RESOLVED : That the report be considered and that the allocation of the projected underspend be approved as follows: i) £0.525 million to Average Speed Cameras ii) £0.170 million to fund Bin Replacement within the Capital Programme iii) up to £1.0 million additional funding to be added to the Highways (BBC Funded) Capital Programme.
Word for word from the decision Bedford published for this meeting.Source: councillorsupport.bedford.gov.uk
To advise Full Council of the outcome of the Executive’s consideration of the 2017/2018 Revenue Trends and to consider a recommendation to allocate the projected underspend.
Recommendation
Full Council is requested to consider the report and, if satisfied, to approve the allocation of the projected underspend as follows: i) £0.525 million to Average Speed Cameras ii) £0.170 million to fund Bin Replacement within the Capital Programme iii) up to £1.0 million additional funding to be added to the Highways (BBC Funded) Capital Programme.
Reason for recommendation
To receive a recommendation from the Executive concerning the allocation of the projected revenue budget underspend.
4. Key Implications
4.1Legal Issues
The Council is required, by law, to set a balanced revenue budget each year which for 2017/2018 was approved by Full Council on 1 February 2017. The purpose of this report, in accordance with best financial management practice, is to advise of significant variations from that budget. 12.1(1) 4.2 Policy Issues
The Medium Term Financial Strategy (MTFS) states that, to ensure a continuously stable financial base for the provision of Council services and functions, the Council will ensure that annual ongoing General Fund revenue expenditure can be covered by annual income sources in each financial year. The MTFS requires regular reports to be submitted to the Executive in respect of budget trends and the report, therefore, provides an update on the latest budget position and also identifies a number of emerging budget issues that will need to be monitored during the remainder of 2017/2018.
4.3Resource Implications (i) Revenue Budget
The Council’s approved 2017/2018 gross General Fund Revenue Budget reported to Full Council on 1 February 2017 totalled £358.446 million, this is reduced through specific grants, subsidies, fees, charges, rents, fixed income sources such as commuted sums and the planned use of Reserves resulting in a net budget requirement of £128.342 million.
In year, the Council has received £1.733 million capital grant to support the delivery of 30 hours free childcare for working parents for 3-4 year olds which has a net nil effect. The Department for Transport allocated £0.153 million Capital Grant in relation to the Pothole Action Fund; the Capital Grant is to be spend prior to September 2018.
The net budget requirement is financed as follows:
2017/2018 Original £million Net Budget Requirement 128.342 Financed by: Revenue Support Grant 14.595 Local Business Rates 31.290 Council Tax Yield 82.457
A review of forecast expenditure and income has highlighted that there are variations compared to the approved budget and, as such, these variations are set out in this report.
12.1(2) 4.4 Risk Implications
When the Council considers each revenue service and function budget it is important that endeavours are made to identify potential risks. Inevitably, during the course of the financial year, some of these risks will occur and impact on the budget by either requiring further expenditure or by reducing the Council’s budgeted income.
The budget is monitored on a monthly basis to identify risks and take action to mitigate the risks when they arise. The Council holds a contingency with regard to budgetary risk in year, together with a range of Reserves to deal with specific issues.
4.5Environmental Implications
There are no environmental implications arising directly from the report.
4.6Equality Analysis
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Report of the mayor/executive membersThat the use of the Special Urgency Procedure be noted. (2) Membership of Executive and Changes to Executive Committe...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.