Resolved
The Committee notes the report.
Community, Environment and Partnerships Committee decided this item on Wednesday 19 January 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee notes the report.
2.1In late 2021 a team of specialist consultants were appointed to advise the council on the future of the Leisure Park and future Aquadrome facility mix.
2.2This is a significant asset owned directly by the council but subject to a number of long leasehold interests. Unlike the plans proposed by the original joint development partner New River to buy out these interests and undertake comprehensive re-development, it is considered likely that future plans will focus on unfettered land developed on a phased basis.
3 Indicative Programme
3.1The consultant team has been commissioned to report on its initial advice by the end of April 2022. Up to the start of the pre-election period the Masterplanning Architect, BDP will lead the engagement process on the options for the Leisure Park in conjunction Camargue and FMG in relation to the future Aquadrome mix. The Engagement Plan is attached at Appendix 1.
4 Objectives of the engagement
4.1The aims of this engagement will be:
to be open and clear about the context of the opportunities and constraints of the possible options for development
to involve elected representatives at BDBC and HCC, borough residents, local communities, leisure park users, statutory consultees and special interest groups in shaping the future, giving them the opportunity to put forward ideas and suggestions and to input into decision-making on options and proposals to use locations or platforms that are widely accessible and to give regular updates on what is what happening and how people can have their say. 4.2 Key to maintaining transparency will be regular communications, setting out opportunities for the local community and stakeholders to be involved and openly documenting consultation responses and how they have helped shape the proposals.
4.3The engagement will not take a broad-brush ‘what would you like to see’ approach but is focused on underpinning a robust, viable and deliverable masterplan.
3 of 9 5 Previous engagement relevant to the leisure park
5.1The emerging proposals will take into account parallel consultations, including the Town Centre Strategy and the Local Plan Update.
5.2NewRiver undertook some initial engagement in 2018 and although it had a different context, a summary of the feedback has been shared with the current consultant team.
6 Engagement Stakeholders
6.1Elected Representatives
6.1.1 Ward councillors will be regularly involved through discussions with the master planners and officer team. To ensure portfolio holders have cross-party input into the project, a minuted Members’ Advisory Panel has been established.
6.1.2 There will be regular updates to the Community, Environment and Partnership Committee and EPH.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Leisure Park and Aquadrome: Engagement StrategyReport | 378 KB | DownloadRead as text |
Follow Community, Environment and Partnerships Committee at Basingstoke and Deane and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Jan 2024 | Draft Biodiversity StrategyThe Committee provides its comments requests that the results of the Biodiversity audit be circulated to all members.... | Decided | Open |
| 15 Nov 2023 | Progress on implementing the adopted Climate Change and Air Quality StrategyThe Committee: · Considers and makes recommendations to the Portfolio Holder for the Climate and Ecological Emergency... | Decided | Open |
| 15 Nov 2023 | Biodiversity Strategy PresentationTo note the contents of the presentation. | Noted | Open |
| 13 Sep 2023 | Council-owned community centres: revised lease and service level agreement approachThe Committee provides its comments to the Portfolio Holder. | Decided | Open |
| 19 Jul 2023 | Green Infrastructure Strategy - Progress UpdateThe Committee notes the work undertaken during years 3 and 4 of the Green Infrastructure Strategy (2018). | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.