Description of Decision (1) That the forecast 2010/2011 revenue outturn position against the approved revenue budget, the projected major variances with reasons for these variances and the action being taken to address the underlying issues, be acknowledged. (2) That £75,000 be allocated from the revenue contingency in 2010/2011 to meet the cost pressure associated with Children’s Services locum staffing as outlined in the report. (3) That Full Council be recommended to: ( i ) allocate £150,000 from the revenue contingency in 2010/2011 to meet the cost pressure associated with Local Land Charges as outlined in the report; (ii) allocate £190,000 from the revenue contingency in 2010/2011 to meet the cost pressure associated with Off Street Car Parking budget as outlined in the report; (iii) establish a new reserve in the sum of £300,000 for advance receipts in respect of Section 38 Highway Agreements. Reason for Decision To acknowledge the latest trends in respect of 2010/2011 revenue budget and emerging budget issues that impact on the Council’s Medium Term Financial Strategy and make recommendations to Full Council, where appropriate.
Word for word from the decision Bedford published for this meeting.Source: councillorsupport.bedford.gov.uk
To consider the latest trends in respect of the 2010/2011 revenue budget and emerging budget issues.
Recommendations
The Executive is requested to consider the report and, if satisfied, to:
(a) Acknowledge the forecast 2010/2011 revenue outturn position against the approved revenue budget, the projected major variances with reasons for these variances and the action being taken to address the underlying issues;
(b) Recommend to Council the allocation of £150,000 from the revenue contingency in 2010/2011 to meet the cost pressure associated with Local Land Charges as outlined in the report;
(c) Approve the allocation of £75,000 from the revenue contingency in 2010/2011 to meet the cost pressure associated with Children’s Services locum staffing as outlined in the report;
(d) Recommend to Council the allocation of £190,000 from the revenue contingency in 2010/2011 to meet the cost pressure associated with Off Street Car Parking budget as outlined in the report;
(e) Recommend to Council the establishment of a new Reserve in the sum of £300,000 for advance receipts in respect of Section 38 Highway Agreements;
(f) Receive an update in respect of the Comprehensive Spending Review announcement on 2 December 2010 and the impact on the Medium Term Financial Strategy.
Executive 8.12.10 Rac5414 Revenue Budget Update 3. Reason for Recommendations
To advise the Executive of the latest trends in respect of the 2010/2011 revenue budget and emerging budget issues that impact on the Council’s Medium Term Financial Strategy.
4. Key Implications
4.1Legal Issues
The Council is required, by law, to set a balanced revenue budget each year which for 2010/2011 was approved by Full Council on 3 February 2010. The purpose of this report, in accordance with best financial management practice, is to advise the Executive of significant variations from that budget.
4.2Policy Issues
The Medium Term Financial Strategy (MTFS) states that, to ensure a continuously stable financial base for the provision of Council services and functions, the Council will ensure that annual ongoing General Fund revenue expenditure can be covered by annual income sources in each and every financial year. The MTFS requires regular reports to be submitted to the Executive in respect of budget trends and this report, therefore, provides a detailed update on the latest revenue budget position and also identifies a number of emerging budget issues that will need to be monitored during 2010/2011.
The MTFS also requires that due regard is given to revenue budget forecasts and that any increase in the ongoing annual revenue budget (by way of use of the contingency provision or virement) will be subject to the expenditure being either legally unavoidable or considered affordable after taking into account:
any forecast savings targets; implications on Council Taxpayers in future years.
The current MTFS, being considered separately on the Executive agenda, identifies a net savings requirement of £3.2 million to achieve a balanced budget in 2011/2012. The MTFS will continue to be reviewed in light of the budget monitoring undertaken to date and refreshed given the emerging medium term pressures and further specified impacts upon the Council, including the implications arising from the Comprehensive Spending Review.
4.3Resource Implications
The Council’s approved 2010/2011 gross General Fund Revenue Budget is £386.3 million and this is reduced by income from specific grants, subsidies, fees, charges and rents which can be subject to variation as well as fixed income sources such as CSD Dividend, commuted sums, reserves and provisions giving a net budget requirement of £127.751 million. This is financed as follows:
Social Housing Allocations PolicyDescription of Decision (1) That the publication of the revised Bedford Borough (at Appendix A) on 1st September 2026...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.