was decided on.

Item7/19

Resolved

1) Note the Council’s Motion of 12 July 2012 to promote the land at Manydown for development. 2) Note the council has responded to and submitted a proposal for the land at southern Manydown as part of the Local Planning Authority’s Call for Sites to assist in the Local Plan Update process. 3) Approve the establishment of a project to support the proper planning of infrastructure at southern Manydown and strategy to promote the land for inclusion in the updated Local Plan on the basis set out in the report and Appendix 2 of the report. 4) Approve the proposal to work in collaboration with adjoining landowners, to support the proper planning of infrastructure at southern Manydown on the basis set out in Appendix 1 of the report. 5) Approve the proposal to use the MHCLG Garden Village and Town Capacity Fund money to support the proper planning of infrastructure at Manydown and delegates the management and expenditure of the funding to the Project Director Manydown in consultation with the Manydown Executive Committee.
Word for word from the decision Basingstoke and Deane published for this meeting. Source: democracy.basingstoke.gov.uk

Follow this further

Built from Basingstoke and Deane's papers

What the report saysPro

Report to Manydown Executive Committee

Report to Manydown Executive Committee – 17 December 2019 Southern Manydown - Project Update Report Cllr John Izett, Cabinet Member for Regeneration and Property

Ward(s): All Key Decision: Yes Appendix 1: (Confidential) Proposed joint working arrangements Appendix 2: (Confidential) Southern Manydown Project Framework

Papers relied on:

Foreword - Cllr John Izett, Cabinet Member for Regeneration and Property

Basingstoke and Deane Borough Council and Hampshire County Council as owners of the Manydown South land have, under the terms of its acquisition in 2012 as confirmed by the subsequent High Court decision, a legal responsibility to promote the land and secure the better planning of the area. This paper provides for the establishment of a formal project and budget for Manydown South which builds on the work undertaken since 2015 on capacity studies. It is a continuation of previous responses to the local planning authority’s Call for Sites in July 2017 and 2019 so as to put forward a comprehensively prepared and investigated case for inclusion of the land in the updated Local Plan.

In relation to further comprehensive studies to assess and plan for development of the land including the provision of new homes, it will be essential that infrastructure requirements including transport are to the fore as well as our environmental priorities. It is also necessary to engage with adjoining landowners for the better planning of any development that may be permitted by the Local Plan process as it unfolds.

This report addresses an important next stage in relation to the two councils’ ownership as public bodies of the Manydown South land.

1 of 12 It is recommended that the Manydown Executive Committee:

i. Notes the Council’s Motion of 12 July 2012 to promote the land at Manydown for development. ii. Notes the council has responded to and submitted a proposal for the land at southern Manydown as part of the Local Planning Authority’s Call for Sites to assist in the Local Plan Update process. iii. Approves the establishment of a project to support the proper planning of infrastructure at southern Manydown and strategy to promote the land for inclusion in the updated Local Plan on the basis set out in the report and Appendix 2. iv. Approves the proposal to work in collaboration with adjoining landowners, to support the proper planning of infrastructure at southern Manydown on the basis set out in Appendix 1. v. Approves the proposal to use the MHCLG Garden Village and Town Capacity Fund money to support the proper planning of infrastructure at Manydown and delegates the management and expenditure of the funding to the Project Director Manydown in consultation with the Manydown Executive Committee.

Background, corporate objectives and priorities

In 1996, in recognition of the potential strategic importance of the Manydown land, Basingstoke and Deane Borough Council (BDBC) acquired 2024.13 acres by way of a 999-year lease from the Manydown Estate. Simultaneously with entering into the lease, the council entered into an agreement to share its interest with Hampshire County Council (HCC) on a 50:50 basis. The scale and location of the Manydown land makes it a logical place for a significant element of Basingstoke’s necessary growth over the current Local Plan timescale, and potentially beyond. With the borough experiencing a growing population, strategic sites such as Manydown will play a vital role in addressing the need for housing including affordable housing that meets the requirements of local demand.

It offers the opportunity not just for much-needed housing development but for the creation of a new place based on ‘Garden Community’ principles.

The Vision of Manydown was adopted in 2014 and the Manydown objectives and 10 key principles were developed through consultation during 2015 and 2016.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Southern Manydown Project Update ReportReport 366 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

3 of 5 attended
JI
Councillor John IzettCommittee Member, present
SB
Councillor Simon BoundCommittee Member, present
HG
Councillor Hannah GoldingCommittee Member, present
C
CommunicationsOfficer, expected
AR
Andrew ReynoldsOfficer, expected

On this subject at Basingstoke and Deane

Search all
  1. Southern Manydown Project Update ReportThis decision
  2. Southern Manydown Project Update ReportNoted
  3. Southern Manydown - Project Update ReportDecided

More from Basingstoke and Deane Manydown Executive Committee

All decisions
MeetingDecisionOutcome
21 Mar 2022 Manydown Programme Update Report· The progress being made on the Manydown Programme be noted. · The comments of the Manydown Overview Committee at Ap... Noted Open
18 Jan 2021 Manydown Programme Update Report1) Note the progress made on the Manydown Programme. 2) Note the comments of the Manydown Overview Committee 3) Appro... Noted Open
8 Sep 2020 Manydown North Project Update Report1) Note the progress made on the Manydown project. 2) Note the comments of the Manydown Overview Committee. 3) Note t... Noted Open
8 Sep 2020 Southern Manydown Project Update Report1) Note the progress made on the southern Manydown project. 2) Note the comments of the Manydown Overview Committee. ... Noted Open
17 Dec 2019 Manydown North - Project Update ReportTo note: 1) The progress made on the Manydown Project. 2) The comments of the Manydown Overview Committee Noted Open