Resolved
The Committee agrees to re-establish the task and finish group.
Community, Environment and Partnerships Committee agreed this item on Wednesday 20 October 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee agrees to re-establish the task and finish group.
This briefing paper provides feedback on the work of the Recycling from Flats and Apartments Task and Finish Group (the group), formed on 23rd October 2019 in response to a motion presented to Council on 18th July 2019 concerning the recycling rate for the Borough.
The original Council motion asked the group to ensure that steps were taken to improve the recycling rate from its current level and to investigate any barriers to maximising the recycling potential from flats and apartment blocks.
At the first meeting of the Task and Finish group, the group received an overview of the service by Officers. In response to this the members agreed that they would like to carry out further work to:
Improve Basingstoke’s recycling rate with a specific focus on flatted developments.
Send out a coordinated approach and message.
See an improvement in the key areas identified.
. Page 1 of 3 1. Information received
1.1The Group received a wide range of background information from Officers at the meetings including:
The Council was awaiting national guidance from the government to implement a standardised process across the UK.
There are over 800 bin stores in Basingstoke and Deane and over 1200 flats.
The Teams would focus on key areas and an audit carried out of all bin stores to determine whether the facilities were correct or new signage required
In 2017, a recycling information leaflet was circulated to every flat in the Borough but there was a high turnover of individuals who lived in flats.
Officers continually had meetings with those responsible for flatted developments but some were owned by management companies and the others by housing associations.
Officers had carried out a number of initiatives to try to increase the recycling rate and raise awareness such as recycling champions, giving out information packs to local estate agents, educating local school children, new build information packs and examples of locations where recycling issues had been written into rental agreements.
Locations where bin stores were locked caused less issues as they stopped issues such as fly tipping.
Officers had chosen two locations to target to try and increase/improve the recycling rate which were Popley East which was an existing problematic development and Chapel Gate a new development
Officers acknowledged that Serco’s charges to remove incorrect items were passed on to residents through management company service charges.
2. Update on the current position from Officers
2.1The Joint Waste Team identified a number of sites on which to start this project and these were as follows:
Skyline Plaza Crown Heights Some of the communal areas on the new Chapel Gate Development
2.2At these sites, Officers installed new signage, stickered the bins with refuse, and recycling and glass signs, delivered leaflets and flat bags to residents. Page 2 of 3 2.3 Once this was completed, in conjunction with the management company, Officers monitored collections for a period of time and did see some reduction in contamination of the recycling bins.
2.4Lessons learnt from the first sites were that the signs are too large for some of the locations and smaller signs needed to be produced.
2.5Unfortunately shortly after the start of the programme, the planned work was immediately stopped due to Covid and Officers are only just now being able to pick this work up again so progress has been slow.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Recommendations from the Task and Finish Group considering the Council Motion on Recycling from flats and apartmentsReport | 240 KB | DownloadRead as text |
Follow Community, Environment and Partnerships Committee at Basingstoke and Deane and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Jan 2024 | Draft Biodiversity StrategyThe Committee provides its comments requests that the results of the Biodiversity audit be circulated to all members.... | Decided | Open |
| 15 Nov 2023 | Progress on implementing the adopted Climate Change and Air Quality StrategyThe Committee: · Considers and makes recommendations to the Portfolio Holder for the Climate and Ecological Emergency... | Decided | Open |
| 15 Nov 2023 | Biodiversity Strategy PresentationTo note the contents of the presentation. | Noted | Open |
| 13 Sep 2023 | Council-owned community centres: revised lease and service level agreement approachThe Committee provides its comments to the Portfolio Holder. | Decided | Open |
| 19 Jul 2023 | Green Infrastructure Strategy - Progress UpdateThe Committee notes the work undertaken during years 3 and 4 of the Green Infrastructure Strategy (2018). | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.