Resolved
RESOLVED : That the performance report for both the first and second quarters of 2012/2013 be noted. SOSO
Environment and Sustainable Communities Overview and Scrutiny Committee noted this item on Thursday 17 January 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED : That the performance report for both the first and second quarters of 2012/2013 be noted. SOSO
1.1To receive an Exception report on performance indicators relevant to the Environment & Sustainable Communities Directorate.
2.1The Committee is invited to consider, seek clarification and acknowledge, both the Quarter 1 (April to June 2012) and Quarter 2 (July to September 2012) performance in respect of reported indicators and the actions that have been taken to improve the Performance in areas of service relevant to this Committee.
3.1To provide the latest performance issues affecting the Key Indicator set for Environment and Sustainable Communities Directorate and any actions that have been put in place to improve overall performance.
4. Key Implications
Legal Issues
4.1There are no specific legal issues arising from this report
Policy Issues
4.2The Council uses Performance Indicators, both national and local as one of a number of measures of how it is achieving its priorities and objectives as set out in the Corporate Plan.
Resource Implications
4.3There are no direct resource implications arising from this report at this stage.
8(1) Environment and Sustainable Communities Overview & Scrutiny Committee – January 2013 Exceptions Performance 4.4 There are no direct risk implications arising from this report at this stage. Environmental Implications
4.5There are no direct Environmental implications arising from this report.
Equalities Impact
4.6In preparing this report, due consideration has been given to the Borough Council’s statutory Equality Duty to eliminate unlawful discrimination, advance equality of opportunity and foster good relations, as set out in Section 149(1) of the Equality Act 2010.
4.7A relevance test for equality has been completed. The equality test determined that the activity has no relevance to Bedford Borough Council’s statutory equality duty to eliminate unlawful discrimination, advance equality of opportunity and foster good relations. An equality analysis is not needed.
5. Details
Q1 & Q2 Summary of half year performance April – September 2012
5.1.1 There is no longer a requirement for Local Authorities to report a set of indicators to National Government for Environment and Sustainable Communities. The Corporate indicator set for 2012/13 consists of 38 indicators which include former NI indicators and locally developed indicators.
5.1.2 Overall the first half of the year has been relatively good with 27 indicators able to report and 18 indicators on track to meet target at end of year. Only 4 indicators are significantly off target at this time and these will be closely monitored.
Climate Change
5.2Progress of Carbon Management Plan – The 1 remaining Carbon Management Project from 2012/13 has now been completed.
5.3There are currently 7 energy savings projects under development within the RE:FIT programme. MITIE were appointed as the preferred Partner and Energy Service Company (ESCo) to deliver these projects under the RE:FIT programme. The majority of these projects are likely to complete during 2013/14 period but we will provide regular quarterly reports on the progress of all these projects.
5.4Water baseline is currently being calculated across all Council facilities to enable us to set a Water saving pledge target and we expect that we will be able to do this in Q3
8(2) Environment and Sustainable Communities Overview & Scrutiny Committee – January 2013 Exceptions Performance Crime
5.5The Community Safety Partnership continues to deliver a consistent strong performance, however performance can be sensitive to seasonal variations particularly over the summer months. Q2 has reported some slight increases in incidents being reported for anti-social behaviour and gun crime but we expect that the end of year targets for these indicators will be met.
Recycling
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Exceptions PerformanceReport | 29 pages | DownloadRead as text |
Follow Environment and Sustainable Communities Overview and Scrutiny Committee at Bedford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2026 | Previous MinutesRESOLVED That the Minutes of the meeting of the Committee held on the 18 June 2026 be confirmed. Chair | Decided | Open |
| 16 Jul 2026 | Local Plan 2050RESOLVED That the Committee noted the update. HCPI&ST | Noted | Open |
| 16 Jul 2026 | Executive DecisionsRESOLVED 1. The Committee noted that there were no meetings of Executive prior to the publication of the agenda, deci... | Noted | Open |
| 16 Jul 2026 | Notice of Forthcoming Decisions to be taken by the ExecutiveThat the Notice of Forthcoming Decisions for the period 1 August 2026 to 30 November 2026 be received. SDSO | Decided | Open |
| 16 Jul 2026 | Committee Work ProgrammeThat an item on Biddenham (Great Ouse Way) Country Park be added to the Committee’s Work Programme. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.