Item21/21
Resolved
Note: 1. The financial position for quarter 1 of 2021/22 and the forecast for the financial year as set out in paragraph 2.1 of the report. 2. The 2021/22 savings position is as detailed in section 11 of the report. 3. Budget virements amounting to £1.26M were processed during the first quarter, as summarised in section 6 of the report. 4. The risks associated with the revenue forecasts are detailed in section 13 of the report. 5. The latest position in relation to Manydown is in section 8 of the report. 6. Update in relation to the funds set aside in the Economic Recovery Fund and Climate Change reserve are notes in sections 9 and 10 respectively. 7. Covid-19 related grant funding available to the authority during 2021/22 is outlined in section 12 of the report.
Word for word from the decision Basingstoke and Deane published for this meeting.
Source: democracy.basingstoke.gov.uk