Briefing Note
From: Paul Pace, Head of Environment Services
To: Environment and Sustainable Communities Overview and Scrutiny Committee
Date: 18 May 2017
Subject: Moor Lane Skate Track Update on Delivery.
1 Executive Summary 1.1 This briefing report has been requested by the Environment and Sustainable Communities Overview and Scrutiny Committee to provide information on progress with the delivery of the Moor Lane Skate Track.
2 Background 2.1 Kingsbrook and Cauldwell Big Local approached the Council regarding their desire to have a new skate park installed in the Moor Lane open space in Cauldwell.
2.2The Kingsbrook and Cauldwell Big Local are an externally funded trust whose mission is ‘to enable residents to make their communities and their areas even better places in which to live’. The trust helps residents develop and use their skills and confidence to identify what matters most to them, and to take action to change things for the better, now and in the future. The trust will fund projects supported by residents in order to deliver sustainable change, maximise impact and make the best use of scarce resources.
2.3Previously there was a small steel ramped skate area on the site which was removed to provide space for the larger and more comprehensive concrete skate area.
1 2.4 A skating event was organized jointly with Bedford Sports Development (Just Turn Up) in June 2015. This was successful with over 50 skaters attending. As a result of the event the skater group liaised with Gravity, a company specialising in the design and construction of skate parks, and worked extensively with them to design a skate-park. The resultant design for a completely new skate park for Moor Lane (which would be located next to the existing MUGA) was costed at £100,000. The proposed appointment of Gravity as the preferred contractor has been determined by Big Local. This followed a competitive tendering process in collaboration with Wootton Parish Council for a similar project implemented in 2015. Big Local contributed more than 80% of the capital cost. Bedford Borough Council’s procurement officers were satisfied that the Big Local’s preferred contractor could be appointed on a fixed price contract on condition they meet technical and financial tests.
2.5The project is part of the Council’s Section 106 proposals; the £20,000 contribution was from receipts from the Telecom House St Johns Street redevelopment. Officers have been working with Big Local to improve the facilities on the recreational land off Moor Lane. Big Local carried out a consultation in 2015 with young people living in the area, pupils of the local Bedford Academy and users of the existing sports court and small skate facility. As a result of the consultation design proposals have been developed and a fixed price contract negotiated with the preferred contractor Gravity. The total contract cost of £105,000. (£5,000 of this is retained for contingencies) was funded from Section 106 funding (£20,000) and £85,000 grant funding from Big Local.
3 Works 3.1 Works started on site in November 2016 and achieved Practical Completion on 3 January 2017 following a post installation inspection by RoSPA. The council has been undertaking maintenance of the facility from this date.
3.2As part of the project the council laid grass turfing of the central part of the site to limit the incidents of mud being transferred to the site, and has also installed a litter bin.
3.3During the works some damage was caused as a result of unauthorised access to the contractor’s equipment. Damage to the adjacent grassed area, footpath and play area fencing has been repaired. One item of damaged play equipment is to be repaired during the defects period.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Skate Park at Moor Lane, BedfordReport | 5 pages | DownloadRead as text |
Follow Environment and Sustainable Communities Overview and Scrutiny Committee at Bedford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2026 | Previous MinutesRESOLVED That the Minutes of the meeting of the Committee held on the 18 June 2026 be confirmed. Chair | Decided | Open |
| 16 Jul 2026 | Local Plan 2050RESOLVED That the Committee noted the update. HCPI&ST | Noted | Open |
| 16 Jul 2026 | Executive DecisionsRESOLVED 1. The Committee noted that there were no meetings of Executive prior to the publication of the agenda, deci... | Noted | Open |
| 16 Jul 2026 | Notice of Forthcoming Decisions to be taken by the ExecutiveThat the Notice of Forthcoming Decisions for the period 1 August 2026 to 30 November 2026 be received. SDSO | Decided | Open |
| 16 Jul 2026 | Committee Work ProgrammeThat an item on Biddenham (Great Ouse Way) Country Park be added to the Committee’s Work Programme. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.