Resolved
That the progress on the delivery of the 2008/09 Internal Audit Plan be noted.
Audit Committee noted this item on Tuesday 23 September 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
That the progress on the delivery of the 2008/09 Internal Audit Plan be noted.
The Committee is requested to consider the report and if satisfied, to note the progress.
To enable the Committee to review the progress made in respect of the completion of the 2008/2009 Internal Audit Plan.
4. Details
At its meeting held on 30 June 2008 the Committee received the first progress report on the 2008/09 Internal Audit Plan. I am able to report that in addition to completing those audits which were shown as being in progress at that time, a further eleven audits have now been completed and seven are currently in progress.
Detailed in Appendix A is the 2008/2009 agreed internal audit plan together with the current status of the individual audit assignments.
As shown in Appendix A four other audit assignments have also been completed in this period. A sample of the Best Value Performance Indicators have been audited and in accordance with the recommendation from the Audit Commission, arising from their Data Quality review, the results of the audit have been reported to the Strategic Management Team.
Three specific grant aided projects are shown against the contingency provision. The expenditure and the operation of financial controls for the Local Area Agreement and the Growth Area Funding Schemes have been reviewed and certified in accordance with the grant conditions. The grant conditions for the Innovation Centre require an external independent audit. In preparation
Reports/2008/Auidit/102 je for this internal audit have also completed a check of eligible expenditure and ensured that all supporting documentation is available for the external audit.
On the basis of work completed to date there are no issues to raise with the Committee. At this point in time it is anticipated that the plan will be completed with existing resources.
The Committee is requested to consider and if satisfied, note the progress made.
5. Summary of Consultations and Outcome
The following Council Units or Officers and/or other organisations have been consulted in preparing this report:
Corporate Operational Management Group
No adverse comments have been received.
6. Ward Councillor Views Not applicable for this report
Report Contact Officer: Philip Houghton File Reference: A6 Previous Relevant Minutes: Minutes 18 of 25 September 2007, 26 of 15 January 2008, 37 of 3 April 2008 and 9 of 30 June 2008. Background Papers: None Appendices: A
Reports/2008/Auidit/102 je Bedford Borough Council Appendix A Internal Audit Plan 2008/09
Key:- Outstanding In-Progress Completed
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Delivery of 2008/09 Internal Audit PlanReport | 4 pages | DownloadRead as text |
Follow Audit Committee at Bedford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | MinutesThat the of the meeting of the Committee held on 21 July 2026, be confirmed. Chair | Decided | Open |
| 9 Sep 2026 | KPMG: External Auditor - Draft Audit Results Report 2025/26 - Bedfordshire Pension FundRESOLVED That the Committee considered the draft Audit Results Report 2025/2026 for Bedfordshire Pension Fund issued ... | Noted | Open |
| 9 Sep 2026 | KPMG: Value For Money 2025/26 - VFM Risk Assessment Report - Bedford Borough CouncilRESOLVED That the Committee considered and were satisfied, to note the report. HOA | Noted | Open |
| 9 Sep 2026 | Internal Audit Plan Update 2026/27RESOLVED That the Committee considered the report and was satisfied to acknowledge the progress made to date against ... | Approved | Open |
| 9 Sep 2026 | Report on Fraud and Corruption 2025/26RESOLVED That the Committee considered the report, sought clarification, and noted, (a) The Council’s performance in ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.