Description of Decision (1) That, having considered the Council’s Community Assets Transfer Policy, the transfer of Waveney Green, Brickhill and the Brickhill Community Centre, to Brickhill Parish Council, be approved subject to: ( i ) the Parish Council notifying the Council of its Precept (to include full responsibility for the transferred assets) by 31 January 2011 in line with statutory timescales; (ii) the Net Borough Requirement from Council Tax in 2011/2012 being reduced by £40,140 with a consequent reduction in the level of Council Tax; (iii) the submission of an acceptable business plan, including compliance with assessment criteria; (iv) agreement being reached on the lease terms; (v) the determination of any objection received to the disposal of public open space land at Waveney Green. (2) That, in the event of an objection to the public open space land transfer being received, this will be considered by the Mayor/Executive. Reason for Decision To respond to the request by Brickhill Parish Council in accordance with the Council’s policy on Community Assets Transfer. (Note: Councillor Royden disclosed a personal and prejudicial interest in this item as a member of Brickhill Parish Council and as operator of St Mark’s Church Community Centre, Brickhill and left the room during the discussion of the item.)
Word for word from the decision Bedford published for this meeting.Source: councillorsupport.bedford.gov.uk
To determine the request from Brickhill Parish Council for a transfer of public open space and a Community Centre (as shown on the plans at Appendix B) from the Borough Council to Brickhill Parish Council
Recommendations
The Executive is requested, subject to approval being given to the proposed Community Assets Transfer Policy earlier on this agenda, to consider the request received from Brickhill Parish Council and either:
(a) Determine, on balance, not to agree the transfer of assets; OR
(b) Approve the transfer of assets subject to:
- The Parish Council notifying the Council of its Precept (to include full responsibility for the transferred assets) by 31 January 2011 in line with statutory timescales;
- The Net Borough Requirement from Council Tax in 2011/2012 being reduced by £40,140 with a consequent reduction in the level of Council Tax;
- The submission of an acceptable business plan, including compliance with assessment criteria;
- Agreement being reached on the lease terms.
(c) That, in the event of an objection to the public open space land transfer being received, this will be considered by the Mayor/Executive.
Reason for recommendations
To determine whether to approve the transfer of community assets to Brickhill Parish Council.
rac5440 Executive 19.01.11 7(1) Community Asset Transfer – Brickhill Parish Council 4. Key Implications
4.1Legal Issues
The Council has considered a Community Assets Transfer Policy as part of this meeting. If approved it provides the basis for considering requests from third parties for the transfer of assets.
Section 2 of the Local Government Act 2000 enables the Council to do anything it believes would promote or improve the economic, social or environmental well being of the Borough. Under section 2 the Council can use the well-being powers in relation to or for the benefit of:
(a) the whole or any part of a local authority’s area, or (b) all or any persons resident or present in a local authority’s area.
It has been held that the power can even be used to benefit only one individual, although the Council should have regard to its fiduciary powers to the Council Taxpayers overall in any such decision.
In considering this matter, it is relevant that the improvement of the social and environmental well being of the area would be likely to be achieved in a number of ways and, in particular, embracing the principle of fostering, supporting and increasing community involvement and participation in local neighbourhoods.
The project has the potential to act as a social driver, enabling local participation in decision making and the tailoring of services more specifically to meet local needs, and the effective restoration of environmentally challenged areas. Any improvement in the open space area associated with the transfer is also likely to deliver environmental benefits.
The Council must have regard to its Sustainable Community Strategy under section 4 of the Local Government Act 2000 in determining whether or how to exercise this power. The link to the Sustainable Community Strategy is:
The Sustainable Community Strategy is generally supportive of the localism agenda and, specifically, the Bedford Partnership Board supports the alignment of service delivery with the local needs of areas. It also has a clear goal of being an inclusive borough. Three aims of this goal are supported by empowering communities to take on and manage local facilities. These are:
• promote activities that bring people together and communities closer together;
• Encourage and support more people, particularly from under- represented groups, to take on civic roles and volunteer within their communities;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Social Housing Allocations PolicyDescription of Decision (1) That the publication of the revised Bedford Borough (at Appendix A) on 1st September 2026...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.