Waste Service Review Programme (WSRP) - Outline Business Case

Approved Executive 1 paper

Cabinet approved this item on Tuesday 30 July 2024. Below is the council's own wording, with the papers it was decided on.

Item15/24

Resolved

1) Approve the extension and variation of the joint contract with Hart District Council with Serco for the collection of waste for a further eight years from October 2025. 2) Agree that weekly waste and fortnightly recycling collections together with a new weekly food waste collection service will commence in October 2025 and that a simpler weekly collections model will commence from 30 September 2026. 3) Recommend to Council on 17 October 2024 that they approve an increase in the budget allocation in the current medium-term financial strategy of £2.73M during 2025/26 to 2027/28 to reflect the additional costs of the new contract with Serco from October 2025 as shown in the table at 11.5 of the report. 4) Delegate authority to the Director of Resident Services, in consultation with the Cabinet Member for Resident Services and Housing and Head of Law and Governance to negotiate, prepare and, subject to Council approving the budget on 17 October 2024, to enter into final documentation to complete the extension and variation of the contract.
Word for word from the decision Basingstoke and Deane published for this meeting. Source: democracy.basingstoke.gov.uk

Follow this further

Built from Basingstoke and Deane's papers

What the report saysPro

Report to Cabinet

Cabinet Date: 30 July 2024

Subject: Waste Service Review Programme (WSRP) Outline Business Case

Report of: Cllr L James, Cabinet Member for Residents’ Services and Housing

Fiona Darby, Director of Resident Services Lead Officer: Helen Taylor-Cobb, Head of Contracted Services

Kerry De Rosa, PMO and Improvement Manager Contact Officer: Ian Spicer, Contract Performance Manager Ashley Wild, Waste and Recycling Manager

Ward(s): All Key Decision: Yes Appendix 1: WSRP – Outline Business Case

Exempt or Confidential Information

It is considered that information contained within Appendix 1 contains exempt information under the meaning of paragraph 3 of Schedule 12A of the Local Government Act 1972, as amended, and therefore cannot be made public.

Foreword – Cllr L James, Cabinet Member for Residents’ Services and Housing

Residents have been asking us to introduce food waste collections for some time and we have been looking at the best way to do this across the borough as soon as possible.

We have listened and this decision will see the introduction of a new weekly food waste collection from October next year.

1 of 16 This means that the council is well ahead of the deadline for ‘mandatory’ introduction of food waste collections under the ‘simpler recycling’ programme in The Environment Act 2021. The act aims to make what is collected for recycling more consistent across the country, increasing what can be collected at the kerbside, as well as reducing the amount of packaging that just gets thrown away.

Our new weekly food waste service will take over a third of waste from residents’ grey bins and use it to generate greener energy.

At the moment Basingstoke is at the bottom of the recycling tables. We want to see our recycling rates go up and the only way to do this is to help residents to recycle more and put less into their grey bins.

The borough council collects recycling and rubbish from the kerbside. But Hampshire County Council (HCC) disposes of or recycles what is collected. We know there is frustration that, at the moment, we can only collect plastic bottles for recycling, and no other types of plastic.

Introducing our new weekly food waste collection service will allow residents to take more out of their grey bin while HCC progresses plans for new and better waste sorting facilities. When these are introduced, we will be able to collect even more items in green bins, especially more plastics. These changes will boost recycling so we will be left with very little to go into the grey bin.

All of these changes will give us the opportunity to redesign the weekly collection service that we know residents prize very highly. Weekly collection of food waste - that makes up over a third of grey bin contents - addresses issues around smells and food attracting animals to bins.

After the food waste service has been introduced, we must consider the most efficient, value-for-taxpayers’ money weekly bin service for our residents. We are guided by our cross council, unanimously supported, climate change emergency declaration. This decision will make a significant contribution to cutting carbon and reducing waste to meet that climate challenge.

Recommendation to Cabinet

Who should collect the bins?

 To approve the extension and variation of the joint contract with Hart District Council with Serco for the collection of waste for a further eight years from October 2025.

How often should the bins be collected?

 To agree that weekly waste and fortnightly recycling collections together with a new weekly food waste collection service will commence in October 2025 and that a simpler weekly collections model will commence from 30 September 2026.

2 of 16 Financial recommendations:

 To recommend to Council on 17 October 2024 that they approve an increase in the budget allocation in the current medium-term financial strategy of £2.73M during 2025/26 to 2027/28 to reflect the additional costs of the new contract with Serco from October 2025 as shown in the table at 11.5.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Waste Service Review Programme (WSRP): Outline Business CaseReport 825 KB DownloadRead as text

At this meeting

Whole meeting
15/24Waste Service Review Programme (WSRP) - Outline Business CaseThis decision

Who was there

7 of 11 attended
PH
Councillor Paul HarveyChair, present
OC
Councillor Onnalee CubittCommittee Member, present
GJ
Councillor Gavin JamesCommittee Member, present
LJ
Councillor Laura JamesCommittee Member, present
AK
Councillor Andy KonieczkoCommittee Member, present
JM
Councillor John McKayCommittee Member, apologies
KM
Councillor Kerry MorrowCommittee Member, present
CT
Councillor Chris TomblinCommittee Member, present
SD
Councillor Sean DillowGuest, in attendance
SM
Councillor Simon Minas-BoundGuest, in attendance
JV
Councillor Jenny VauxGuest, in attendance

On this subject at Basingstoke and Deane

Search all
  1. Waste Service Review Programme (WSRP) - Outline Business CaseThis decision
  2. New food waste collection serviceDecided
  3. Improvements to the Council's Garden Waste ServiceDecided
  4. Improvements to the Council's Garden Waste ServiceApproved

More from Basingstoke and Deane Cabinet

All decisions
MeetingDecisionOutcome
8 Sep 2026 Motion referred from Council - Protecting South Ham And Buckskin Residents From Compulsory Purchase And Ensuring Full Democratic AccountabilityThat Cabinet note the motion referred by Council and agree to progress the actions within the motion in accordance wi... Noted Open
8 Sep 2026 Motion referred from Council - Increasing Biodiversity Net Gain Through the Local PlanThat Cabinet support the direction of travel set out in the motion and continue work through the Local Plan process t... Decided Open
8 Sep 2026 Recommendations from the Environment and Infrastructure Committee – Climate Emergency StrategyThat Cabinet endorse the recommendations of the Environment and Infrastructure Committee and incorporate them into th... Decided Open
8 Sep 2026 Local Plan - Next Steps1) Agree that work on a new local plan should proceed under the new planning system as set out in the Planning and Co... Agreed Open
8 Sep 2026 Regeneration Lettings Plans – Amendment to Housing Allocations Scheme1) Approve the Regeneration Priority Assessment Framework as at Appendix 2 of the report. 2) Authorise the Head of Le... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies