Description of Decision (1) That the concept of the Digital Operating Model as summarised in Appendix A (detailed in Appendices B, C and D) to the report be approved and that the use of the Transformation Reserve and Capital Financing to fund the Implementation Phase, be approved. (2) That it be acknowledged that a report will be submitted to the General Purposes Committee on 7 March 2017 regarding the Senior Management structure of the Council. Reason for Decision To enable consideration to be given to the Design Phase of the Digital Operating Model and to note the way forward.
Word for word from the decision Bedford published for this meeting.Source: councillorsupport.bedford.gov.uk
To provide to the Executive the “Design Phase” of the Digital Operating Model as developed with PwC and to determine the way forward.
Recommendations
The Executive is invited to consider the report and to if satisfied to:
(a) approve the concept of the Digital Operating Model as summarised in Appendix A (detailed in Appendices B, C and D) and in so doing approve the use of the Transformation Reserve and Capital Financing to fund the Implementation Phase;
(b) acknowledge that subject to (a) above being approved, a report will be submitted to the General Purposes Committee on 7 March 2017 regarding the Senior Management structure of the Council.
Reasons for recommendations
To enable the Executive to consider the Design Phase of the Digital Operating Model and to provide the Executive with the way forward.
4. Key Implications
(a) Legal/Policy Issues
The Council has to set a balanced budget by law and as such it is critical that all aspects of expenditure are scrutinised. Given the significant financial pressures facing the Council (see Resource Implications below) the Executive at its meeting on 7 July 2016 6(1) Reports/2017/Executive/003 je – 22 February 2017 - DOM (Minute No 18) approved a Business Transformation Programme for the next three years and incorporated into this was the development of a Digital Operating Model. The purpose of this report is to enable the Executive to receive the report on the Design Phase of the Digital Operating Model and for the Executive to agree the way forward.
(b) Resource Implications
The Council’s Medium Term Financial Strategy approved by Council on 12 October 2016 identified the need to make savings of £27.5 million over the period 2017/2021. In addition, the Council, through its Efficiency Plan as approved by Full Council on 12 October 2016, identified a saving of £10.3 million from a Digital Operating Model. The Executive Summary report attached at Appendix A, with further details in Appendix C, identifies a saving range of £10 to £11 million and thus it is in line with the original case for change considered by Executive on 7 July 2016. Given the level of savings needed over the medium term, then unless the Council is to embark on savage service cuts, there is no other option available.
The implementation costs are shown in the details section of this report.
(c) Risk Implications
If the Executive accept the recommendation and move to the Implementation Stage, there will be risks during the delivery and these can be summarised as:
savings not materialising for unforeseen reasons; information technology not delivering the savings or not being delivered on time; key staff not being available.
These risks are mitigated by continuing to engage external partners to work alongside the Council’s Project Management Office in delivering the project, ie they have a vested interest to ensure that savings they have identified and delivered in terms of quantum are in accordance with their proposed delivery timescale. Specific risks together with mitigation are detailed in the Implementation Plan at Appendix D.
(d) Environmental Implications
None arising from this report.
6(2) Reports/2017/Executive/003 je – 22 February 2017 - DOM (e) Equalities Impact
All changes to staffing will be delivered in accordance with the Council’s staffing policies. An Equality Analysis has been undertaken and this has identified that the proposed implementation of the Council’s transformation programme is likely to have a positive impact arising from the principles developed during the ‘design phase’ and the inclusion of accessibility as key element of the digital principles. As each element of the programme is developed more detailed equality analysis will be undertaken.
5. Details
(a) Background
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Social Housing Allocations PolicyDescription of Decision (1) That the publication of the revised Bedford Borough (at Appendix A) on 1st September 2026...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.