Bedford Conservation Area Management Plan and Design Framework for Public Realm Works for Bedford High Street (Report of Housing, Planning and Licensing Portfolio Holder and Assistant Director (Planning and Housing) enclosed)
NotedExecutive1 paper
Executive noted this item on Wednesday 16 March 2011. Below is the council's own wording, with the papers it was decided on.
Description of Decision (1) That the proposed response to consultation comments received, as set out in Appendix A to the report, be noted. (2) That the Bedford Conservation Area Management Plan, as set out in Appendix B to the report, be adopted as a technical document for the purposes of guiding the Council’s approach to all works and matters related to the continued preservation and enhancement of the Bedford Conservation Area. (3) That the Design Framework for Public Realm works to Bedford High Street, as set out in Appendix C to the report, be adopted as a technical document to inform any further proposals for the street. Reason for Decision To meet the Council’s statutory obligations and to ensure the continued preservation and enhancement of the Bedford Conservation Area. To support the Council’s Townscape Heritage Initiative Stage 2 funding bid to the Heritage Lottery Fund (HLF) for the regeneration of Bedford High Street.
Word for word from the decision Bedford published for this meeting.Source: councillorsupport.bedford.gov.uk
1.1An up-to-date Conservation Area Management Plan is required to support the Townscape Heritage Initiative Stage 2 funding bid to the Heritage Lottery Fund (HLF) for the regeneration of Bedford High Street. The Design Framework for Public Realm Works on Bedford High Street has been produced to support several of the measures proposed in the Management Plan, particularly to work towards a unified design approach to works in the public realm in the Conservation Area.
1.2Draft copies of both documents were agreed for the purposes of public consultation by Executive decision by the Portfolio Holder for Housing, Planning and Licensing on 2nd November 2010. Consultation took place during November and December 2010 and a consultation report is included as Appendix A to this report. The report sets out the issues raised during the consultation and proposes amendments to the Management Plan and Design Framework in response to the comments received. The Executive is recommended to adopt the revised Conservation Area Management Plan (included as Appendix B) as a technical document to guide the Council’s approach to all works and matters related to the continued preservation and enhancement of the Conservation Area and to adopt the revised Design Framework (Appendix C) as a technical document to inform any further proposals for the street.
Recommendations
a) That the proposed response to consultation comments received as set out in Appendix A be noted.
b) That the Bedford Conservation Area Management Plan as set out in Appendix B be adopted as a technical document for the purposes of guiding the Council’s approach to all works and matters related to the continued preservation and enhancement of the Bedford Conservation Area.
6(1) Executive Bedford Conservation Area Management Plan c) That the Design Framework for Public Realm Works to Bedford High Street as set out in Appendix C be adopted as a technical document to inform any further proposals for the street.
Reasons for recommendations
3.1To meet the Council’s statutory obligations and to ensure the continued preservation and enhancement of the Bedford Conservation Area.
3.2To support the Council’s Townscape Heritage Initiative Stage 2 funding bid to the Heritage Lottery Fund (HLF) for the regeneration of Bedford High Street.
4. IMPLICATIONS
Legal
4.1Under Section 71 of the Planning (Listed Buildings and Conservation Areas) Act 1990, local planning authorities are required to draw up and publish proposals in the form of Management Plans, for the preservation and enhancement of Conservation Areas in their districts. The Act also requires that a public meeting be held for consideration of the proposals. In response to this requirement, a meeting was held on 1st December 2010 at the Harpur Suite in Bedford.
4.2Although it is not mandatory, it is acknowledged that local consultation can help to bring valuable public understanding and ‘ownership’ to proposals for an area. English Heritage advises that consultation should be undertaken generally in line with the Local Authority’s Statement of Community Involvement. A four week public consultation exercise has therefore been completed, details of which may be found in Appendix A of this report.
Policy
4.3The documents are consistent with the Council’s adopted policies contained within the Bedford Borough Local Plan (2002), the Core Strategy and Rural Issues Plan (2008), the Bedford Town Centre Area Action Plan (2008) and the Strategy for Bedford High Street (2010).
Resource
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Bedford Conservation Area Management Plan and Design Framework for Public Realm Works for Bedford High Street (Report of Housing, Planning and Licensing Portfolio Holder and Assistant Director (Planning and Housing) enclosed)Report
103Bedford Conservation Area Management Plan and Design Framework for Public Realm Works for Bedford High Street (Report of Housing, Planning and Licensing Portfolio Holder and Assistant Director (Planning and Housing) enclosed)This decision
Social Housing Allocations PolicyDescription of Decision (1) That the publication of the revised Bedford Borough (at Appendix A) on 1st September 2026...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.