Resolved
That the 2012/2013 audit progress report be noted and that updates be presented to future meetings of the Committee. External Auditors
Audit Committee noted this item on Wednesday 20 March 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
That the 2012/2013 audit progress report be noted and that updates be presented to future meetings of the Committee. External Auditors
\""
Bedford Borough Council Year ending 31 March 2013
Audit Progress Report
March 2013
2i] ERNST & YOUNG Audit Committee 8 March 2013 Bedford Borough Council
Borough Hall
Cauldwell Street
Bedford
MK42 9AP
Dear Sir
Audit progress report — 2012-13
We are pleased to attach our audit progress report.
This progress report summarises the work we have undertaken to date since our appointment as your auditor on 1 September 2012. The purpose of this is to provide the Audit Committee with an overview of the stage we have reached in your 2012-13 audit and ensure our audit is aligned with the Committee’s service expectations.
Our audit will be undertaken in accordance with the requirements of the Audit Commission Act 1998, the Code of Audit Practice, the Audit Commission Standing Guidance, auditing standards and other professional requirements.
We are presenting our audit plan to the Audit Committee this month. We are in the process of completing our walk throughs and tests of control and have continued to update our risk assessment. There are no new issues that we are required to communicate to you at this stage of our work.
We welcome the opportunity to discuss this report with you as well as understand whether there are other matters which you consider may influence our audit.
Yours faithfully
AP. tJest—
Mick West
Director
For and behalf of Ernst & Young LLP Enc
Ernst & Young |i Contents
1. Work completed 2. Timetable Appendix 1: Audit Progress. ...........ccccsseeseseeeseeeseeeeeseeeeeseeeeeeeesseeeeaseneesseeeeseeeeasenenesenensenees 4
Ernst & Young |i Work completed
Work completed
Meetings We have held a number of meetings as part of our ongoing audit process:
e 4 October 2012 — Meeting with Chief Executive and Assistant Director of Finance covering initial planning considerations.
e 28 November 2012 — Handover meeting with outgoing auditors to understand prior year issues, findings, control environment and significant risks.
e 28 November 2012 — Introductory meeting with the Chief Executive and Director of Finance and Corporate Services to discuss engagement team and outline on our audit approach.
e 8 March 2013 — Meeting with Chief Executive and Assistant Director of Finance to discuss the draft audit plan.
Interim visit
We are in the process of completing our walk throughs and some testing of controls, placing reliance on the work of internal audit where possible.
At this stage our work has not identified any issues that we need to bring to your attention as those charged with governance.
Value for money conclusion assessment
We are in the process of completing our initial risk assessment for our value for money conclusion work against the Audit Commission’s specified criteria and areas of focus. Once we have completed our risk assessment we will communicate to you any specific risks we have identified and any additional local risk based work we may need to undertake as a result.
Certification of claims and returns
We have not yet started certification work for 2012-13 claims or returns. We plan to start the work on your housing and council tax benefit subsidy claim in June 2013 and your national non-domestic rates return in July 2013.
Ernst & Young |2 Timetable
Timetable
Audit Committee timeline
We have set out below a timetable showing the key stages of the financial statements and value for money conclusion audit, and certification work, and the deliverables we have agreed to provide to you through the 2012-13 Audit Committee cycle.
We will provide reports to the Audit Committee throughout our audit process as outlined below. Where required, we will issue an interim report, summarising the findings from our audit at that stage. From time to time matters may arise that require immediate communication with the Audit Committee and we will discuss them with the Audit Committee Chair as appropriate.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Audit Progress Report: 2012/2013: Bedford Borough Council (Report of the External Auditors copy enclosed)Report | 7 pages | DownloadRead as text |
Follow Audit Committee at Bedford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | MinutesThat the of the meeting of the Committee held on 21 July 2026, be confirmed. Chair | Decided | Open |
| 9 Sep 2026 | KPMG: External Auditor - Draft Audit Results Report 2025/26 - Bedfordshire Pension FundRESOLVED That the Committee considered the draft Audit Results Report 2025/2026 for Bedfordshire Pension Fund issued ... | Noted | Open |
| 9 Sep 2026 | KPMG: Value For Money 2025/26 - VFM Risk Assessment Report - Bedford Borough CouncilRESOLVED That the Committee considered and were satisfied, to note the report. HOA | Noted | Open |
| 9 Sep 2026 | Internal Audit Plan Update 2026/27RESOLVED That the Committee considered the report and was satisfied to acknowledge the progress made to date against ... | Approved | Open |
| 9 Sep 2026 | Report on Fraud and Corruption 2025/26RESOLVED That the Committee considered the report, sought clarification, and noted, (a) The Council’s performance in ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.