Description of Decision *That Full Council be recommended to approve: ( i ) that the date on which the levy comes into effect be 1 April 2014; (ii) the Charging Schedule in line with the recommendations of the independent examiner, as set out at Appendix A to the report; (iii) the Regulation123 list, as set out at Appendix B to the report; (iv) the Instalment Policy, as set out at Appendix C to the report; (v) the Exceptional Circumstances Statement, as set out at Appendix D to the report; (vi) that the Assistant Director (Planning, Strategic Transport & Housing) be given delegated authority to make minor editorial changes to the supporting text of the Charging Schedule and other documents in particular to reflect the impending changes to the Government regulations. Reason for Decision To implement the Community Infrastructure Levy (CIL) in the Borough that will enable the Council to charge the CIL on new development. This will enable the Council to obtain funding from a wider range of types and scale of developments and to pool this funding where appropriate to assist in delivery of the Council’s priorities. * Recommendations to Full Council are not available for call in.
Word for word from the decision Bedford published for this meeting.Source: councillorsupport.bedford.gov.uk
1.1Following the independent examination of the Community Infrastructure Levy (CIL) Draft Charging Schedule in November 2013 the Council has now received a positive Examiner’s Report (Appendix E). Consideration needs to be given to whether to approve the Charging Schedule and if so, the date on which the levy will come into effect.
1.2The Draft Charging Schedule was subject to two rounds of public consultation before approval by Executive on 10 July 2013 for submission for examination. The draft Regulation 123 list (a list of projects to which CIL may be applied), the draft Instalment Policy and the Council's intention to offer Exceptional Circumstances Relief were all part of the background evidence for the draft Charging Schedule and were also approved by Executive prior to submission.
1.3The next step is to implement the levy in the Borough and this report seeks approval of the Charging Schedule (Appendix A) which sets out the rates applying and charging zones, the Regulation 123 list (Appendix B) the Instalment Policy (Appendix C ) and the exceptional circumstances relief statement (Appendix D). This report also seeks agreement that the date on which CIL should be brought into force in the Borough will be 1 April 2014.
6(1) 2. Recommendations
2.1To consider and, if satisfied, to recommend that Full Council approve
(a) that the date on which the levy comes into effect be 1 April 2014 (b) the Charging Schedule in line with the recommendations of the independent examiner (Appendix A), (c) the Regulation 123 list (Appendix B) (d) the Instalment Policy (Appendix C) (e) the Exceptional Circumstances Statement (Appendix D) (f) Delegating authority to the Assistant Director (Planning, Strategic Transport & Housing) to make minor editorial changes to the supporting text of the Charging Schedule and other documents in particular to reflect the impending changes to the government regulations.
Reasons for recommendations
3.1To implement the Community Infrastructure Levy in the borough that will enable the Council to charge CIL on new development. This will enable it to obtain funding from a wider range of types and scale of developments and to pool this funding where appropriate to assist in delivery of the Council’s priorities.
4. Key Implications
4.1The Community Infrastructure Levy is the mechanism that councils are being encouraged to use for securing developer contributions towards provision of infrastructure to support growth. It is a tariff approach based on a flat-rate per square metre of new floorspace. The use of Section 106 agreements is to be scaled back so as only to cover site-specific mitigation and affordable housing. CIL is intended to complement rather than replace other funding streams. Its main advantages compared with planning obligations in Section106 agreements under the Town and Country Planning Act 1990 (S106 agreements) are that:
• It is a fixed, non-negotiable charge and is therefore transparent and predictable which can be applied (subject to viability considerations) to all new developments that cause pressures on infrastructure, not just the larger schemes. • It obviates the need for the negotiation of legal agreements, a process which sometimes delays the grant of planning permission, • It can be spent on a wide array of infrastructure that supports the development of the borough, and, unlike section 106 provision, there does not need to be a direct geographical or functional relationship with the proposed development
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Social Housing Allocations PolicyDescription of Decision (1) That the publication of the revised Bedford Borough (at Appendix A) on 1st September 2026...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.