RESOLVED : that the Manydown Overview Committee: § notes the progress made on the Manydown North project. § reviews and provides comments on the content of this report for consideration by the Executive Director Corporate Services and Assets (S151 Officer) in consultation with, Project Director Manydown and Chief Operating Officer MGC LLP and Cabinet Member for Major Projects and Regeneration to inform the gateway review process outlined at paragraph ... view the full minutes text for item 12/23
Word for word from the decision Basingstoke and Deane published for this meeting.Source: democracy.basingstoke.gov.uk
Report of: Cllr Onnalee Cubitt, Cabinet Member Major Projects and Regeneration
Andrew Reynolds, Project Director Manydown & Chief Lead Officer: Operating Officer MGC LLP (01256) 845675
Ward(s): All Key Decision: Yes Manydown North Land drawdown purchase strategy – Appendix 1: (Confidential) Appendix 2: Manydown North – Financial Summary (Confidential) Manydown North – Draft Section 123 valuation Appendix 3: (Confidential) Appendix 4: Draft Heads of Terms (Confidential) Manydown North - MDV LLP Overarching Business Plan – Appendix 5: (Confidential) Including Proposed Updates 5a & 5b Manydown North - MDV LLP Phase 1 Business Plan – Appendix 6: Confidential
Exempt or Confidential Information It is considered that information contained within appendices 1-6 contain exempt information under the meaning of Schedule 12A of the Local Government Act 1972, as amended, and therefore cannot be made public.
Foreword - Cllr Onnalee Cubitt, Cabinet Member Major Projects and Regeneration Since our administration came to power in May 2023, we have been determined to fulfil the promises made to the residents of Basingstoke and Deane since 1995. We have worked tirelessly with our officers and partners over the last 5 months to ensure that we fulfil those commitments made to develop Manydown.
The decisions recommended at the Extraordinary Cabinet Meeting of 13th November marked a momentous occasion. These decisions will be transformational for the future of our residents and our Borough. This important Development will have
1 of 10 significant consequences for our residents in Basingstoke for many years to come and for us to ensure that this major development area is built to the highest standard.
Many of us in this Cabinet have personally expended “blood, toil, sweat and tears” to get to this place over many, many years. It should never have been this way. Our Council should not have been taken to the High Court. On the 17th April 2012 Basingstoke and Deane Borough Council was found to have acted unlawfully by Justice Lindblom.
This Council has spent so much money, time, and political capital on this strategic site for far too long. We have a fiduciary duty to our residents to fulfil the Council’s duty and commitment to develop Manydown.
The whole of Manydown North was scheduled to have been built by 2028/29 in accordance with the phasing set out in Policy SS3 in our adopted Local Plan dated May 2016 on page 36 of 185. The knock- on effects from all these delays have contributed to the Council failing to have a 5- year land supply resulting in planning by appeal rather than planning by design. This decision under this new administration means we will be able to start the process of bringing back control of our Local Plan.
This is a journey which has taken too long. A 999-year leasehold in Manydown was acquired by The Council and the County Council on 20th February 1996 for £10m with the receipt of the monies from the sale of our council housing stock. We promised the then council house tenants that we would use the LSVT receipts to build more housing for our residents.
This land was acquired and held for planning purposes and, in particular, that it was to be developed for housing.
“Excerpt from The Manydown Judgment 17 April 2012
4.2The Council's objectives in purchasing the site, in partnership with the County Council, would be:
(i) To achieve a properly planned, comprehensive development of the area. (ii) To secure land for low-cost housing in accordance with existing Council policy. (iii) To achieve a financial gain which, in turn, could be put, in whole or in part, to further housing initiatives.
4.3The partnership with the County Council is important for many reasons. In particular there will be requirements for infrastructure investment prior to the first land sales. This load needs to be shared. ….”
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Manydown Overview Committee at Basingstoke and Deane and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.