(1) That the report be received and that the Local Transport Plan 3 be adopted as Bedford Borough’s Transport Policy Document to 2021. (2) That the Executive Director for Environment and Sustainable Communities, be given delegated authority, following consultation with the Portfolio Holder, to make minor amendments and to approve contextual information (such as the evidence base) to the policy document. (b) Revenue Budget Update Councillor Headley moved and the Mayor seconded that the report be received and that the recommendation be adopted. On the motion being put to the meeting, the Speaker declared it to be carried. That the report be received and that the sum of £141,010 received from the Department for Communities and Local Government, in conclusion of the successful appeal against the rating assessment of Bedford International Athletic Stadium, be transferred to the revenue contingency.
Word for word from the decision Bedford published for this meeting.Source: councillorsupport.bedford.gov.uk
1.1To advise the Council of the outcome of the Executive’s consideration of the latest trends in respect of the 2010/2011 revenue budget and emerging budget issues, particularly in relation to the refund received in conclusion of the successful appeal against the rating assessment of Bedford International Athletic Stadium (BIAS).
Recommendation
1.2That the sum of £141,010 received from the Department for Communities & Local Government in conclusion of the successful appeal against the rating assessment of Bedford International Athletic Stadium be transferred to the revenue contingency.
Key Issues
Legal
1.3The Council is required, by law, to set a balanced revenue budget each year which for 2010/2011 was approved by Council on 3 February 2010.
Policy
1.4The Medium Term Financial Strategy (MTFS) states that, to ensure a continuously stable financial base for the provision of Council services and functions, the Council will ensure that annual ongoing General Fund revenue expenditure can be covered by annual income sources in each and every financial year. The MTFS requires regular reports to be submitted to the Executive in respect of budget trends. Accordingly, it has received a detailed update on the latest revenue budget position and the emerging budget issues that will need to be monitored during 2010/2011.
1.5The MTFS also requires that due regard is given to revenue budget forecasts and that any increase in the ongoing annual revenue budget (by way of use of the contingency provision or virement) will be subject to the expenditure being either legally unavoidable or considered affordable after taking into account:
14.2(1) any forecast savings targets;
implications on council taxpayers in future years.
1.6The MTFS will continue to be reviewed in light of the budget monitoring undertaken to date and refreshed given the emerging medium term pressures and further specified impacts upon the Council, including the implications arising from the Local Government Finance Settlement. It is now clear that the finance settlement will provide a significant challenge to local government given the major reduction in grant funding over the four year spending review period 2011/2015 and this has been taken into account in determining the 2011/2012 revenue budget. A refreshed version of the MTFS is scheduled to be considered by the Executive at its meeting on 16 March 2011 in accordance with the requirement for an annual review.
Resource
1.7The Council’s approved 2010/2011 gross General Fund Revenue Budget is £386.3 million and this is reduced by income from specific grants, subsidies, fees, charges and rents which can be subject to variation as well as fixed income sources such as CSD Dividend, commuted sums, reserves and provisions giving a net budget requirement of £127.751 million. This is financed as follows:
£million 2010/2011
Net Budget Requirement 127.751 Financed by: Formula Grant 54.099 Council Tax Yield 73.652
1.8The gross 2010/2011 revenue budget is, therefore, dependant upon the receipt of a range of ring-fenced and other government grants (in addition to the Formula Grant) and these are summarised below:
£million 2010/2011
Dedicated School Grant 98.38 Area Based Grant 11.48 Other Revenue Grants 34.30
1.9The report considered by the Executive identified relevant movements in budget trends since the report to the Executive meeting 8 December 2010 that required remedial action. There will, in addition, be continued vigilance (as part of the established monitoring process) in identifying issues that will impact upon the current budget for the remainder of the financial year and the 2011/2012 budget.
14.2(2) Risk
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Report of the mayor/executive membersThat the use of the Special Urgency Procedure be noted. (2) Membership of Executive and Changes to Executive Committe...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.