AI summaryCabinet unanimously reaffirmed support for the Somer Valley Enterprise Zone. [D] If the scheme proceeds, up to £53m may be needed from several sources, but no Council budget allocation was approved. [D] [2.2] [P26] [5.5]
Written from the decision and the officer reportPDF Pro
OutcomeDecidedThe Council will continue promoting the scheme. [D] [2.1]
Moneyup to £53m
What happens nextReassess funding before implementationFurther approvals are required for additional funding or measures. [P50] [5.6]
Who it affectsSomer Valley Enterprise ZoneJobs, business space, infrastructure and local travel. [P8] [P9] [5.2] [8.2]
What was decided
Cabinet unanimously reaffirmed its commitment to promoting the scheme, while recognising potential viability concerns. [D] [2.1] Report 2.1
It acknowledged that, if the scheme proceeds, up to £53m may need securing from further Council investment, other public funding, public loans and developer partnership. [D] [2.2] [P25] Report 2.2, P25
This decision creates no obligation to allocate Council budget or pay a specified amount. Further Council investment would need later approval. [P26] [5.5] [5.6] Report P26, 5.5, 5.6
Why
The draft assessment says the scheme is not currently viable for delivery by the private sector, even with Council land assembly, highway work and site preparation. It may need more public support. [P23] Report P23
Advice and assumptions about the viability deficit are still changing. Reaffirmation is needed to support the CPO and show how any shortfall could be met. [P24] [P36] Report P24, P36
Long delivery, changing rents and build costs, and a possible developer partner could reduce the shortfall. The assessment may change. Land receipts, higher rents, changes in property yields and direct Council delivery could also improve the position. [P31] [P33] [P34] [P39] [P40] [P41] [P42] [P43] Report P31, P33, P34, P39, P40, P41, P42, P43
What happens next
Progress the CPO and related SRO, land assembly and enabling works. It is intended to submit a Full Business Case in 2026. [P30] [5.2] [5.4] Report P30, 5.2, 5.4
Explore further Council investment, capital from land receipts, regional or national grants and an in principle Public Works Loan Board loan. The Council is taking advice on procuring a developer partner. [P26] [P27] [P28] [P29] [P39] Report P26, P27, P28, P29, P39
Reassess the funding position before affirming implementation of the CPO and scheme. Obtain further approvals before committing additional funding. [P50] [5.6] Report P50, 5.6
The money
up to £53m Potential amount needing several funding sources. No Council budget allocation is approved. [D] [2.2] [P26] [5.5] Report 2.2, P26, 5.5
£9.3m Accepted WECA Investment Fund grant for land assembly and technical design. [P21] [5.1] Report P21, 5.1
£29.9m Total estimated cost for the next stage, covering OBC+ and FBC activities. [5.4] Report 5.4
£28.8m Proposed WECA grant request for the next stage. [5.4] Report 5.4
£1.1m B&NES match funding for project implementation. [5.3] Report 5.3
£20.6m Total project implementation cost targeted through the Full Business Case in 2026. [5.2] Report 5.2
£19.5m Proposed WECA grant request towards implementation costs. [5.2] Report 5.2
£6.4m Estimated capital from land receipts that could reduce the funding need. [P39] [P40] Report P39, P40
Options considered
Chosen: Reaffirm support and pursue funding measures. Continued support is critical to securing the CPO and delivering the scheme, while other options are pursued in parallel. [D] [P77] [P78] Report P77, P78
Rejected: Do nothing. Without continued support for further investment, there is considerable risk to securing the CPO. If the CPO is not secured, the scheme will not come forward. [P77] Report P77
Rejected: Delay promoting the CPO. Delay could prolong uncertainty for landowners and risk funding already committed or expected. The Council considers the scheme should come forward now. [P78] Report P78
Implications
Financial: Up to £53m may be needed, but this decision allocates no budget and sets no payment amount. [D] [2.2] [P26] Report 2.2, P26
Legal: CPO guidance requires confidence that resources are likely to be available and the scheme has a reasonable prospect of full delivery. [P36] Report P36
Risk: The private sector may not develop the plots without more public support. [P30] Report P30
Financial: Additional Council borrowing could add revenue financing costs to the Council's revenue budget. [P51] [5.7] Report P51, 5.7
Risk: A developer partner could reduce delivery costs and Council risk, subject to a negotiated contract. [P29] Report P29
Climate: The scheme includes a new cycle link, a bus stop, EV charging and 100% regulated operational carbon emission reduction. [8.2] [8.3] Report 8.2, 8.3
Equalities: An Equality Impact Assessment is complete, and the decision is not considered to change its conclusions. [7.3] Report 7.3
Other: The scheme could create up to 1,300 jobs and up to circa 35,800 sqm of commercial floorspace. [P8] [P9] Report P8, P9
People seeking local employment in Somer Valley Report P8
Businesses and employers in Somer Valley Report P9, P10
Developers and occupiers at the enterprise zone Report P14, P16, P29
Consultants advising on funding and procurement Report P27, P29
People making journeys in Somer Valley Report 8.2
Bath and North East Somerset Council Report P26, P51
Timeline
2007: The site was allocated as an employment site. [P11] Report P11
March 2019: The Council declared a Climate Emergency. [8.1] Report 8.1
February 2024: Cabinet approved the LDO and the Ambitions Paper. [P16] [P19] Report P16, P19
July 2024 and November 2024: Further decisions committed the Council to land assembly and enabling and infrastructure works. [P20] Report P20
September 2025: Cabinet amended conditions in the LDO for highway design changes. [P18] Report P18
2026: A Full Business Case is intended to secure project implementation funding. [5.2] Report 5.2
2030: The Council committed to achieve carbon neutrality. [8.1] Report 8.1
up to 20 years: The development may take this long to complete. [5.5] Report 5.5
Plain English for the jargon
SVEZ: Allocated enterprise zone at Old Mills, to the north west of Midsomer Norton, covering 13.5 hectares. [P5]
LDO: Local Development Order, granting planning permission for specified uses and reducing planning risk and cost. [P14] [P16] [P17]
CPO: Compulsory Purchase Order, proposed to facilitate land assembly for the scheme. [P30] [P36]
SRO: Side roads order, promoted with the CPO as part of the next stage. [P30] [5.4]
WECA: West of England Combined Authority, whose investment fund has supported the scheme. [P21] [5.1]
OBC+: Outline Business Case ‘+’, used to request the accepted grant funding. [5.1]
FBC: Full Business Case, intended in 2026 to secure project implementation funding. [5.2]
Public Works Loan Board: A possible source of an in principle loan if the viability deficit remains a concern. [P28]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item74
Resolved
RESOLVED (unanimously): (1) To reaffirm the commitment to promoting the Somer Valley Enterprise Zone (SVEZ) scheme, notwithstanding the Council’s recognition of potential viability concerns with the project. (2) If the SVEZ scheme proceeds, to acknowledge that up to £53m may need to be secured from various means to ensure the delivery of the project, including potential further investment from the Council, other public funding sources, public loans and developer partnership.
Word for word from the decision Bath and North East Somerset published for this meeting.Source: democracy.bathnes.gov.uk
2.1Reaffirm its commitment to promoting the SVEZ scheme, notwithstanding the Council’s recognition of potential viability concerns with the project.
2.2If the SVEZ scheme proceeds, acknowledge that up to £53 million may need to be secured from various means to ensure the delivery of the project, including potential further investment from the Council, other public funding sources, public loans and developer partnership.
WORK\79497635\v.2 Printed on recycled paper 3 THE REPORT
Background
(1) The SVEZ is an allocated site (Policy SSV9) within the Local Plan which seeks to deliver a mixed-use commercial development in the Somer Valley. The SVEZ is located on 13.5 hectares of land at Old Mills, which is situated to the north-west of Midsomer Norton.
(2) The delivery of the SVEZ is identified as a corporate priority in the B&NES Economic Strategy (2014-2030).
(3) The SVEZ will provide economic, environmental and social benefits including:
a) Supporting the Somer Valley to become self-reliant by enabling economic growth through the creation of up to 1,300 jobs for local people, increasing prosperity in the area.
b) Diversifying the type of employment available in the area, offering flexible space to accommodate new and expanding local businesses and creating up to circa 35,800 sqm of commercial floorspace.
c) Delivering new sustainable and attractive commercial space, addressing business and employment land losses experienced in the Somer Valley.
(4) The SVEZ has been allocated as an employment site since 2007. However, the market has failed to deliver the development due to significant barriers to private sector led intervention. These include:
a) Viability – The Development has not been delivered by the private sector due to the high enabling and infrastructure costs.
b) Land ownership – The land is held in multiple ownerships. This makes the land assembly very complex and requires a comprehensive approach to delivery.
c) Planning consent – Planning permission requires time, cost and risk. The adopted Local Development Order (LDO) reduces the planning risk and cost to future developers and/or occupiers.
3.2Governance
(1) A Local Development Order (LDO) was approved by Cabinet in February 2024 under Decision E3486. The Cabinet approval granted planning permission on the site for the development of plots and buildings within the Use Classes B2, B8, C1, E and sui generis, and related enabling works, subject to conditions and limitations.
(2) The adoption of the LDO addresses a market failure and partially de-risks the delivery of the site through a flexible planning framework. Compliance Applications will allow plots to be delivered in a swifter timeframe than the conventional planning route.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.