Basingstoke and Deane Borough Council
Development Control Committee, Wednesday 25 February 2026 at 6.30pm

Applications for planning permission and public participation thereon

Approved Planning 5 papers

AI summaryBasingstoke and Deane Council approved four dwellings at Mac's Field, St Mary Bourne, subject to a legal agreement for on-site biodiversity net gain. The scheme follows minor amendments to plot 4's layout and design.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedSubject to Section 106 legal agreement and conditions
MoneyCIL liableOne market dwelling and three self-build plots; CIL payable
What happens nextLegal agreement to be completed
Who it affectsNot stated

What was decided

The application was approved, subject to completion of a legal agreement securing significant on-site biodiversity net gain enhancements, and subject to the conditions set out in the report.

The Planning and Development Manager was delegated to grant permission once the legal agreement is in place, or to refuse if the biodiversity requirement is not satisfactorily secured.

This was a revised scheme reconsidered after minor amendments to plot 4's plot size, dwelling width, and the relocation of a single-storey element from the side to the rear. Report 1.1, 4.2, 4.3, 4.4

Why

Officers accepted that the four-dwellings scheme would cause less than substantial harm to the St Mary Bourne Conservation Area and a small degree of landscape harm within the North Wessex Downs National Landscape, but judged that the public benefits of new housing, economic activity and biodiversity enhancements outweighed the identified harms. Report 10.4, 10.5, 10.7, 10.8

The council cannot currently demonstrate a deliverable five-year housing supply, meaning the countryside policy (SS6) is considered out of date and the tilted balance under NPPF paragraph 11(d) applies. Report 10.3

Officers concluded that surface water flood risk and the absence of a Sequential Test represented only a minor conflict, with mitigation measures proposed; revised plot 4 sits further from the identified flood area, giving a modest drainage benefit. Report 8.11, 10.6

What happens next

The applicant must enter into a legal agreement with the council to secure significant on-site biodiversity net gain enhancements before permission can be issued. Report P151, P152

Several pre-commencement conditions must be discharged before development begins, covering archaeology, tree protection, a Construction Environmental Management Plan, drainage, nutrient mitigation, and a Biodiversity Gain Plan. Report P69, P70, P71, P72, P73, P89, P90, P91

The development must begin within three years of the date of the planning permission. Report P68

The money

  • 37.13% Biodiversity net gain increase from baseline originally proposed; to be maintained Report 8.16

Options considered

  • Chosen: Approve subject to Section 106 legal agreement and conditions. Public benefits of four dwellings and biodiversity gains outweighed less than substantial heritage harm, minor landscape harm and flood risk conflict; tilted balance applied due to lack of five-year housing supply. Report 10.3, 10.5, 10.6, 10.8
  • Rejected: Refuse. Officers considered harms limited and not sufficient to justify refusal when weighed against housing delivery and other public benefits; delegated refusal only if biodiversity legal agreement is not secured. Report 10.8

Implications

  • Legal: Permission is subject to a Section 106 legal agreement to secure on-site biodiversity net gain; a Biodiversity Gain Plan must also be approved before development begins. Report P89, P90, P91
  • Financial: The development is CIL liable (one market dwelling and three self-build plots); a separate CIL Liability Notice will be issued. Report 9.1, P142, P143
  • Equalities: All four dwellings must be constructed to accessible and adaptable Building Regulations M4(2) standards. Report P73
  • Climate: Conditions require a water efficiency standard of 110 litres per person per day and address nutrient neutrality affecting internationally protected habitat sites; an informative draws attention to the council's Climate Emergency declaration. Report P73, P87, P133
  • Environment: Conditions secure ecological mitigation, bat-sensitive lighting, great crested newt District Licensing compliance, tree protection, landscaping, and a Construction Environmental Management Plan. Report P70, P71, P72, P77, P80, P81
  • Risk: A land contamination informative requires any discoloured, odorous or hazardous soils to be reported and remediation approved before works resume. Report P136

Who and where

  • Neighbouring residents of Bells Meadow (especially No. 8) and the St Mary Bourne Bowls Club to the east Report 8.12, 8.13
  • St Mary Bourne Parish Council (majority vote of 5 to 4, no objection) Report P27
  • Users of St Mary Bourne Footpath 38, which runs near the southern boundary Report P140
  • Bourne House (Dipland House) and associated Dipland Court/Lodge, identified as non-designated heritage assets Report 8.6, 3.4

Timeline

  • 14 January 2025: Planning application registered Report P150
  • 3 April 2025: Application expiry date Report P150
  • 7 January 2026: Initial Development Control Committee resolved to approve, subject to legal agreement Report 1.1
  • 09/01/2026: Re-consultation letters issued on revised scheme to neighbours and Parish Council Report P22
  • 29/01/2026: Parish Council comment submitted (majority no objection, 5 to 4) Report P27
  • 30/01/2026: Re-consultation period closed; no public representations received Report P22
  • 25 February 2026: Development Control Committee approved the revised scheme, subject to legal agreement and conditions
  • Within 3 years of permission: Development must begin Report P68

Plain English for the jargon

  • Biodiversity Net Gain (BNG): A measurable improvement in habitat biodiversity resulting from a development, calculated as a percentage increase from a baseline survey.
  • Community Infrastructure Levy (CIL): A charge that local authorities in England can apply to most new development to fund infrastructure.
  • Section 106 agreement (S106): A legal agreement between an applicant and a local planning authority, used to secure planning obligations such as affordable housing or biodiversity enhancements.
  • Sequential Test: A planning test for sites at risk of flooding, requiring development to be directed to land with the lowest risk first.
  • National Landscape: The current name for areas formerly designated as Areas of Outstanding Natural Beauty (AONB), protected for their scenic quality.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item77/25

Resolved

RESOLVED that : the application be APPROVED subject to the application entering into a legal agreement (in accordance with the Community Infrastructure Levy Regulations 2010 and Policy EM4 of the Basingstoke and Deane Local Plan 2016-2029 and Policy P 5 St Mary Bourne Neighbourhood Plan 2016-2029 between the applicant and the Borough Council to secure: · Significant on-site biodiversity net gain enhancements Should the requirements set out above not be satisfactorily secured, then the Planning and Development Manager be delegated to REFUSE permission for appropriate reasons. On completion of the legal agreement the Planning and Development Manager be delegated to grant planning permission subject to the conditions and informatives set out below. Conditions 1 The development hereby permitted shall be carried out in accordance with the following approved plans: Location plan - dwg no. P01 rev B Block plan - dwg no. P02 rev F Proposed site plan - dwg no. P03 rev F Street scene/ section - dwg no. P05 rev C House 1 Plans - dwg no. P10 rev C House 1 Elevations - dwg no. P11 rev C House 2 Plans – dwg no. P20 rev B House 2 Elevations – dwg no. P21 rev D House 3 Plans - dwg no. P30 rev F House 3 Elevations - dwg no. P31 rev F House 4 Plans - dwg no. P40 rev B House 4 Elevations - dwg no. P41 rev B Detached carport plans and elevations - dwg no. P50 rev A Bin and Cycle Store Plans and Elevations - dwg no. 52 rev A REASON: For the avoidance of doubt and in the interests of proper planning. 2 The development hereby permitted shall be begun before the expiration of 3 years from the date of this planning permission. REASON: To comply with Section 91 of the Town and Country Planning Act 1990 and to prevent an accumulation of unimplemented planning permissions. 3 No development (including site clearance and preparation) shall take place until: 1. The applicant has secured the implementation of a programme of archaeological evaluation, in accordance with a Written Scheme of Investigation (WSI) that has been submitted to and approved in writing by the Local Planning Authority. 2. Following evaluation, the applicant has secured the implementation of a programme of archaeological mitigation of impact, also in accordance with an approved WSI. 3. Following the completion of archaeological fieldwork, to be undertaken in accordance with the WSI, the applicant shall submit a report in accordance with a programme previously approved in ... view the full minutes text for item 77/25
Word for word from the decision Basingstoke and Deane published for this meeting. Source: democracy.basingstoke.gov.uk

Follow this further

Built from Basingstoke and Deane's papers

What the report saysPro

Report to Development Control Committee

Summary

1.1This application was debated at the Development Control Committee on 7th January 2026, where it was resolved to approve the application, subject to the completion of a legal agreement. The application has now been modified to make a minor amendments to the arrangement for plot 4, including a change to the red edge, which impacts the arrangement of plot 4 and the design of the dwelling.

1.2This report does not intend to repeat the full assessment of the application but will address the specific modifications to the scheme. The Committee Report (Appendix A) and Update Paper (Appendix B) outline the assessment of the application in all other respects and this assessment has not changed. Consequently, the recommendation to approve the application remains, subject to the completion of a Section 106 agreement and conditions listed and the end of this report.

2 REASON FOR COMMITTEE DETERMINATION

2.1The Application has been brought to Development Control Committee in line with the Scheme of Delegation due to the number of objections received and the Officer's recommendation for approval.

3 DESCRIPTION OF THE SITE AND ITS SURROUNDINGS

3.1The report attached at Appendix A has the description of the site and its surroundings.

4 DESCRIPTION OF THE PROPOSAL AND ANY RELEVANT PLANNING HISTORY

Description

4.1The report attached at Appendix A has the description of the main proposal and planning history. Set out below is the proposed change to the scheme as originally considered.

4.2The site area allocated to Plot 4 has been marginally reduced by 2m², resulting in a slight decrease in the overall size of the application site. The proposal reduces the width of the plot from 22m to 13.3m and increases its length by 11.8m to align with the adjoining Plot 3 to the west.

4.3As part of the revised site layout, the design of the dwelling has been amended, with the overall width of the building reduced by 3.6m. This alteration effectively relocates the single-storey side element from the side elevation to the rear of the property.

4.4The revised Plot 4 would now incorporate a single-storey, flat-roofed rear extension measuring 3.2m by 7m, with an overall height of 3.2m.

4.5As such, the Location Plan, Block Plan, Site Plan, Elevation, Street Scene and Floor plans for Plot 4 have been revised.

5 DEVELOPMENT PLAN

5.1Basingstoke and Deane Local Plan 2011-2029

The report attached at Appendix A has the list of relevant Policies. There have been no changes since then. 5.3 St Mary Bourne Neighbourhood Plan 2016-2029

The report attached at Appendix A has the list of relevant Policies. There have been no changes since then.

6 MATERIAL PLANNING CONSIDERATIONS

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Applications /25Report 2.4 MB DownloadRead as text
PDF
Applications for planning permission and public participation thereonReport 160 KB Download
PDF
Index /25Report 38 KB Download
PDF
Update Front Sheet: 25.02.2026 /25Frontsheet 69 KB Download
PDF
Update Paper /25Report 115 KB Download

At this meeting

Whole meeting
77/25Applications for planning permission and public participation thereonThis decision
78/25Amendment to Resolution to Grant Planning Permission subject to Section 106 Agreement for application 24/00930/FULApproved

Who was there

11 of 12 attended
TD
Councillor Tony DurrantChair, present
AM
Councillor Andrew McCormickCommittee Member, present
MB
Councillor Mike BoundCommittee Member, present
RC
Councillor Richard CourtCommittee Member, present
AF
Councillor Angie FreemanVice-Chair, present
JG
Councillor Jay GaneshCommittee Member, present
PG
Councillor Paul GaskellCommittee Member, present
SG
Councillor Sheena GrassiCommittee Member, present
RH
Councillor Ronald HusseyCommittee Member, present
JJ
Councillor Julian JonesCommittee Member, present
KW
Councillor Karen WattsCommittee Member, present
KF
Katherine Fitzherbert-GreenOfficer, expected

On this subject at Basingstoke and Deane

Search all
  1. Applications for planning permission and public participation thereonThis decision
  2. Applications for planning permission and public participation thereonApproved
  3. Applications for planning permission and public participation thereonRefused
  4. Applications for planning permission and public participation thereonApproved
  5. Applications for planning permission and public participation thereonApproved
  6. Applications for planning permission and public participation thereonApproved

More from Basingstoke and Deane Development Control Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Applications for planning permission and public participation thereonRESOLVED that : the application be APPROVED subject to the applicant entering into a Section 106 legal agreement unde... Approved Open
9 Sep 2026 Quarterly Planning Appeals ReportRESOLVED that: Members of the Development Control Committee note the outcomes of the appeal decisions and the reasons... Noted Open
12 Aug 2026 Applications for planning permission and public participation thereonRESOLVED that : the application be REFUSED for the following reason: Reason for Refusal 1 The proposed development by... Refused Open
8 Jul 2026 Applications for planning permission and public participation thereonRESOLVED that : the application be APPROVED subject to: · the completion of a Section 106 legal agreement under the T... Approved Open