Resolved

Description of Decision (1) That the commencement of a competitive tender process for the provision of leisure facilities currently provided by the Borough Council, be approved. (2) That, subject to (3) below, the detailed specification, attached at Appendix A to the report, outlining the Council’s requirement for the future provision of Leisure Services, be approved. (3) That the Executive Director for Adult and Community Services, following consultation with the Portfolio Holder for Leisure and Culture, be given delegated authority to authorise amendments to the detailed specification. (4) That the extension of the Bunyan Centre service until no later than January 2014, to coincide with the duration of the tender process, be approved and, in doing so, that it be established whether the Bunyan Centre has a viable commercial future. (5) T hat the need to identify a one-off sum of £320,000 in the 2013/2014 revenue budget to fund the extended continuance of the leisure service at the Bunyan Centre until January 2014, be acknowledged. (6) That it be acknowledged that the focus of the procurement process should be to enable alternative arrangements for the provision of leisure services to be appraised against a comparator value with the aim of reducing the Council’s net cost whilst still ensuring a good level of service to the customer. (7) That the allocation of funding, in the estimated sum of £80,000 from the revenue contingency, for property condition surveys and specialist legal advice to be undertaken to support the procurement process, be approved. (8) That the need to undertake essential property investment at the Oasis Pool at an estimated cost of £135,000 and to incorporate within the capital programme, when reviewed, provision for this investment, be acknowledged. (9) That the need to incorporate within the capital programme at a future date provision for the cost of essential property investment in leisure facilities at an estimated cost of £2.435 million (subject to the outcome of condition surveys), be acknowledged.
Word for word from the decision Bedford published for this meeting. Source: councillorsupport.bedford.gov.uk

Follow this further

Built from Bedford's papers

What the report saysPro

Report to Executive, 14 pages

Executive summary

This report concerns the future management and development of Leisure Services provided by the Council. Currently the provision of the service is operated directly by the Council and the precise details of each facility and service are contained in the draft specification attached at Appendix A to this report. The management arrangements for Leisure Services need to be reviewed to reflect the current changing economic conditions and the ongoing requirement to provide the most cost effective and efficient services, as well as delivering the savings outlined in previously agreed policy options (referenced ACS46 and ACS48) as part of the modernisation programme. This report considers potential alternative management arrangements and outlines the procurement and tendering process by which alternative delivery options will be sought and appraised.

Recommendations

The Executive is requested to consider the detailed information provided in this report and, if satisfied, to:

(a) Approve the commencement of a competitive tender process for the provision of leisure facilities currently provided by the Bedford Borough Council;

(b) Approve, subject to (c) below, the detailed specification, attached at Appendix A, outlining the Council’s requirement for the future provision of Leisure Services

(c) Approve a delegation to the Executive Director for Adults & Community Services, following consultation with the Portfolio Holder for Leisure & Culture, to authorise amendments to the detailed specification;

(d) Approve the extension of the Bunyan Centre service until no later than January 2014 to coincide with the duration of the tender process and, in doing so, to establish whether the Bunyan Centre has a viable commercial future;

Executive – 9 January 2013 7(1) rac5633 Provision of Leisure Services (e) Acknowledge the need to identify a one-off sum of £320,000 in the 2013/2014 revenue budget to fund the extended continuance of the leisure service at the Bunyan Centre until January 2014;

(f) Acknowledge that the focus of the procurement process should be to enable alternative arrangements for the provision of leisure services to be appraised against a comparator value with the aim of reducing the Council’s net cost whilst still ensuring a good level of service to the customer;

(g) Approve the allocation of funding, in the estimated sum of £80,000 from the revenue contingency, for property condition surveys and specialist legal advice to be undertaken to support the procurement process;

(h) Acknowledge the need to undertake essential property investment at the Oasis Pool at an estimated cost of £135,000 and to incorporate within the capital programme, when reviewed, provision for this investment;

(i) Acknowledge the need to incorporate within the capital programme at a future date provision for the cost of essential property investment in leisure facilities at an estimated cost of £2.435 million (subject to the outcome of condition surveys).

Reasons for recommendations

The recommendations in the report seek to establish the process for tendering the provision of leisure services and, in particular, to:

(a) To enable the Council to formally evaluate the opportunities and potential benefits (including potentially a more cost effective provision of leisure services) that could be derived from alternative options for the delivery of leisure services, including provision by an external provider or partner, and to comply with legislative and contract procedure requirements in respect of the procurement of services;

(b) To ensure that tenders for the provision of leisure services meet the Council‟s expectations for service delivery and are accurately based on a full understanding of the Council‟s requirements in order to facilitate accurate comparison of the benefits of each tender;

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Item 7: Appendix A Leisures ServicesAppendix 232 pages Download
PDF
Provision of Leisure ServicesReport 14 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Bedford

Search all
  1. Provision of Leisure ServicesThis decision
  2. Leisure Service ProvisionNoted

More from Bedford Executive

All decisions
MeetingDecisionOutcome
15 Jul 2026 Minutes of Previous MeetingDescription of Decision That the Minutes of the meeting of the Executive held on 3 June 2026 be confirmed. Reason for... Decided Open
15 Jul 2026 Local Government and Social Care Ombudsman Annual Review Letter 2025/2026Description of Decision That the Local Government and Social Care Ombudsman’s Annual Review letter for 2025/2026 for ... Noted Open
15 Jul 2026 RIPA Annual ReportDescription of Decision (1) That it be noted that, in the period 1 April 2025 to 31 March 2026, there were no applica... Noted Open
15 Jul 2026 Social Housing Allocations PolicyDescription of Decision (1) That the publication of the revised Bedford Borough (at Appendix A) on 1st September 2026... Approved Open
15 Jul 2026 Corporate Plan 2024-2028 Performance Report year-end 2025/2026Description of Decision That the latest performance as outlined within the Key Indictor Performance Report at Appendi... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies