Pension Fund Administration - Quarterly Performance Update for the Period Ending 31 December 2010

Approved Finance 3 papers

Pension Fund Committee approved this item on Monday 28 February 2011. Below is the council's own wording, with the papers it was decided on.

Item55

Resolved

(1) That, subject to the satisfactory conclusion of legal contracts, the admission of MITIE to the Pension Scheme be approved. (2) That, following confirmation by Hymans Robertson of the new factors for actuarial strain that evidence the need to vary current arrangements, the discontinuation of a 40% uplift to reflect early retirement strain costs be approved and that the revised arrangements be implemented on 1 March 2011 for new calculations. (3) That , having regard to the review by Hymans Robertson, the current practice of immediate payment in full of actuarial pension strain costs be reaffirmed. (4) That the increase in the number of new scheme employers in the Pension Fund, following the transfer of schools to academy status (as detailed in paragraph 5.5 of the report), be acknowledged on the basis that more academy schools would have their share of the Pension Fund deficit transferred to them when calculating their employer contribution rate. FA
Word for word from the decision Bedford published for this meeting. Source: councillorsupport.bedford.gov.uk

Follow this further

Built from Bedford's papers

What the report saysPro

Report to Pension Fund Committee, 7 pages

Executive summary

This report highlights areas of work undertaken by Pensions Administration and its performance during the quarter to 31 December 2010.

Recommendations

The Committee is requested to consider the report, seek clarification and, if satisfied, to:

(a) Approve the admission of MITIE to the Pension Scheme, subject to the satisfactory conclusion of legal contracts;

(b) Approve, subject to Hymans Robertson producing new factors for actuarial strain by early March 2011 that evidence the need to vary current arrangements, the discontinuation of the 40% uplift to reflect early retirement strain costs and that, in the circumstances, all pending pension strain calculations be deferred pending implementation of the revised arrangements;

(c) That the revised arrangements, identified in (b) above, be implemented on 7 March 2011 if Hymans Robertson confirm their advice following the revised calculation of the factors or, if the advise is delayed, at a date to be determined by the established Pension Fund Sub-Group and that, when the date is confirmed, Officers write to scheme employers explaining the agreed decision;

(d) That, having regard to the review by Hymans Robertson, the current practice of immediate payment in full of actuarial pension strain costs be reaffirmed;

(e) Acknowledge the new scheme employers as detailed in paragraph 5.5 following the schools approval to become Academy schools. Pension Fund Committee 28.02.11 Pension Fund Administration – Quarterly Performance Update 8(1) 3. Reasons for Recommendations

To update the Committee on the administrative activities of the Fund.

4. Key Implications

4.1Legal Issues

None identified.

4.2Policy Issues

None identified.

4.3Resource Implications

There is a potential resource implication arising from the recommendation to reduce the factors in the calculation of pension strain. The value is dependent on the future number of pension strains charged to employers.

Risk implications

None identified.

4.5Environmental Implications

None identified.

4.6Equalities Impact

This activity is exclusively a support or administrative function and has no relevance to the duty to promote equality of opportunity, promote good relations and eliminate unlawful discrimination.

5. Details

Performance Indicators

5.1The key tasks undertaken by Pensions Administration in the period to 31 December 2010 are detailed at Appendix A to the report. Data is compiled using the work flow system, held within AXISe, and records the time taken to undertake and verify calculations.

5.2In terms of specific performance it is relevant that:

(a) The creation of member records and payment of refunds remained consistent with 100% in target;

(b) Processing retirements within 10 working days of receipt of all paperwork remained at 100% for the quarter. Pension Fund Committee 28.02.11 Pension Fund Administration – Quarterly Performance Update 8(2) (c) Retirement estimates were completed within target – overall performance for the quarter at 92%. Although this is a slight decrease from the quarter 2, 427 quotations were processed (an additional 125 quotations from the Quarter 2 total of 302).

(d) Following instruction from the Department for Communities & Local Government (DCLG) on 6 July 2010, the calculation of certain transfers into the fund was suspended, pending relevant advice from Government Actuary’s Department.

Further instruction from DCLG, and the relevant factors, were received on 15 December 2010 and the cases have been reviewed and progressed accordingly.

Admitted Body Application/Employer update

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Item 8.1: Appendix AAppendix 1 pages Download
PDF
Item 8.2: Appendix BAppendix 1 pages Download
PDF
Pension Fund Administration: Quarterly Performance Update for the Period Ending 31 December 2010Report 7 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Bedford

Search all
  1. Pension Fund Administration - Quarterly Performance Update for the Period Ending 31 December 2010This decision
  2. KPMG: External Auditor - Draft Audit Results Report 2025/26 - Bedfordshire Pension FundNoted
  3. External Audit of the Statement of Accounts 2025/26 - Bedfordshire Pension FundNoted
  4. Report of the chair of the pension fund committeeDecided
  5. KPMG: External Auditor's Reports 2024/25 - Bedfordshire Pension FundNoted
  6. Bedfordshire Pension Fund Committee Decisions and Board SummaryNoted

More from Bedford Pension Fund Committee

All decisions
MeetingDecisionOutcome
27 Jan 2026 MinutesThat the non confidential of the meeting of the Pension Fund Committee held on 20 November 2025 be confirmed. Decided Open
27 Jan 2026 Local Government Act 1972: Schedule 12A (as amended) - Exclusion of the PublicThat, pursuant to Section 100(A)(4) of the Local Government Act 1972, the public be excluded from the remainder of th... Agreed Open
11 Mar 2025 MinutesThat the non confidential of the meeting of the Pension Fund Committee held on 28 January 2025 be confirmed. Decided Open
11 Mar 2025 Minutes of the Local Pension BoardThat the Minutes of the meeting of the Bedfordshire Local Pension Board held on 6 February 2025 be noted. FA Noted Open
11 Mar 2025 Pension Fund Administration - quarterly performance update for the period ending 31 December 2024(1) That the admission of School Catering Support Ltd t/a Relish f or the provision of catering services at Icknield ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies