RESOLVED : (1) That the contents of the report including the Project update be noted. (2) That the proposed criteria, sub criteria and weightings to be used to evaluate bidders’ submissions during the procurement for the long term residual waste treatment contract, be agreed. (3) That the Executive Director for the Environment and Sustainable Communities, in consultation with the Portfolio Holder (Environment), be authorised to make minor and consequential amendments to the criteria. Reason for Decision To agree the criteria and weightings to be used in order to evaluate the submissions for the procurement of the long term residual waste treatment contract. (Note: Councillors Headley, Hodgson and Sawyer requested that their vote against the decision be recorded.) DCPS & DepCEX
Word for word from the decision Bedford published for this meeting.Source: councillorsupport.bedford.gov.uk
1.1At its meeting on 7 October 2008 the Implementation Executive approved the submission to DEFRA of the Outline Business Case (OBC) for the BEaR project as part of the process to secure PFI funding for the procurement of a long term residual waste treatment solution. 1.2 As part of the process for preparing for procurement it is necessary to determine the evaluation criteria which will be used during the assessment of tenders for the residual waste treatment contract. This report details the basis of the evaluation strategy, summarises the methodology of the evaluation process and outlines the approach undertaken in developing the proposed criteria. 1.3 The report also provides the Implementation Executive with a summary of work carried out since the OBC approval in October 2008, an overview of the next steps in the delivery of the Project and a summary of the key objectives of the contract to be let
Recommendation
2.1The Implementation Executive is requested to consider, and if satisfied, (a) Note the contents of this report including the Project update; (b) Agree the proposed criteria, sub criteria and weightings to be used to evaluate bidders’ submissions during the procurement for the long term residual waste treatment contract; (c) Authorise the Executive Director for the Environment & Sustainable Communities, in consultation with the Portfolio Holder (Environment), to make minor and consequential amendments.
Reason for recommendation
3.1Recommendation (b): Item 8, Section C of the Joint Working Agreement (JWA) identifies the approval of the evaluation criteria as a “Reserved Matter” for agreement by each Council. The evaluation criteria have been developed to enable all technologies to be evaluated on an equal basis and that there is no bias towards any technology. The waste treatment solution will be procured on technology neutral basis (i.e. no preferred technology choice). 3.2 Recommendation (c): The production of the Evaluation Criteria is a complex process following tight timescales. Due to the amount of work involved and the constantly changing market conditions the criteria and weightings for each stage of the procurement are not yet finalised. The criteria and weightings must be provided to bidders ahead of each procurement stage and the Team would work to ensure that they were finalised ahead of this time. This report to the Implementation Executive along with the attached Appendices’ details the high level criteria and weightings which are unlikely to change.
4 Key Issues/Risk Assessment
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.