Quarter 1 Revenue Monitoring Report and Covid-19 Financial Impact Update 2020/21

Noted Executive 1 paper

Cabinet noted this item on Tuesday 8 September 2020. Below is the council's own wording, with the papers it was decided on.

Item16/20

Resolved

The following additional spend for new funding requests as noted in section 8 of the report, to be funded from the MTFS Risk Reserve , be approved : • £1.07M 2020/21 MHCLG Capacity Grant Manydown South. This funding was allocated to this reserve for this purpose as part of the Revenue Outturn Report for 2019/20 approved by Cabinet in July 2020 and the release can be therefore be approved by Cabinet; Recommendation to Council Council be recommended to note: 1) The significant financial implications that Covid-19 is having on the council, including the current estimated cost of £5.98M in 2020/21 which exceeds the current £2.13M of funding received from Government, as detailed in section 6 of the report ; 2) The likely ongoing financial implications of Covid-19 on the MTFS in future years and that current savings plans must continue to be delivered where possible to prevent further deterioration in the council’s financial position; 3) Further lobbying is being made to Government for further funding both directly and through other associations and societies; 4) The proposed rebasing of the 2020/21 budget and use of central resources to mitigate the Covid-19 financial impact as shown in section 7 noting that there is a £2.21M budget gap in 2020/21; 5) That the non Covid-19 net revenue expenditure on services in 2020/21, before net transfers to/from reserves is forecast to be £1.64M lower than the working budget. Details of the significant variances can be seen in section 6 of the report ; 6) The 2020/21 savings position is as detailed in section 9 of the report ; 7) That budget virements amounting to £2.69M were processed in the first quarter, as summarised in section 10 of the report ; and 8) The risks associated with the revenue forecasts are as detailed in section 11 of the report. Council be recommended to approve: 9) The revised 2020/21 budget, which has been prepared in response to the financial impact of Covid-19 as shown in section 7 (table 5) of the report , and notes that c urrent accountancy policies will allocate any year end deficit against the Medium Term Financial Risk Reserve; 10) The following additional spend for new funding requests as noted in section 8 of the report to be funded from the Homelessness Reserve: • £0.02M 2020/21 and £0.06M 2021/22 Rough Sleeper Initiative; 11) The additional spend for new funding requests as noted in section 8 to be funded from the MTFS Risk Reserve: • Up to £0.25M 2020/21 Support J7 Planning; and • Up to £0.10M 2020/21 Devolution and LGR Review.
Word for word from the decision Basingstoke and Deane published for this meeting. Source: democracy.basingstoke.gov.uk

Follow this further

Built from Basingstoke and Deane's papers

What the report saysPro

Report to Cabinet

Quarter 1 Revenue Monitoring Report and Covid-19 Financial Impact Update 2020/21

Cllr Hannah Golding – Cabinet Member for Finance and Service Improvement

Cabinet Report to: Council 8 September 2020 Meeting Date: 15 October 2020 Ward(s): All Key Decision: Yes Appendix 1: None Appendix 2: Appendix 3:

Papers Relied On: None

FOREWORD – Cabinet Member for Finance and Service Improvement

It has been a very challenging period since March 2020 when restrictions on day to day activity were put in place as result of Covid-19 and councils, including Basingstoke and Deane Borough Council, had to change ways of working to deal with those and provide support to communities.

As well as the operational changes, this had inevitably led to pressures on finances caused by additional expenditure, significantly reduced income from fees and charges, property and investment. Some of this has already been alleviated by funding from Central Government and there are plans for further compensations. Notwithstanding all that the council now needs to rebase its budget based on what is currently known or anticipated for the rest of the financial year whilst looking forward to the Medium Term Financial Strategy and the implications on that.

The first step is to consider the implications for this financial year and the way in which any budget gap can be minimised. It is recommended that:

Cabinet requests Council to note:

1 The significant financial implications that Covid-19 is having on the council, including the current estimated cost of £5.98M in 2020/21 which exceeds the current £2.13M of funding received from Government, as detailed in section 6;

2 The likely ongoing financial implications of Covid-19 on the MTFS in future years and that current savings plans must continue to be delivered where possible to prevent further deterioration in the council’s financial position;

3 Further lobbying is being made to Government for further funding both directly and through other associations and societies;

4 The proposed rebasing of the 2020/21 budget and use of central resources to mitigate the Covid-19 financial impact as shown in section 7 noting that there is a £2.21M budget gap in 2020/21;

5 That the non Covid-19 net revenue expenditure on services in 2020/21, before net transfers to/from reserves is forecast to be £1.64M lower than the working budget. Details of the significant variances can be seen in section 6;

6 The 2020/21 savings position is as detailed in section 9;

7 That budget virements amounting to £2.69M were processed in the first quarter, as summarised in section 10; and

8 The risks associated with the revenue forecasts are as detailed in section 11;

Cabinet is recommended to approve:

9 The following additional spend for new funding requests as noted in section 8 to be funded from the MTFS Risk Reserve: • £1.07M 2020/21 MHCLG Capacity Grant Manydown South. This funding was allocated to this reserve for this purpose as part of the Revenue Outturn Report for 2019/20 approved by Cabinet in July 2020 and the release can be therefore be approved by Cabinet;

Cabinet requests Council to approve:

10 The revised 2020/21 budget, which has been prepared in response to the financial impact of Covid-19 as shown in section 7 (table 5), and notes that current accountancy policies will allocate any year end deficit against the Medium Term Financial Risk Reserve;

11 The following additional spend for new funding requests as noted in section 8 to be funded from the Homelessness Reserve: • £0.02M 2020/21 and £0.06M 2021/22 Rough Sleeper Initiative; 12 The additional spend for new funding requests as noted in section 8 to be funded from the MTFS Risk Reserve: • Up to £0.25M 2020/21 Support J7 Planning; and • Up to £0.10M 2020/21 Devolution and LGR Review.

Background, Corporate Objectives and Priorities

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Quarter 1 Revenue Monitoring Report and Covid-19 Financial Impact Update 2020/21Report 616 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 6 attended
KR
Councillor Ken RhatiganChair, present
SB
Councillor Simon BoundVice-Chair, present
RB
Councillor Rebecca BeanCommittee Member, present
HE
Councillor Hayley EachusCommittee Member, present
HG
Councillor Hannah GoldingCommittee Member, present
JI
Councillor John IzettCommittee Member, present

On this subject at Basingstoke and Deane

Search all
  1. Quarter 1 Revenue Monitoring Report and Covid-19 Financial Impact Update 2020/21This decision
  2. Quarter 3 Revenue Monitoring as at 31 December 2025Decided
  3. Quarter 2 Revenue Monitoring as at 30 September 2025Decided
  4. Quarter 1 Revenue Monitoring 2025/26Decided
  5. Quarter 3 Revenue Monitoring 2024/25Decided
  6. Quarter 2 Revenue Monitoring Report 2024/25Noted

More from Basingstoke and Deane Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 Motion referred from Council - Protecting South Ham And Buckskin Residents From Compulsory Purchase And Ensuring Full Democratic AccountabilityThat Cabinet note the motion referred by Council and agree to progress the actions within the motion in accordance wi... Noted Open
8 Sep 2026 Motion referred from Council - Increasing Biodiversity Net Gain Through the Local PlanThat Cabinet support the direction of travel set out in the motion and continue work through the Local Plan process t... Decided Open
8 Sep 2026 Recommendations from the Environment and Infrastructure Committee – Climate Emergency StrategyThat Cabinet endorse the recommendations of the Environment and Infrastructure Committee and incorporate them into th... Decided Open
8 Sep 2026 Local Plan - Next Steps1) Agree that work on a new local plan should proceed under the new planning system as set out in the Planning and Co... Agreed Open
8 Sep 2026 Regeneration Lettings Plans – Amendment to Housing Allocations Scheme1) Approve the Regeneration Priority Assessment Framework as at Appendix 2 of the report. 2) Authorise the Head of Le... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies