Internal Audit Progress Report (December 25 - March 26)

Decided Finance 6 papers

AI summaryBasingstoke and Deane Audit and Accounts Committee considered the Internal Audit Progress Report covering December 2025 to March 2026, noting 32 overdue significant and fundamental recommendations and 47 not yet due.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedCommittee considered the Internal Audit Progress Report
MoneyNo financial implications stated in the report
What happens nextContinue 2025/26 planAudits in testing and draft stages in progress
Who it affectsCouncil governance and risk managementAffects officers implementing audit recommendations

What was decided

The Committee considered the Internal Audit Progress Report covering December 2025 to March 2026 and noted its contents. Report 1.1, P3

Why

The report informs members of the Audit and Accounts Committee of work completed against the 2025/26 Internal Audit Plan and the current position with audit recommendations. Report 1.1, 1.2, 2.2

The report highlights higher-risk audits (Reasonable or Limited assurance), lower-risk audits (Full or Substantial Assurance), and overdue significant and fundamental recommendations. Report 1.2, P3, 3.1

What happens next

Audits in testing stage continue: Staffing, Skills and Capacity; Waste Contract; Information Management. Report P41

Audits in draft report stage: Project Management; Fees and Charges; IT Critical Systems; Major Strategic Projects. Report P42

Owners of audit recommendations are requested to provide progress updates until they are evidenced as complete. Report 8.7, P71

Implications

  • Risk: Implementation of audit recommendations improves the council's control environment, reducing the likelihood of error and fraud. Report P62
  • Legal: No legal implications with this report. Report 8.1, P60
  • Financial: No financial implications with this report. Report P61
  • Staffing: No HR implications with this report. Report 8.8, P75
  • Other: The report assists the Head of Audit, Fraud and Insurance with the annual opinion on the council's risk management, control and governance processes. Report P62

Who and where

  • The Head of Audit, Fraud and Insurance, who provides the annual opinion on the council's risk management, control and governance Report 2.1, 2.2, P62
  • Officers who own audit recommendations, who must provide progress updates until completion Report 8.7, P71
  • Service areas with overdue recommendations, including 32 overdue fundamental and significant recommendations Report 4.1, P29, P36

Timeline

  • 31st March 2025: The 2025/26 Internal Audit Plan was approved by the Audit and Accounts Committee. Report 2.2, 9.1, P77
  • December 2025 to March 2026: Reporting period for the audit work summarised in this progress report. Report 1.1, P3
  • 30th March 2026: Audit and Accounts Committee meeting at which the report was considered. Report P77
  • 2026/27: The Health and Safety audit was deferred to this year because of ongoing work by HR Services. Report P46

Plain English for the jargon

  • BIA: Business Impact Assessment, used within Service Recovery Plans.
  • BCSG: Business Continuity Steering Group, chaired by the Deputy Chief Executive.
  • CIL: Community Infrastructure Levy, referenced in the Treasury Planning audit.
  • HClic: Homelessness Case Level Information Collection, the statutory reporting tool for homelessness casework.
  • MoU: Memorandum of Understanding, here the Hampshire and Isle of Wight Local Resilience Forum mutual aid arrangement.
  • SLA: Service Level Agreement, here the ended Hampshire County Council civil protection SLA.
  • SRP: Service Recovery Plan, the business continuity plan owned by each service.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item48/25

Resolved

The Committee considers the Internal Audit Progress Report (December 25- March 26) and notes the contents of the ... view the full minutes text for item 48/25
Word for word from the decision Basingstoke and Deane published for this meeting. Source: democracy.basingstoke.gov.uk

Follow this further

Built from Basingstoke and Deane's papers

What the report saysPro

Report to Audit and Accounts Committee

Executive summary

1.1This report provides the Audit and Accounts Committee with details of the work carried out against the 2025/26 Internal Audit Plan between December 2025 & March 2026.

1.2To assist the Committee's focus on the key areas, this report provides the following information:

• Paragraph 3.1 - Audit reports in this period of a higher risk, i.e. Reasonable or Limited assurance • Paragraph 3.2 - A summary of the audit report findings of a lower risk (Full or Substantial Assurance) • Overdue significant audit recommendations (Appendix 4) • Other significant & fundamental audit recommendations not yet overdue (appendix 5) • Audit Levels of Assurance definitions & recommendation categories (section 7)

2 Current Position

2.1Internal Audit’s primary objective is to “review the council's risk management, control and governance arrangements through completion of the internal audit plan enabling an annual opinion of the effectiveness of the arrangements to be provided to the executive and the Audit and Accounts Committee. (Taken from the Audit, Fraud & Insurance Improvement Plan 2025-26)

2.2The annual audit plan for 2025/26 was approved by the Audit and Accounts Committee on 31st March 2025 and will assist the Head of Audit, Fraud and Insurance in providing an annual opinion on the effectiveness of the council’s risk management, control and governance processes.

3 Audit Reviews Completed

3.1For this period of work there were three audit reports issued that gave a Reasonable or Limited assurance as per appendices 1 - 3 to this report.

3.2Audit reports issued for this period that were given either Full or Substantial Assurance are summarised in the following table with key points of interest for the Committee listed together with the management response to the audit. Level of Assurance No. of Recommendations Audit 2025/26 2024/25 Fund Sig M/A Business Continuity Substantial Reasonable - 3 2

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
/25Appendix 1 192 KB Download
PDF
/25Appendix 2 244 KB Download
PDF
/25Appendix 3 220 KB Download
PDF
/25Appendix 4 145 KB Download
PDF
/25Appendix 5 161 KB Download
PDF
Internal Audit Progress Report (December 25: March 26)Report 221 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 10 attended
PB
Councillor Paul BashamChair, present
MB
Councillor Michael BlackberryCommittee Member, present
KC
Councillor Kevin ChatburnCommittee Member, apologies
DC
Councillor David ConquestCommittee Member, present
JI
Councillor John IzettCommittee Member, present
SK
Councillor Samir KotechaCommittee Member, present
SM
Councillor Simon Minas-BoundVice-Chair, present
ST
Councillor Sajish TomCommittee Member, apologies
JT
Councillor Jacky TustainCommittee Member, present
RH
Richard Harbord (Co Opted Member of the Audit and Accounts Committee)Committee Member, present

On this subject at Basingstoke and Deane

Search all
  1. Internal Audit Progress Report (December 25 - March 26)This decision
  2. Internal Audit Progress Report (April - June 2026)Decided
  3. Internal Audit Annual Report 2025/26Decided
  4. Internal Audit Plan 2026/27Approved
  5. Internal Audit Progress Report (October - November 2025)Decided
  6. Internal Audit Progress Report (July-September 2025)Noted

More from Basingstoke and Deane Audit and Accounts Committee

All decisions
MeetingDecisionOutcome
1 Jul 2026 EY Audit Planning Report 2025/26The Committee note the EY Planning report. Noted Open
1 Jul 2026 Internal Audit Progress Report (April - June 2026)The Committee considers the Internal Audit Progress Report (April-June 2026) and notes the contents of the report. Decided Open
1 Jul 2026 Internal Audit Annual Report 2025/26The Committee considers the Internal Audit Annual Report 2025/26 and notes the contents of the report. Decided Open
1 Jul 2026 Fraud Update – Protecting The Public PurseThe Committee considers the Fraud Update- Protecting the Public Purse and notes the contents of the report. Decided Open
1 Jul 2026 Local Code of Corporate Governance 2026/2027The Committee approve the . Approved Open