2012/2013 Revenue Budget Update

Approved Executive 3 papers

Executive approved this item on Wednesday 13 February 2013. Below is the council's own wording, with the papers it was decided on.

Item97

Resolved

Description of Decision (1) That the forecast 2012/2013 revenue outturn position against the approved revenue budget, as shown in Appendix A to the report, the projected major variances with reasons for these variances and the action being taken to address the underlying issues, be acknowledged. (2) That the acceptance of the additional grant allocation of up to £382,000 in 2012/2013 from the Department of Health for investment in social care services, in recognition of winter pressures being experienced, be approved. (3) That Full Council be recommended to realign the balance of the previously approved revenue contingency in the sum of £1.552 million in 2012/2013 to meet the forecast cost pressure arising from the unforeseen and unexpected levels of demand for looked after children, as outlined in the report. Reason for Decision To receive the latest trends in respect of the 2012/2013 revenue budget and emerging budget issues that impact on the Council’s Medium Term Financial Strategy.
Word for word from the decision Bedford published for this meeting. Source: councillorsupport.bedford.gov.uk

Follow this further

Built from Bedford's papers

What the report saysPro

Report to Executive, 14 pages

Executive summary

To consider the latest trends in respect of the 2012/2013 revenue budget and emerging budget issues.

Recommendations

The Executive is requested to consider the report and, if satisfied, to:

(a) Acknowledge the forecast 2012/2013 revenue outturn position against the approved revenue budget shown in Appendix A, the projected major variances with reasons for these variances and the action being taken to address the underlying issues;

(b) Approve the acceptance of the additional grant allocation of up to £382,000 in 2012/2013 from the Department of Health for investment in social care services in recognition of winter pressures being experienced;

(c) Recommend Full Council to realign the balance of the previously approved revenue contingency in the sum of £1.552 million in 2012/2013 to meet the forecast cost pressure arising from the unforeseen and unexpected levels of demand for looked after children as outlined in the report.

Reason for recommendations

To advise the Executive of the latest trends in respect of the 2012/2013 revenue budget and emerging budget issues that impact on the Council’s Medium Term Financial Strategy.

rac5613 Revenue Budget Update 9(1) Executive 13 February 2013 4. Key Implications

4.1Legal Issues

The Council is required, by law, to set a balanced revenue budget each year which for 2012/2013 was approved by Full Council on 1 February 2012. The purpose of this report, in accordance with best financial management practice, is to advise the Executive of significant variations from that budget.

4.2Policy Issues

The Medium Term Financial Strategy (MTFS) states that, to ensure a continuously stable financial base for the provision of Council services and functions, the Council will ensure that annual ongoing General Fund revenue expenditure can be covered by annual income sources in each and every financial year. The MTFS requires regular reports to be submitted to the Executive in respect of budget trends and the report, therefore, provides a detailed update on the latest budget position and also identifies a number of emerging budget issues that will need to be kept under review.

The MTFS also requires that due regard is given to revenue budget forecasts and that any increase in the ongoing annual revenue budget (by way of use of the contingency provision or virement) will be subject to the expenditure being either legally unavoidable or considered affordable after taking into account:

 any forecast savings targets;  implications on Council Taxpayers in future years.

The MTFS will continue to be reviewed in light of the budget monitoring undertaken to date and refreshed given the emerging medium term pressures and further impacts upon the Council, including the implications from the 2013/2014 Finance Settlement.

A refreshed version of the MTFS is scheduled to be considered by the Executive at its meeting on 13 March 2013 in accordance with the requirement for an annual review.

4.3Resource Implications

The Council’s approved 2012/2013 gross General Fund Revenue Budget is £307 million and this is reduced by income from specific grants, subsidies, fees, charges and rents which can be subject to variation as well as fixed income sources such as commuted sums, reserves and provisions giving a net budget requirement of £126.028 million. This is financed as follows:

£million 2012/2013

Net Budget Requirement 126.028 Financed by: Formula Grant 51.157 Council Tax Yield 74.871

rac5613 Revenue Budget Update 9(2) Executive 13 February 2013 The gross 2012/2013 revenue budget is, therefore, dependant upon the receipt of a range of ring-fenced and other government grants (in addition to the Formula Grant) and these are summarised below:

£million 2012/2013

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2012/2013 Revenue Budget UpdateAppendix 1 pages Download
PDF
Item 9 rac5613: Revenue Budget Update 2012-2013Report 14 pages DownloadRead as text
PDF
Item 9 rac5613: Revenue Budget Update 2012-2013: Appendix AAppendix 6 pages Download

At this meeting

Whole meeting

On this subject at Bedford

Search all
  1. 2012/2013 Revenue Budget UpdateThis decision
  2. Revenue Budget Trends 2025/26Approved
  3. 2026/2027 revenue budget updateNoted
  4. General Fund Revenue Budget 2026/2027Approved
  5. 2024/25 Revenue and Capital Budget TrendsNoted
  6. General Fund Revenue Budget 2025/2026Approved

More from Bedford Executive

All decisions
MeetingDecisionOutcome
15 Jul 2026 Minutes of Previous MeetingDescription of Decision That the Minutes of the meeting of the Executive held on 3 June 2026 be confirmed. Reason for... Decided Open
15 Jul 2026 Local Government and Social Care Ombudsman Annual Review Letter 2025/2026Description of Decision That the Local Government and Social Care Ombudsman’s Annual Review letter for 2025/2026 for ... Noted Open
15 Jul 2026 RIPA Annual ReportDescription of Decision (1) That it be noted that, in the period 1 April 2025 to 31 March 2026, there were no applica... Noted Open
15 Jul 2026 Social Housing Allocations PolicyDescription of Decision (1) That the publication of the revised Bedford Borough (at Appendix A) on 1st September 2026... Approved Open
15 Jul 2026 Corporate Plan 2024-2028 Performance Report year-end 2025/2026Description of Decision That the latest performance as outlined within the Key Indictor Performance Report at Appendi... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies