Description of Decision (1) That the performance achieved in relation to the Capital Programme Schemes substantially completed in 2008/2009, be acknowledged. (2) That, when new bids for funding are considered at the next meeting of the Executive, only priority schemes which are: - Legally/contractually unavoidable; - Essential for health and safety reasons; - Support corporate objectives or benefit from external funding opportunities; or - “Invest to Save” projects (depending upon the length of the investment payback period) will be approved for public consultation. (3) That consideration of capital programme bids must have regard to the Comprehensive Area Assessment “Use of Resources” assessment in terms of affordable, links to priorities and outcomes. Reason for Decision To consider the outturn performance of the Council’s Capital Programme in 2008/2009 and to ensure the future funding of capital investment is based upon meeting priority needs within affordability levels.
Word for word from the decision Bedford published for this meeting.Source: councillorsupport.bedford.gov.uk
The Executive is requested to consider the report and, if satisfied, to:
(i) Acknowledge the performance achieved in relation to the Capital Programme Schemes substantially completed in 2008/2009;
(ii) Approve that, when new bids for funding are considered at the next meeting of the Executive, only priority schemes which are:
- Legally/contractually unavoidable; - Essential for heath and safety reasons; - Support corporate objectives and benefit from external funding opportunities; and; - “Invest to Save” projects (depending upon the length of the investment payback period)
will be approved for public consultation;
(iii) Acknowledge that the consideration of capital programme bids must have regard to the Comprehensive Area Assessment “Use of Resources” assessment in terms of affordable, links to priorities and outcomes.
Reason for recommendations
To enable the Executive to consider the outturn performance of the Council’s Capital Programme in 2008/2009 and to consider the future funding of capital investment based upon meeting priority needs within affordability levels.
rac5160 Executive Capital Programme Update 4. Key Implications
4.1Policy Issues
Full Council, as part of its consideration of the Forward Capital Programme in February each year, must have regard to the CIPFA Prudential Code and a number of indicators are determined to assist in this process. In essence, these indicators relate to Prudence, Affordability and Sustainability. In other words, is the Capital Programme affordable in both the short and medium term having regard to the expected available capital finance and any revenue implications arising from the schemes, and has the most prudent way of funding the Capital Programme been identified.
The Council has two policies which underpin the Capital Programme, having regard to the prudential indicators, namely the Capital Investment Strategy and the Medium Term Financial Strategy (MTFS). The former provides the framework for the evaluation, approval and monitoring of capital schemes and this includes a requirement for an annual report each September relating to schemes completed in the previous financial year. The MTFS provides the framework for funding the Capital Programme and the relevant extract is reproduced at Appendix A. The Strategy specifically states that “No capital schemes can be authorised and no commitment made until:
Capital finance is in place to cover the full capital costs; and
It has been determined by Council that the ongoing revenue cost consequences are affordable in the light of forward three year Revenue Budget forecasts and related Council Tax consequences”.
All capital programme bids are subject to the completion of a priority evaluation form in accordance with the Capital Investment Strategy. This covers, amongst other things, project risks, resource implications and compliance with the key priorities of the Council.
The Implementation Executive, at its meeting on 12 November 2008, approved the Capital Investment Strategy reproduced at Appendix B. The MTFS requires the Capital Investment Strategy to be reviewed annually and the Implementation Executive were advised that the next review would take place in March 2010, unless any specific issues required a more immediate review. The Strategy provides the framework for submitting and considering new bids and for reviewing the performance of schemes in the approved programme.
4.2Legal Issues
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Social Housing Allocations PolicyDescription of Decision (1) That the publication of the revised Bedford Borough (at Appendix A) on 1st September 2026...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.