Resolved
Description of Decision That the Minutes of the meting of the Sustainability Committee of the Executive held on 26 January 2011 be confirmed.
Sustainability Committee decided this item on Wednesday 2 March 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
Description of Decision That the Minutes of the meting of the Sustainability Committee of the Executive held on 26 January 2011 be confirmed.
There is a legal requirement for the Minutes of the previous meeting to be considered before being confirmed as an accurate record.
17. DISCLOSURES OF INTEREST
There were no disclosures of interest.
18. CARBON TRUST LOCAL AUTHORITY CARBON MANAGEMENT PROGRAMME (LACMP) - UPDATE
The Corporate Carbon and Energy Manager gave a presentation on the Carbon Trust’s Local Authority Carbon Management Programme (LACMP), which would be sent to the Carbon Trust for review on 31 January 2011, signed off by the Project Sponsor on 8 February 2011 and signed off by this Committee on 2 March 2011.
The intention of the LACMP was to meet the Council’s aspirational target of reducing its CO2 emissions by 40% by 2015 from its recorded baseline of 2009/10.
The Council’s main sources of CO2 emissions were Borough Hall itself, schools, street lighting, refuse vehicles and fleet vehicles. The carbon value at stake was 39,867 tCO2 and a financial value at stake of £6,918,456. Thirty two projects had
3(1) 26 January 2011
been identified in the LACMP, divided into different types of projects. Officers were still looking at adding to the statistics already contained in the LACMP.
In answer to a Member’s question, it was stated that schools were a major element of the plans to reduce CO2 emissions and officers had some major inroads into schools in this area. It was hoped to establish a Carbon Management Group in which schools could share best practice and encourage each other. Eight school representatives were already involved in the project. Further representatives for the Schools Carbon Management Group are being sought from the January edition of the school bulletin ASPIRE which is due to go out in the week of the meeting to all Borough schools.
RESOLVED:
That the briefing note on the Carbon Trust’s Local Authority Carbon Management Programme (LACMP) be noted.
To receive a further update on the Council’s progress on the Carbon Trust’s Local Authority Carbon Management Programme (LACMP).
19. RATIONALISATION AND GREENING OF BOROUGH COUNCIL STATIONERY SUPPLIES
The Senior Procurement Review Officer reported that the Sustainability and Procurement Teams were working together across areas of procurement throughout the Council to assess the sustainability of stationery products and to generate savings. The review had produced the following benefits:
• Reducing the Council’s stationery requirements from 1,600 product lines to 160 core items; • All stationery will now be purchased from the “sole supplier” (Banner) to take advantage of discounts; • The number of deliveries had been reduced from daily to twice weekly, with a consequent reduction in CO2 emissions; and • The Procurement and Sustainability Teams were assessing the sustainability or “greenness” of the core list of products and highlighting alternatives whilst adhering to the Council’s value for money guidelines.
The new system had gone live in December 2010 and the cost of stationery products for that month had been £5,500, compared with an average of £8,000+ per month in the period April to November 2010. The Senior Procurement Review Officer stated that the Council would obtain better prices if it commits to using only one supplier.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
To confirm the Minutes of the meeting of the Sustainability Committee held on 26 January 2011(copy previously circulated)Minutes | 7 pages | DownloadRead as text |
Follow Sustainability Committee at Bedford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Jan 2015 | To confirm the Minutes of the meeting of the Sustainability Committee held on 12 November 2014 (copy previously circulated)Description of Decision That the Minutes of the meeting of the Sustainability Committee held on 12 November 2014 be c... | Decided | Open |
| 28 Jan 2015 | Water DeregulationThat the presentation on Water De-regulation be noted. CCEM | Noted | Open |
| 28 Jan 2015 | Water StrategyDescription of Decision That the be approved. Reasons for Decision ( i ) The will help the Council to reduce its annu... | Approved | Open |
| 28 Jan 2015 | Work Programme UpdateThat the progress report on the Committee’s work programme be noted. That further information on Biomass fuel pellets... | Noted | Open |
| 9 Apr 2014 | To confirm the Minutes of the meeting of the Sustainability Committee held on 29 January 2014Description of Decision : That the Minutes of the meeting of the Committee held on 29 January 2014 be confirmed. Reas... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.