Resolved
That the position statement be noted. Chair
Environment, Regeneration and Corporate Services Policy Review and Development Committee noted this item on Thursday 31 March 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
That the position statement be noted. Chair
1.1This report provides an update on delivery of the winter maintenance service in 2010/11 and plans for reviewing operational policy for 2011/12
2.1That the position statement is noted.
3.1To ensure that Committee are fully briefed on the Council’s Winter Maintenance strategy.
4 Implications
Legal
4.1Bedford Borough Council is the highway authority for the Borough and its duty to maintain the highway is set out by Section 41 of the Highways Act 1980 as amended by S111 of the Railways and Transport Safety Act 2003 (which came into force on 1 November 2003): This amendment inserted after section 41(1) of the Highways Act 1980 (c. 66) (duty of highway authority to maintain highway) the following requirement “(1A) In particular, a highway authority are under a duty to ensure, so far as is reasonably practicable, that safe passage along a highway is not endangered by snow and ice”. Case law since then has clarified the minimum actions needed to meet the duty.
Policy
4.2The Council’s current winter maintenance plan has key objectives of keeping the roads clear of ice and snow.
9(1) Resource
4.3The Winter Maintenance service is delivered in part through the Highways term Contract with Amey, and in part through in house delivery via our own staff.
4.4Funding to cover the Amey lump sum costs, and anticipated in-house costs have been included in the 2010/11 Highways Revenue budget based on a ‘normal’ winter period. The occurrence of severe weather conditions which necessitates additional snow clearance to be undertaken may require consideration to be given to provide additional resources to maintain the service; this is usually through a call on general contingency funds.
4.5As part of the winter maintenance budget an allocation is made for the purchase of salt. As the winter season develops salt is replenished through supply contracts and this cost is covered from existing resource. In 2010/11 additional funding was made available from the Council’s general contingency fund to purchase and store 3,000 tonnes of marine salt from abroad in order to ensure the council was fully prepared in the event of a further severe winter (see Executive Decision 825).
Risk
4.6In the event of severe winters it is possible that there will be a national shortage of salt supplies, with Government dictating how salt supplies are allocated. If this happens then the Council may be required by Government to reduce the number of roads that are treated in anticipation of ice.
Environmental
4.7The value of keeping roads open and relatively safe in icy conditions using salt is widely acknowledged. If roads are not cleared, the impact of accidents and increased fuel consumption are likely to be significant in environmental and economic terms.
Equalities
4.8Increasing the robustness of our winter maintenance service can ensure that the priority highway network is available for all to use during periods of adverse weather.
5 Details
As a result of the last two winters a number of reviews are underway at national, regional and local level. A further review of the Council’s Winter Maintenance Operational Plan will commence in Spring 2011 picking up on lessons learnt from this year. For 2010 ‘in season’ a number of operational improvements were put in place.
9(2) The sections below outline key issues and summarise the changes made to operations and policy.
5.1Coordination
5.1.1 Following changes arising from the formation of a Unitary Authority the decision-making protocol was clarified with roles better defined.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Item 9 Winter Maintenance Appendix 1Appendix | 1 pages | Download |
PDF |
Item 9 Winter Maintenance Appendix 2Appendix | 1 pages | Download |
PDF |
Winter Maintenance PlanReport | 5 pages | DownloadRead as text |
Follow Environment, Regeneration and Corporate Services Policy Review and Development Committee at Bedford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 31 Mar 2011 | MinutesThat the of the meeting of the Committee held on 1 March 2011 be confirmed. Chair | Decided | Open |
| 31 Mar 2011 | Forward Plan of Key DecisionsThat the Forward Plan of Key Decisions for the period April – July 2011 be noted. Chair | Noted | Open |
| 31 Mar 2011 | Benefits Service Review(1) That the recommendations and conclusions sections of the report on the be agreed, with the addition of the follow... | Agreed | Open |
| 31 Mar 2011 | Electric Car Charging FacilitiesThat the position statement be noted. AD(H&T) | Noted | Open |
| 31 Mar 2011 | Performance InformationThat the exceptions report be noted. Chair | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.