CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Bedford Borough Council
Sustainability Committee, Wednesday 29 January 2014 at 6.30pm

To confirm the Minutes of the meeting of the Sustainability Committee held on 13 November 2013 (copy previously circulated)

Decided Committee 1 paper

Sustainability Committee decided this item on Wednesday 29 January 2014. Below is the council's own wording, with the papers it was decided on.

Item16

Resolved

Description of That the Minutes of the meeting of the Sustainability Committee held on 13 November 2013 be confirmed. Reason for Decision There is a legal requirement for the Minutes of the previous meeting to be considered before being confirmed as an accurate record.
Word for word from the decision Bedford published for this meeting. Source: councillorsupport.bedford.gov.uk

Follow this further

Built from Bedford's papers

What the report saysPro

Report to Sustainability Committee, 6 pages

Reason for decision

There is a legal requirement for the Minutes of the previous meeting to be considered before being confirmed as an accurate record.

10. DISCLOSURE OF LOCAL AND/OR DISCLOSABLE PECUNIARY INTEREST

Item and Minute Member Nature of Interest Present or Absent during discussion of the Number Disclosing an specified part of the item Interest Item No. 5 Councillor Local interest being a Member of Brickhill Present Minute No. 11 Royden Parish Council. .

3(1) 13 November 2013

11. CLIMATE CHANGE FUND PROJECTS

The Climate Change Officer introduced her report which provided the Committee with details of two applications that requested funding from the Climate Change Fund from Brickhill Parish Council and Brickhill Lower School.

During consideration of the report, Members were informed that a number of other projects were expected to emerge in due course. They were also pleased to note that the lighting along The Embankment would shortly be replaced with low energy bulbs.

RESOLVED:

That funding be approved from the Climate Change Fund for

Brickhill Parish Council‟s application to fund 50% of the cost of an Energy Performance Survey and Certificate in the sum of £125.00 for the reasons set out in the report; and

Brickhill Lower School‟s application to replace the single glazed windows in the main hall and classrooms of the school with double glazed windows in the sum of £10,875 for the reasons set out in the report.

(i) To allow one further project and one Energy Performance Survey and Certificate to be funded which will contribute to reducing the overall carbon emissions in the Borough.

(ii) The applications are to replace single glazed windows with double glazed windows in the school and for an Energy Performance Survey and Certificate to be carried out at the Community Centre.

(iii) The Council is committed to encouraging all sectors in the local community to take the opportunity to reduce their own carbon emissions.

(iv) By helping local community groups and schools improve the energy efficiency of their community buildings and install renewable energy technologies through the implementation of the fund they will be able to reduce their energy consumption and carbon emissions which will help the Council contribute to the Government‟s carbon reduction targets.

3(2) 13 November 2013

(Note: Councillor Royden, having declared a local interest in this item being a member of Brickhill Parish Council, remained in the meeting during discussion of the item)

12. RE:FIT ENERGY PERFORMANCE CONTRACT UPDATE

The Head of Environment introduced his briefing note which provided the Committee with an update on the details of the tranche 2 Investment Grade Proposals which formed part of the Energy Performance Contract which the Council entered into under the RE:FIT framework.

Members noted that Bromham Mill was one of the initial ten properties which were deferred into tranche 2 and that, following further investigation due to the complex nature of the project and the payback period being outside of the ten years period, this project had been removed from the programme. A full list of all the properties left in the programme was set out in the report together with the Energy Conservation Measure (ECM) for each property detailed in Appendix 1 to the report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
To confirm the Minutes of the meeting of the Sustainability Committee held on 13 November 2013 (copy previously circulated)Minutes 6 pages DownloadRead as text

At this meeting

Whole meeting
16To confirm the Minutes of the meeting of the Sustainability Committee held on 13 November 2013 (copy previously circulated)This decision
18Climate Change Fund ProjectsApproved 19Affordable Warmth Strategy and Action PlanApproved 20Work Programme updateNoted

On this subject at Bedford

Search all
  1. To confirm the Minutes of the meeting of the Sustainability Committee held on 13 November 2013 (copy previously circulated)This decision
  2. To Confirm the Minutes of the meetings of the Committee held on the 5 February 2026 and 13 May 2026 (copies enclosed)Decided
  3. To confirm the Minutes of the meeting of the Board held on 23 October 2025Approved
  4. To confirm the Minutes of the meeting of the Board held on 6 February 2025Approved
  5. To confirm the Minutes of the meeting held on 25 November 2024 (copy enclosed)Decided
  6. To confirm the Minutes of the meeting of the Committee held on 7 November 2024Decided

More from Bedford Sustainability Committee

All decisions
MeetingDecisionOutcome
28 Jan 2015 To confirm the Minutes of the meeting of the Sustainability Committee held on 12 November 2014 (copy previously circulated)Description of Decision That the Minutes of the meeting of the Sustainability Committee held on 12 November 2014 be c... Decided Open
28 Jan 2015 Water DeregulationThat the presentation on Water De-regulation be noted. CCEM Noted Open
28 Jan 2015 Water StrategyDescription of Decision That the be approved. Reasons for Decision ( i ) The will help the Council to reduce its annu... Approved Open
28 Jan 2015 Work Programme UpdateThat the progress report on the Committee’s work programme be noted. That further information on Biomass fuel pellets... Noted Open
9 Apr 2014 To confirm the Minutes of the meeting of the Sustainability Committee held on 29 January 2014Description of Decision : That the Minutes of the meeting of the Committee held on 29 January 2014 be confirmed. Reas... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies