A Strategy for Bedford High Street - Supplementary Planning Document (Report of Housing & Planning Portfolio Holder and Assistant Director (Planning and Housing) enclosed)
AgreedExecutive1 paper
Executive agreed this item on Wednesday 11 November 2009. Below is the council's own wording, with the papers it was decided on.
Description of Decision (1) That the draft high street strategy, as set out at Appendix A to the report, be agreed for the purposes of public consultation, subject to the following: To add to the end of section 4 – status of this document - “ the draft high street strategy is consistent with delivery of bedford ’s sustainable community strategy and is identified as a priority within bedford ’s approved infrastructure delivery programme.”; and That the draft high street strategy be strengthened in relation to the early detrafficking of the high street, bedford and to regard this as a priority for change as part of the proposals for the renaissance of bedford high street. (2) That the assistant director (planning and housing) be authorised to make any minor editorial textual changes to appendix a of the report. Reason for Decision To agree the draft strategy for public consultation as part of the process of preparing a Supplementary Planning Document.
Word for word from the decision Bedford published for this meeting.Source: councillorsupport.bedford.gov.uk
Policy TC8 of the adopted Bedford Town Centre Area Action Plan states that the Council will prepare a strategy for the renaissance of Bedford High Street. A draft strategy has been prepared and this is set out in Appendix A. It has three main themes: Restoring the Existing Fabric, Uses and Activity and Access and Movement and lists a number of key actions which will assist with the regeneration of Bedford High Street.
Recommendations
Executive is recommended to:
(a) Consider the draft High Street Strategy set out in Appendix A and subject to any amendments Executive may wish to make, agree the draft for the purposes of public consultation;
(b) Authorise the Assistant Director Planning and Housing to make minor editorial textual changes to Appendix A of the report.
Reasons for recommendations
3.1The purpose of the report is for Executive to agree the draft strategy for public consultation as part of the process of preparing a Supplementary Planning Document.
4. IMPLICATIONS
4.1Legal
Reclassification of the High Street and associated changes in signing so that it ceases to be part of the Primary Route Network will require the appropriate statutory processes to be followed in conjunction with the Government Office. 4.2 Policy
The draft strategy is consistent with the Council’s adopted policies set out in the Bedford Town Centre Area Action Plan.
4.3Resource
The costs of producing the document will be contained within existing budgets.
The draft strategy includes a number of measures to regenerate the High Street. These include:-
a) The need to make provision through the Capital Programme bidding process to support the Townscape Heritage Initiative (THI) and public realm improvements. A bid has been made for £1m with a focus on the restoration of historic buildings and shop frontages/facades, the promotion of upper floor living/working, revised highway signage as a precursor to de-trafficking and public realm improvements to potentially include improved lighting, footway resurfacing, and street furniture to ensure that the traditional character of Bedford High Street is preserved. The capital programme funding would be used as match funding for the THI bid of £1m which is to be submitted by 30 November 2009.
b) A further bid would be required to fund the phased highway improvements set out in the draft strategy.
c) The need to establish a grant scheme to encourage better quality shopfronts and advertisements. There is currently no budget provision for this.
d) The need to establish a dedicated officer resource to drive the strategy forward and administer the relevant schemes. The THI requires the appointment of a THI Project Officer. The costs of this will be met from the THI bid. In addition it is likely that additional officer resource would be needed to deliver the different elements of the strategy including a robust enforcement regime to deal with breaches of planning control.
e) The costs of commissioning the 10 condition surveys and one concept design scheme will be met from an Economic Development town centre projects budget.
The regeneration of the High Street is a long term project and no funding has been identified at this stage for the strategic acquisition of property or to achieve the full aspirations for the High Street.
4.4Risk
The success of the strategy is dependent in part on the success of any bid to establish a Townscape Heritage Initiative. In addition, without an effective strategy there is a risk that the High Street deteriorates further and that the commercial heart of the town centre continues to move further to the west once the Bedford Town Centre West proposals come forward.
5 DETAILS
Background
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
A Strategy for Bedford High Street: Supplementary Planning Document (Report of Housing & Planning Portfolio Holder and Assistant Director (Planning and Housing) enclosed)Supplementary
28A Strategy for Bedford High Street - Supplementary Planning Document (Report of Housing & Planning Portfolio Holder and Assistant Director (Planning and Housing) enclosed)This decision
A Strategy for Bedford High Street - Supplementary Planning Document (Report of Housing & Planning Portfolio Holder and Assistant Director (Planning and Housing) enclosed)This decision
Social Housing Allocations PolicyDescription of Decision (1) That the publication of the revised Bedford Borough (at Appendix A) on 1st September 2026...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.