Resolved
Tree Preservation Order BDB/0723 be confirmed.
Development Control Committee decided this item on Wednesday 12 February 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
Tree Preservation Order BDB/0723 be confirmed.
The council made a Tree Preservation Order to protect two woodlands to ensure that the woodlands are fully considered as part of any future change of land use of the wider site. This report summarises the background behind the making of TPO/BDB/0723 and sets out the council’s reasons and basis upon which it is considered that the order should be confirmed (i.e. made permanent).
1 of 8 Glossary of terms
Term Definition The tree preservation order takes immediate effect but only Provisional tree lasts for six months after which it lapses and is of no legal preservation order effect unless it has been confirmed. Tree preservation orders (TPO) should be confirmed (made permanent) within the initial six months. A Tree Preservation Order is an order made by a local planning authority in England to protect specific trees, groups of trees or woodlands in the interests of amenity. An Order prohibits the: cutting down Tree Preservation topping Order lopping uprooting wilful damage wilful destruction of trees without the local planning authority’s written consent.
Main considerations
1 Background and relevant planning history
1.1The woodlands subject to the TPO are located on land to the north of East View, South of Highfields and adjacent to Dummer Down Lane. The juvenile woodlands are a result of replanting that was undertaken after the former woodland was felled circa 2014. Permission for felling was granted by the Forestry Commission and a Restocking Notice also issued.
1.2TPO request T/00130/23/TRQ2 was received on 28th March 2023 following concerns that the woodland was under threat of damage or removal.
1.3The TPO request was reviewed again once the Tree Service was notified of the submission of 23/00567/FUL on 3rd March 2023 proposing the change of use of the existing barn and site to equestrian purposes and the replacement of a field gate onto Dummer Down Lane.
1.4Following further assessment of the subject woodland, TPO/BDB/0715 was subsequently made on 11th December 2023. The provisional 6-month period of TPO/BDB/0715 ended on 11th June 2024. To maintain protection of the trees, TPO/BDB/0723 was subsequently made on 22nd October 2024 and any outstanding representations from TPO/BDB/0715 were to be addressed as part of the confirmation process.
1.5The application site plan for 23/00567/FUL was subsequently revised to exclude the woodlands from the proposed change of use to equestrian purposes and approved by the Development Control Committee on 6th March 2024.
2 of 8 1.6 Existing trees, that is individuals, groups, area and woodland are viewed and assessed for their amenity impact to evaluate their suitability for a TPO. This system is based on factors that assess: -
Their health & condition Their remaining longevity Future consideration Their relative public visibility Specialist considerations such as ‘veteran’ status, historical interest etc. The known (or perceived) ‘threat’ to their health & condition or existence The impact of the trees on the landscape Special factors such as proximity and orientation to the nearest habitable structure.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Confirmation of tree Preservation Order BDB/0723 Land Adjacent to East View, Dummer Down Lane, Dummer, HampshireReport | 358 KB | DownloadRead as text |
PDF |
TPO 0723 Appendix 1: TPO Plan /24Appendix | 609 KB | Download |
PDF |
TPO 0723 Appendix 2: TPO Schedule of Trees /24Appendix | 187 KB | Download |
Follow Development Control Committee at Basingstoke and Deane and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | Applications for planning permission and public participation thereonRESOLVED that : the application be APPROVED subject to the applicant entering into a Section 106 legal agreement unde... | Approved | Open |
| 9 Sep 2026 | Quarterly Planning Appeals ReportRESOLVED that: Members of the Development Control Committee note the outcomes of the appeal decisions and the reasons... | Noted | Open |
| 12 Aug 2026 | Applications for planning permission and public participation thereonRESOLVED that : the application be REFUSED for the following reason: Reason for Refusal 1 The proposed development by... | Refused | Open |
| 8 Jul 2026 | Applications for planning permission and public participation thereonRESOLVED that : the application be APPROVED subject to: · the completion of a Section 106 legal agreement under the T... | Approved | Open |
| 10 Jun 2026 | Applications for planning permission and public participation thereonRESOLVED that : the application be APPROVED subject to: · the completion of a Section 106 legal agreement under the T... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.