Sustainability Committee, Wednesday 30 January 2013 at 6.30pm

Climate Change Fund Projects

Approved Committee 1 paper

Sustainability Committee approved this item on Wednesday 30 January 2013. Below is the council's own wording, with the papers it was decided on.

Item18

Resolved

Description of Decision That funding be approved from the Climate Change Fund for: Putnoe Primary School’s application to install roof insulation in the sum of £11,988 for the reasons set out in the report.
Word for word from the decision Bedford published for this meeting. Source: councillorsupport.bedford.gov.uk

Follow this further

Built from Bedford's papers

What the report saysPro

Report to Sustainability Committee, 5 pages

Executive summary

1.1This report provides details of 1 application to the Climate Change Fund and recommends approval of the application.

1.2The group applying for funding is Putnoe Primary School.

Recommendations

2.1That the Committee consider, and if satisfied, approve funding from the Climate Change Fund for:

Putnoe Primary School’s application to install roof insulation in the sum of £11,988 for the reasons set out in the report.

Reasons for recommendations

3.1To allow one further project to be funded in 2012/13 which will contribute to reducing the overall carbon emissions in the Borough.

3.2The application to install roof insulation on the school’s flat roof will reduce the heat loss from the previously un-insulated roof which will reduce the school’s heat loss, energy consumption and carbon emissions.

3.3The Council is committed to encouraging all sectors in the local community to take the opportunity to reduce their own carbon emissions.

3.4By helping local community groups and schools improve the energy efficiency of their community buildings and install renewable energy technologies through the implementation of the fund they will be able to reduce their energy consumption and carbon emissions which will help the Council contribute to the Government’s carbon reduction targets.

5(1) 4. Key Implications

4.1Legal Issues

The Council can carry out works of maintenance to educational buildings under its powers as education authority and land owner. These powers are supplemented where necessary by the general power of competence under the Localism Act.

Policy Issues

Corporate Plan 2012-16:-

4.2Theme 2B Climate Change and Environmental Sustainability - Objective: ‘To ensure that the Borough reduces its carbon footprint, including managing our waste more effectively.

Sustainable Community Strategy 2009-2021:-

4.3Theme 2 ‘A Greener Borough’: Environment and Climate Change – has the goal of: a high quality natural and built environment which is valued and enjoyed by all; which encourages biodiversity and supports the development of a low carbon community, including local businesses, capable of adapting to the impacts of climate change. In particular, it aims to:

o Minimise carbon emissions and adapt to the impacts of climate change focussing on transport, business and homes. o Minimise domestic and commercial waste production and maximise reuse and recycling. o Protect and enhance our natural resources including air, soil and water to minimise the impacts of flooding, climate change and pollution o Improve the understanding, enjoyment and care for the natural and built environment o Reduce our dependence on fossil fuels.

Climate Change Strategy 2012/13 - 2015/16:-

4.4The Climate Change Strategy states that the Council ‘aims to influence and empower residents, community groups, schools and businesses in the Borough to help them to mitigate climate change by reducing their carbon emissions’. 4.5 In particular the strategy includes objectives to: o Reduce the carbon emissions from the Council’s buildings (including schools) o Support the communities and businesses of Bedford Borough to reduce energy consumption and mitigate climate change.

5(2) Resource Implications

4.6The Climate Change Fund budget 2012/13 is £100,000 and commitments to date total £80,007.66. Therefore funding is available to cover the application detailed in this report which is £11,988 which would bring the total committed 2012/13 to £91,995.66.

4.7The Climate Change Fund is revenue funded and therefore it is necessary to have all the works completed and invoices received by 31st March 2013.

4.8The Climate Change Fund was established to help communities in the Borough to reduce the use of fossil fuels, which will result in a reduction in carbon emissions and will promote and improve energy efficiency in the Borough.

Risk implications

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Climate Change Fund ProjectsReport 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Bedford

Search all
  1. Climate Change Fund ProjectsThis decision
  2. Health Impacts of Climate ChangeApproved
  3. Mayors Climate Change FundNoted
  4. The Mayor's Climate Change FundNoted
  5. Trees and the important role they play in combating climate change in the BoroughNoted
  6. Staff climate change trainingNoted

More from Bedford Sustainability Committee

All decisions
MeetingDecisionOutcome
28 Jan 2015 To confirm the Minutes of the meeting of the Sustainability Committee held on 12 November 2014 (copy previously circulated)Description of Decision That the Minutes of the meeting of the Sustainability Committee held on 12 November 2014 be c... Decided Open
28 Jan 2015 Water DeregulationThat the presentation on Water De-regulation be noted. CCEM Noted Open
28 Jan 2015 Water StrategyDescription of Decision That the be approved. Reasons for Decision ( i ) The will help the Council to reduce its annu... Approved Open
28 Jan 2015 Work Programme UpdateThat the progress report on the Committee’s work programme be noted. That further information on Biomass fuel pellets... Noted Open
9 Apr 2014 To confirm the Minutes of the meeting of the Sustainability Committee held on 29 January 2014Description of Decision : That the Minutes of the meeting of the Committee held on 29 January 2014 be confirmed. Reas... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies