CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Basingstoke and Deane Borough Council
Development Control Committee, Wednesday 8 October 2025 at 6.30pm

Applications for planning permission and public participation thereon

Approved Planning 5 papers

AI summaryCouncil approves solar farm at Strattons Farm near Kingsclere subject to a legal agreement on biodiversity net gain, with power delegated to refuse if it is not secured within six months.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedDelegated refusal if agreement not signed in six months
MoneyNot stated
What happens nextLegal agreement within six monthsHead of Planning may refuse if not completed
Who it affectsTadley North, Kingsclere and Baughurst wardLand at Strattons Farm, Newbury Road, Kingsclere

What was decided

Application 24/00852/FUL for a solar farm at Strattons Farm, Kingsclere was approved subject to a legal agreement under the Community Infrastructure Levy Regulations 2010 and Local Plan Policy EM4, securing biodiversity net gain significant features. Report P2

If the legal agreement is not satisfactorily secured within six months of the meeting, the Head of Planning and Infrastructure is delegated to refuse permission.

The approval is subject to conditions, including development in accordance with the approved plans and commencement within three years of the permission date.

Why

Officers concluded that the Public Sector Equality Duty had been applied, noting that although no medical evidence was provided, the assessment treated this as a protected characteristic and weighed any adverse impact in the planning balance. Report P8

The applicant confirmed in writing that a grid connection has been secured with the operator for October 2028, and concerns about NESO Gate 2 methodology and the speculative nature of the scheme were not considered to alter the planning balance. Report P9

National Planning Policy Framework paragraph 168 does not require applicants to demonstrate the overall need for renewable energy development, and the system should support the transition to net zero by 2050. Report P10

What happens next

The applicant and the council must complete a legal agreement securing biodiversity net gain significant features within six months of the meeting on 8 October 2025, or the Head of Planning is delegated to refuse permission.

Development must begin before the expiration of three years from the date of the planning permission.

Options considered

  • Chosen: Approve subject to legal agreement for biodiversity net gain. Officers considered planning balance, including energy benefits and equalities, to be acceptable subject to securing BNG Report P2, P8, P9, P10

Implications

  • Legal: A section 106-style legal agreement under the CIL Regulations 2010 and Policy EM4 is required before permission is issued.
  • Equalities: Officers concluded the Public Sector Equality Duty was applied; the lack of medical evidence did not prevent a finding of some adverse impact, which was weighed in the planning balance. Report P8
  • Climate: The proposal is treated as renewable energy development supporting the transition to net zero by 2050 under NPPF paragraph 161, though its specific contribution to energy security and net zero was questioned by objectors. Report P7, P9, P10
  • Risk: Objectors raised concerns that the grid connection is uncertain and that Kingsclere sub-station is subject to planned upgrades and a transmission-level review; officers accepted the applicant's confirmation of an October 2028 connection date. Report P7, P9

Who and where

  • Residents and landowners near Strattons Farm, Kingsclere, including those raising medical and grid-connection concerns Report P6, P7, P8
  • Tadley North, Kingsclere and Baughurst ward councillors and the local planning authority Report P2
  • The applicant and the National Energy System Operator in relation to grid connection Report P7, P9

Timeline

  • 8 October 2025: Development Control Committee meeting and resolution to approve subject to legal agreement Report P1
  • Within 3 years of the planning permission: Development must be begun
  • October 2028 (as confirmed by the applicant): Grid connection to Kingsclere sub-station expected Report P9

Plain English for the jargon

  • BNG: Biodiversity Net Gain, a requirement that development leaves biodiversity in a better state than before.
  • PSED: Public Sector Equality Duty, the duty under the Equality Act 2010 to consider the impacts of decisions on protected groups.
  • NPPF: National Planning Policy Framework, the government's planning policy guidance.
  • NESO: National Energy System Operator, the body that manages energy connections and Gate 2 methodology.
  • EM4: A policy in the Basingstoke and Deane Local Plan 2011-2029, referenced for developer contributions.
  • CIL Regulations 2010: Community Infrastructure Levy Regulations, the legal basis for planning obligations.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item47/25

Resolved

RESOLVED that: the application be APPROVED subject to the applicant entering a legal agreement (in accordance with the Community Infrastructure Levy Regulations 2010 and Policy EM4 of the Basingstoke and Deane Local Plan 2011-2029) between the applicant and the Borough Council to secure: · BNG – significant features. Should the requirements set out above not be satisfactorily secured within 6 months of the date of the meeting, then the Head of Planning and Infrastructure be delegated to REFUSE permission for appropriate reasons. The decision is approve is also subject to the following conditions and informatives:- Conditions 1. The development hereby permitted shall be carried out in accordance with the following approved plans: Proposed Site Layout – drawing no AEM023-PL-01_rev 12 33kV Brick Built Substation – drawing no AEM023-SD-01_rev 01 Cable Trench 600mm – drawing no AEM023-SD-02_rev 02 40ft Solar Inverter – drawing no AEM023-SD-03_rev 01 Internal Access Track – drawing no AEM023-SD-04_rev 01 40ft Customer Switchgear – drawing no AEM023-SD-05_rev 01 CCTV Camera and Post – drawing no AEM023-SD-07_rev 03 27.5° Panel Cross Section – drawing no AEM023-SD-10_rev 01 40ft Solar Inverter with Concrete Posts – drawing no AEM023-SD-11 rev 03 Cable Trench 1000mm – drawing no AEM023-SD-12 rev 01. REASON : For the avoidance of doubt and in the interests of proper planning. 2. The development hereby permitted shall be begun before the expiration of 3 years from the date of this planning permission. REASON: To comply with Section 91 of the Town and Country Planning Act 1990 and to prevent an accumulation ... view the full minutes text for item 47/25
Word for word from the decision Basingstoke and Deane published for this meeting. Source: democracy.basingstoke.gov.uk

Follow this further

Built from Basingstoke and Deane's papers

What the report saysPro

Report to Development Control Committee

BASINGSTOKE & DEANE BOROUGH COUNCIL DEVELOPMENT CONTROL COMMITTEE – 8th October 2025 UPDATE

Item Ref No Address Ward Councillor Recommendation No 1 24/00852/FUL Land At Strattons Cllr Kerry Morrow Approve subject to Farm, Newbury Cllr Mike Bound Legal Agreement Road, Kingsclere Cllr David Conquest Tadley North, Kingsclere & Baughurst

Agenda Page: 21 Officer Presenting: Brian O’Donovan

Update

Representations

Following the publishing of the main paper, two additional letters from the public were received in objection to the application, summarised as:

- Further details provided in relation to a medical condition of a local resident and concerns over lack of communication in relation to providing or need to provide any additional details in this regard - Concern that the Public Sector Equality Duty has not been applied correctly - There is no public record of a connection date to the grid and there are planned upgrades to Kingsclere sub-station in the period up to 2028/29, whilst the SSEN capacity map shows it is subject to transmission level review which could potentially cause delays to connection - The proposal could not qualify as a “Protected Project” under NESO Gate 2 methodology and is a speculative attempt to support a position in the connection queue and does not support timely transition to low carbon energy. - Concerns that the Officers report accepts and repeats the references in the submitted Planning Statement to 2030 connection targets and whether this evidence is credible and relevant and having regard to the implications to the public benefits - The proposals contribution to energy security and net zero targets is speculative and the impact on landscape character cannot be justified by uncertain public benefits Officer Comments:

Having regard to the comments received in relation to medical/health issues and the application of the Public Sector Equality Duty (PSED), it is clarified that the main report notes the lack of medical evidence provided but that this was not intended to be an invitation/requirement for additional information to be provided nor was it questioning the validity of any of the previous representations. The reference to this was only to be transparent about not having reviewed such evidence. However, Sections 9.2 to 9.4 of the main report confirmed in any case that whilst no medical evidence was provided, the assessment considered that from the information provided this would amount to a protected characteristic. Therefore, the PSED has been applied in the main report with full consideration of the impacts of the proposed development and given it was concluded to have some adverse impact, it has been weighed accordingly in the planning balance.

Having regard to comments in relation to concerns over the point of connection to the network and deliverability of the connection to Kingsclere substation, as outlined in the main report the applicant has confirmed in writing that a gird connection has been secured with the operator for October 2028. Concerns have also been raised about the speculative nature of the application and how it is not considered a “Protected Project” under NESO methodology. In this regard, whilst not a planning document, NESO’s Gate 2 methodology, includes several other scenarios that would enable a project to qualify for protections. Having regard to concerns over the report in the main paper’s application of the public benefits of the scheme, there are considered to be no further implications on the planning balance assessment undertaken as a result of these points raised.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
08.10.2025 Update Front Sheet /25Frontsheet 218 KB Download
PDF
08.10.2025 Update Report /25Report 225 KB DownloadRead as text
PDF
Applications /25Report 5.9 MB Download
PDF
Applications for planning permission and public participation thereonReport 360 KB Download
PDF
Index /25Report 10 KB Download

At this meeting

Whole meeting

Who was there

11 of 12 attended
TD
Councillor Tony DurrantChair, present
AM
Councillor Andrew McCormickCommittee Member, present
MB
Councillor Mike BoundCommittee Member, present
RC
Councillor Richard CourtCommittee Member, present
AF
Councillor Angie FreemanVice-Chair, present
PG
Councillor Paul GaskellCommittee Member, present
SG
Councillor Sheena GrassiCommittee Member, present
RH
Councillor Ronald HusseyCommittee Member, present
JJ
Councillor Julian JonesCommittee Member, present
PM
Councillor Paul MillerCommittee Member, present
KW
Councillor Karen WattsCommittee Member, present
KF
Katherine Fitzherbert-GreenOfficer, expected

On this subject at Basingstoke and Deane

Search all
  1. Applications for planning permission and public participation thereonThis decision
  2. Applications for planning permission and public participation thereonApproved
  3. Applications for planning permission and public participation thereonRefused
  4. Applications for planning permission and public participation thereonApproved
  5. Applications for planning permission and public participation thereonApproved
  6. Applications for planning permission and public participation thereonApproved

More from Basingstoke and Deane Development Control Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Applications for planning permission and public participation thereonRESOLVED that : the application be APPROVED subject to the applicant entering into a Section 106 legal agreement unde... Approved Open
9 Sep 2026 Quarterly Planning Appeals ReportRESOLVED that: Members of the Development Control Committee note the outcomes of the appeal decisions and the reasons... Noted Open
12 Aug 2026 Applications for planning permission and public participation thereonRESOLVED that : the application be REFUSED for the following reason: Reason for Refusal 1 The proposed development by... Refused Open
8 Jul 2026 Applications for planning permission and public participation thereonRESOLVED that : the application be APPROVED subject to: · the completion of a Section 106 legal agreement under the T... Approved Open
10 Jun 2026 Applications for planning permission and public participation thereonRESOLVED that : the application be APPROVED subject to: · the completion of a Section 106 legal agreement under the T... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies