Resolved
That the report be noted and that the Mayor and supporting officers be thanked for their attendance at the meeting. Chair
Budget and Corporate Services Overview and Scrutiny Committee noted this item on Thursday 19 January 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted and that the Mayor and supporting officers be thanked for their attendance at the meeting. Chair
To consider whether to terminate the Development Agreement between the Council and St Modwen Developments Limited that was entered into on 20 December 2005, and subsequently extended for a period of 24 months.
The Mayor is invited to consider whether to terminate by mutual agreement the Development Agreement for Town Centre West between the Council and St Modwen Developments Limited.
The extended Development Agreement with St Modwen Developments Limited is due to end on 20 December 2011. The Council must decide what course of action it deems is appropriate at the expiry of the current agreement to enable options for the future development of Town Centre West to be appraised.
4. IMPLICATIONS
(a) Legal
The formal Development Agreement between the Council and St. Modwen Developments Limited (St. Modwen) was entered into on 20 December 2005 and was subject to pre-conditions which must be satisfied or waived by 20 December 2009. Executive Decision 740, dated 1 December 2009, extended the Development Agreement for a period of 24 months (including the unconditional date) to 20 December 2011. If the pre-conditions contained within the Development Agreement are not satisfied or waived by that date, either party may determine the agreement on 10 working days’ notice. If the pre-conditions are satisfied before that 10 days notice expires then the agreement will become unconditional, otherwise it will automatically terminate.
(1) TCW251111 (b) Policy
The regeneration of the town centre is a key priority for the Council, reflecting the importance of a strong and vibrant town centre in achieving the growth objectives set out in national policy, as well as regional and sub-regional strategies. The Bus Station area, known as Bedford Town Centre West, is identified as a key area of change within the approved Local Development Framework and Town Centre Area Action Plan. Redevelopment of the area is a key deliverable of the adopted Town Centre Area Action Plan and its redevelopment should stimulate other deliverables of that plan.
Executive Decision 846, dated 10 August 2010, acknowledged work to bring forward the redevelopment as part of a phased approach and agreed the following key objectives and aspirations of the scheme:-
a) Securing a new shopping opportunity in the town centre, in order to enhance the quality of retail provision; b) Delivering a new bus station and improving public transport facilities within the town centre; c) Enhancing and improving the quality of the car parking provision and public conveniences within the development area; d) Encouraging a greater mix and diversity of uses in the town centre, including shops/restaurants/pubs/cafes and residential; e) Providing replacement community facilities, if appropriate; f) Improving access for pedestrians and cyclists within and to the town centre; g) Enhancing the environment of the town centre; h) Reducing the flow of consumer expenditure out of the town to competing centres (eg Milton Keynes; Cambridge; and London); i) Retaining the core customers as well as increasing the town centre catchment area; j) Providing a modern retailing amenity to complement the increased housing/populations demand and to provide local employment opportunities; and k) Regenerating the area through a phased delivery of the redevelopment whereby each part contributes to the above but does not compromise subsequent phases.
(2) TCW251111 (c) Resource
The financial offer as reflected in the original Development Agreement of 20 December 2005 between the Council and St Modwen Developments Limited provided that:-
(a) For the first five years following practical completion of the development, St Modwen will pay Bedford Borough Council 8% of the total net income received or £690,000 per annum (i.e. the estimated longer term income projected by the Council from the development area), whichever is the highest.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Executive Decision No. 972: Town Centre West: Post Decision ScrutinyDecisions | 8 pages | DownloadRead as text |
Follow Budget and Corporate Services Overview and Scrutiny Committee at Bedford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Jul 2026 | Procurement Initiatives and Improvement PlanRESOLVED : i) That the briefing ... view the full minutes text for item 22. Mgr D&ES | Decided | Open |
| 9 Jul 2026 | Member Finance Awareness Trainingi) That the briefing note, be noted. ii) That it be agreed that all Councillors be strongly recommended and encourage... | Noted | Open |
| 9 Jul 2026 | To consider any "call-ins"That it be noted that there were no call-ins for the Committee to consider. Chair | Noted | Open |
| 9 Jul 2026 | Record of Decisions of the ExecutiveRESOLVED : That it be noted that, as no Executive meetings have been held since the Committee’s last meeting, there w... | Noted | Open |
| 9 Jul 2026 | Summary of Relevant Individual Executive DecisionsRESOLVED : That the individual Executive Decision made since the last meeting of the Committee which fall within the ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.