1) Approve the Outline Business Case to develop a replacement for the Aquadrome on the site of Car Park 8 at the Leisure Park and endorse the Preferred Option Facility Mix and DBOM delivery route and the procuring of a contractor to finalise the full business case. 2) Delegate authority to the Director of Regeneration in agreement with the Executive Director of Corporate Services & Assets (Section 151 Officer), and in consultation with the Cabinet Member for Major Projects and Regeneration and the Cabinet Member for Finance and Property to commence procurement and; · To finalise tender documentation and procure a contractor in accordance with the Preferred Delivery Model · To authorise the Head of Law and Governance to enter into the contract/lease and any other necessary legal documentation with the successful operator · To review, seek such amendments, as required to ensure policy compliance, and to approve, as landowner, the submission of the appointed contractor’s planning application to the Council as Local Planning Authority · To authorise the Head of Law and Governance to enter into such agreements with statutory authorities as are required to support the development of a replacement Aquadrome 3) Delegate authority to the Director of Residents Services in agreement with the Executive Director of Corporate Services & Assets (Section 151 Officer), and in consultation with Cabinet Member for Sports Leisure and Culture and the Cabinet Member for Finance and Property to negotiate extension to the existing Leisure contract to ensure continuity of service. 4) Note that revenue and capital funding requirements will be included in the MTFS Update and Capital Programme update to Council in February 2024.
Word for word from the decision Basingstoke and Deane published for this meeting.Source: democracy.basingstoke.gov.uk
Cabinet Date: 6 February 2024 Subject: New Leisure Centre/Aquadrome – Outline Business Case Cllr Onnalee Cubitt, Cabinet Member for Major Projects and Report of: Regeneration
Lead Officer: Sarah Longthorpe, Director of Regeneration Contact Officer: James Mercer, Development Manager – Leisure Park
Ward(s): All Key Decision: Yes
Appendix 1: Proposed Site location plan
Appendix 2: Exempt: Financial Business Case Summary Appendix 3: Exempt: Outline Business Case
Exempt or Confidential Information It is considered that information contained within appendix 2 and 3 contains exempt information under the meaning of paragraph 3 of Schedule 12A of the Local Government Act 1972, as amended, and therefore cannot be made public.
Foreword – Cllr Onnalee Cubitt, Cabinet Member for Major Projects and Regeneration
Since our Administration came to power in May 2023, we have been determined to fulfil the promises long made to the residents of Basingstoke and Deane to replace our aged, gas guzzling but much loved Aquadrome. Since 2019/2020 alone BDBC has sunk further costs of £4m in “sticking plasters” just to keep “the show on the road”. Going forward, there is a budget of £2m to do work needed on the building over the next five years.
As a new Administration we are passionately committed to providing our residents with an Aquadrome that is a wonderful destination, fit for purpose which meets the needs of our ever-increasing population.
1 of 19 Background
This journey has been far too long and arduous. To misquote a couple of famous songs….:-
“Way, way, back, many…. cabinet decisions ago, the previous Administration promised so much and delivered so little…..”
"Words, words, words….. we’re so sick of words…..”
As far back as 2009 the Council adopted a Council Plan to improve the range of facilities at the Leisure Park.
The Strategic Plan for Sports and Recreation in BDBC up to 2025 and adopted by Cabinet in 2011 identified the need to “Develop a long-term plan to refresh and where possible enhance the Leisure Park”.
The Delivery Schedule for the Strategic Plan for Sports and Recreation in BDBC up to 2025 and approved by Cabinet in 2012 included an action ”to present a strategy for improving Basingstoke Leisure Park to Members for approval”.
On 25th September 2012, the then Cabinet took a Decision to regenerate The Basingstoke Leisure Park. It was agreed that they would go out to Tender and sign a deal with an “experienced developer with a demonstrable track record with the financial capacity to undertake the delivery of development. “The indicative Timetable informing the Decision was that planning application commenced 2014/15 and that the first phase of construction was to commence in 2016.
In December 2015, the then Cabinet approved a Decision to replace the Aquadrome with a new Aquadrome and to build the new Aquadrome subject to planning as part of the first phase for completion late 2019. A condition survey was conducted in 2015 which estimated £4m in remedial works. This estimate did not include any enhancements which had been identified as a further £6m in costs. The New River offer would build a new Aquadrome “at its sole cost” which would be bigger and better than the existing Aquadrome and cost £21m.
In April 2016, the then Cabinet approved the Decision to agree the Heads of Terms with New River in respect of the Leisure Park redevelopment, agree to enter into a Development Agreement and Lease with New River and agree to the use of compulsory purchase orders to assist in site assembly.
Since then, NOTHING has happened with the Aquadrome on the Leisure Park apart from costly remedial works of £4m since 2019/2020 and rising.
The first Phase as promised in 2012 did not start in 2016.
Completion of the new Aquadrome as promised in December 2015 did not happen by 2019.
Sadly, these delays have meant we have had to spend approximately £4m since 2019/2020 just to keep the existing Aquadrome open.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.