Work Programme 2009/11

Agreed Scrutiny 1 paper

Scrutiny Committee agreed this item on Thursday 1 July 2010. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

(1) That an Improvement and Development plan for the scrutiny of the Partnership and the Local Area Agreement be produced. (2) That the Principal Scrutiny and Overview Support Officer carry out research into how other Local Authorities have involved the community in the scrutiny process. (3) That an update on LSP grants and the implications of those grants be submitted to a future meeting of the Committee. (4) That the work already carried out on scrutiny of the Local Strategic Partnership and Local Area Agreement be noted. (5) That the Principal Scrutiny and Overview Support Officer ascertain whether or not the Children’s Services Policy Review and Development Committee has scheduled a review of the issue of children travelling to school and, if not, report on this to the next agenda setting meeting.
Word for word from the decision Bedford published for this meeting. Source: councillorsupport.bedford.gov.uk

Follow this further

Built from Bedford's papers

What the report saysPro

Report to Scrutiny Committee, 4 pages

Summary

This note provides a summary of the proposed draft work programme for Scrutiny Committee, developed by Members at the Work Programme Workshop.

Options

That the Committee considers as part of its work programme this year:

2.1To produce an improvement and development plan for the scrutiny of the Partnership and the Local Area Agreement. This would be considered at the Committee’s next meeting, if agreed;

2.2To note the work already done on scrutiny of the Local Strategic Partnership and Local Area Agreement;

2.3Whether there are any other items for addition to the Committee’s work programme, within its terms of reference.

3. Detail

3.1Outcome of the Workshop

Scrutiny Committee members were asked to consider: 1. ways in which the Committee could improve its scrutiny of the Bedford Borough Partnership and, 2. if it had any other issues to consider for addition to the work programme.

3.2Scrutiny of the Bedford Borough Partnership

The Scrutiny Committee members considered the following:

1 3.2.1. To receive the Bedford Borough Partnership draft Annual Report 2009/10 at the Scrutiny Committee’s next meeting of 1 July 2010, to enable the Committee to consider the Partnership’s performance to date and any issues going forward;

3.2.2. To invite the Bedford Borough Partnership board to suggest partnership issues for possible scrutiny reviews over the municipal year;

3.2.3. To produce an improvement and development plan for the scrutiny of the Partnership and the Local Area Agreement.

With regard to 3.2.1, the annual report was added to the Committee’s agenda for this meeting.

With regard to 3.2.2, the Bedford Borough Partnership board considered a paper from the Principal Scrutiny and Overview Support Officer on behalf of the Committee, inviting the Partnership to suggest ideas for a scrutiny review. Whilst the Partnership did not suggest any issues at this time, it requested that the Scrutiny Committee considers how community and faith groups can become more involved in the scrutiny process. It is suggested that this could be added to 3.2.3 below.

With regard to 3.2.3, the Committee is asked to consider if it wishes to establish an Improvement and Development Plan for the scrutiny of the LSP and LAA, to consider a longer term approach, possibly involving partners and the wider community, in establishing a plan for scrutinising the partnership and its work.

3.3Work done on Scrutiny of the LSP to date

Scrutiny of the LSP and LAA is the responsibility of the Scrutiny Committee. Some development work has already taken place, but it is now timely to relaunch this now that the Partnership has been in operation for a year.

To date, Scrutiny Committee has done the following. Scrutiny Committee members held a workshop with community groups who had been former members of the previous LSP, to disucss how the LSP could be scrutinised and how the community could be involved in the process. As an initial step, each partner, including those groups who were formerly on the Bedford Strategic Partnership, was asked to nominate a named non-Executive who would be willing to be involved in scrutiny work on relation to the LSP.

Scrutiny Committee also had two items on the Partnership at its committee meetings. John Cross, co-chair of the Bedford Borough Partnership, gave a presentation to the Committee on the new structure of the LSP and the Sustainable Communities Strategy. Mayor Hodgson, the other co-Chair of the partnership, spoke to the committee about the work done to date that had already brought in funding to the Borough, as well as future plans.

2 3.4. Other items for the Work Programme

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Work Programme 2009/11Report 4 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Bedford

Search all
  1. Work Programme 2009/11This decision
  2. Work ProgrammeNoted
  3. Work ProgrammeNoted
  4. Committee Work Programme for 2026-2027Agreed
  5. Work Programme 2026/2027Noted
  6. Committee Work ProgrammeDecided

More from Bedford Scrutiny Committee

All decisions
MeetingDecisionOutcome
17 Feb 2011 Decisions of the Executive at its meetings on 19 January and 9 February 2011That the decisions of the Executive taken at its meetings on 19 January and 9 February 2011 be noted. Noted Open
17 Feb 2011 Decisions of the Sustainability Committee at its meeting on 26 January 2011That the decisions of the Sustainability Committee taken at its meeting on 26 January 2011 be noted. Noted Open
17 Feb 2011 Summary of Executive Decisions Nos 887 -893That Executive Decisions Nos. 887 – 893 be noted. Noted Open
17 Feb 2011 Agenda Planning notes and Work ProgrammeThat the agenda planning notes and updated Committee work programme be noted. The meeting finished at 7.35pm. Noted Open
20 Jan 2011 Decisions of the Executive at its meeting on 5 January 2011RESOLVED : That the Decisions of the Executive made at its meeting on 5 January 2011 be noted Noted Open