Budget and Corporate Services Overview and Scrutiny Committee decided this item on Thursday 25 April 2013. Below is the council's own wording, with the papers it was decided on.
RESOLVED : i) That the Head of Economic Development and Economic Development Manager (Growth) be thanked for their attendance and update. ii) That the progress made to date in respect of the planned Borough wide broadband improvements, be acknowledged. Chair
Word for word from the decision Bedford published for this meeting.Source: councillorsupport.bedford.gov.uk
Report to Budget and Corporate Services Overview and Scrutiny Committee, 4 pages
Summary
This briefing provides an update on progress with the Borough Council’s broadband project since the last report to the Committee in October 2012.
Recommendations
1. To acknowledge the progress made to date in respect of planned Borough wide broadband improvements; and
2. That the Committee considers whether it has any recommendations to make.
Background
Members of the Committee may recall that the Council’s project is a partnership project with Central Bedfordshire and Milton Keynes Councils and that, for Bedford Borough’s part of the project, a combination of BDUK funding of £440,000 matched by Bedford Partnership Board funding of £440,000 is aiming to deliver 90% of Borough premises (residential and business) with access to Next Generation Access (NGA)/superfast broadband (>25 Mbps) and 100% having access to at least 2 Mbps.
Recent/Current Activity
1. Broadband Project Agreement and Management Arrangements
The three councils have finalised their formal collaboration arrangements covering, amongst other things, necessary project management and cost sharing arrangements and related legal matters for this complex project.
Overall project direction continues to come from the Joint Broadband Programme Board, comprising the portfolio leads of the three Councils (in the Borough Council’s case, the Mayor of Bedford Borough, Dave Hodgson) and BDUK.
6(1) The project is being taken forward by the Project Team which will be supported in the run up to, and during, delivery by a joint project administration person.
An Executive Decision is expected to be considered by the Mayor in May 2013 to approve contracting arrangements for delivery of the project.
2. Contractor Procurement
The procurement process is now well underway with Atkins providing advice and support. BDUK’s Checkpoints B0 and B1 have been successfully passed and, at the time of writing, the State Aid consultation process was in mid-stream (due to end on 22nd April). The State Aid consultation document can be viewed on the Council’s broadband web page (www.bedford.gov.uk/broadband) along with interactive maps of current and planned NGA and basic broadband provision – see example screen print at Appendix A. At the same time, initial supplier engagement is being undertaken and Invitation to Tender (ITT) documentation has been drafted and is being reviewed.
BT Openreach has identified that there will be additional modelling requirements needed to reflect the different levels of investment and coverage targets adopted by the 3 Local Authorities within our Broadband Partnership. This was possibly problematic in the light of the tight BDUK programming arrangements but a way forward has been identified.
Overall, the project is proceeding in line with our Project Plan as summarised below:-
- Issue final ITT in May 2013
- Supplier responses in July 2013
- Award Contract in August 2013
- Planning/Mobilisation in latter part of 2013
- Implementation in 2014 and 2015
3. Registering Demand
Residents and businesses continue to register their interest in faster broadband on the Council’s broadband web page. This is useful in that it helps to encourage broadband infrastructure providers to invest in Bedford Borough but also in its evidencing of specific local demand. Over 1,600 people have signed up so far, which is 500 more in the 6 months since the last Committee update.
6(2) 4. Broadband in New Developments
The Council has continued to work with the Borough’s main infrastructure suppliers and developers to encourage infrastructure provision for superfast broadband in larger new developments, with retrofitting to earlier phases as and when feasible, although investment decisions between suppliers and developers remain very slow to conclude.
5. Keeping Local Residents and Businesses Up-to-date
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Budget and Corporate Services Overview and Scrutiny Committee at Bedford and we tell you when its next papers are published, before the meeting rather than after it.
Member Finance Awareness Trainingi) That the briefing note, be noted. ii) That it be agreed that all Councillors be strongly recommended and encourage...
Record of Decisions of the ExecutiveRESOLVED : That it be noted that, as no Executive meetings have been held since the Committee’s last meeting, there w...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.